

Question 27 At the end of June, the manager of the B.C. manufacturing plant was provided...
Question:
Waterways Continuing Problem 12 At the end of June the manager of the B.C. manufacturing plant was provided with the following variance analysis report: Favourable (F)/ Unfavourable (U) Budget Actual Variance Production in units 310,000 323,000 13,000 Production costs: Direct material $(11,781) (25,440) (4,538) $737,800 $749,581 U Direct labour Variable overhead costs Fixed overhead costs 1,395,000 131,750 147,250 1,420,440 U 136,288 U 139,870 7,380 F Total production costs $(34,379) $2,411,800 $2,446,179 U The manager immediately called the production supervisor,...
Waterways Continuing Problem 12
At the end of June the manager of the B.C. manufacturing plant
was provided with the following variance analysis report:
Budget
Actual
Variance
Favourable (F)/
Unfavourable (U)
Production in units
332,000
347,000
15,000
F
Production costs:
Direct material
$996,000
$1,017,940
$(21,940)
U
Direct labour
1,411,000
1,442,700
(31,700)
U
Variable overhead costs
166,000
172,957
(6,957)
U
Fixed overhead costs
174,300
168,620
5,680
F
Total production costs
$2,747,300
$2,802,217
$(54,917)
U
The manager immediately called the production supervisor,...
ABC Manufacturing Company's costing system has two direct cost categories: direct materials and direct manufacturing labour. Manufacturing overhead (both variable and fixed) is allocated to products on the basis of standard DMLH At the beginning of 2018, ABC adopted the following standards for its manufacturing costs: Input Cost per Output Unit S 15 75 3 kg at $5 per kg 5 hours at $15 per hour Direct materials Direct manufacturing labour Manufacturing overhead: Variable Fixed Standard manufacturing cost per output...
a) The Walter Group provides the following data for June 2019 when 15,000 units were manufactured. Standard Material cost (per Unit) 8.50kg @ $7.50 per Kg. Actual Material cost (Per Unit) 6.75Kg @ $13.5 per Kg. Standard Labour cost (Per Unit) 5.5hrs @ $15 per hour Actual Labour cost (Per Unit) 6.5hrs @ $12.2 per hour Calculate the following: 1. Direct Material Variance 2. Direct Material Quantity/Usage Variance 3. Total Material Cost Variance 4. Direct Labour rate Variance 5. Direct...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $9.00 per kg Direct labour: 3 hours at $15 per hour Variable overhead: 3 hours at $5 per hour $ 54.00 45.00 15.00 Total standard cost per unit $ 114.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $8.00 per kg $ 48.00 Direct labour: 4 hours at $13 per hour 52.00 Variable overhead: 4 hours at $5 per hour 20.00 Total standard cost per unit $ 120.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 5 kg at $9.00 per kg $ 45.00 Direct labour: 3 hours at $14 per hour 42.00 Variable overhead: 3 hours at $9 per hour 27.00 Total standard cost per unit $ 114.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 4 kg at $9.00 per kg $ 36.00 Direct labour: 3 hours at $12 per hour 36.00 Variable overhead: 3 hours at $8 per hour 24.00 Total standard cost per unit $ 96.00 The company planned to produce and sell 28,000 units in March. However, during March the company actually produced and...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $8.00 per kg $ 48.00 Direct labour: 4 hours at $13 per hour 52.00 Variable overhead: 4 hours at $5 per hour 20.00 Total standard cost per unit $ 120.00 The company planned to produce and sell 20,000 units in March. However, during March the company actually produced and...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: 55.00 36.00 Direct materials: 5 $ kg at $11.00 per kg Direct labour: 3 hours at $12 per hour Variable overhead: 3 hours at $7 per hour 21.00 $ 112.00 Total standard cost per unit The company planned to produce and sell The company planned to produce and sell 21,000 units in March. However,...