Order size =100
Shaping machines = S/U= 1 hour, run time = 1 min/piece
Pickling machine = one tank having a load of 200 units in each 4 hour
Packing= there are 4 individuals each having the production rate of 100/4 =25 units/hr
For shaping department =
Number of machines =3
S/U= 1 hr
RT = 1 min/piece
Time per batch =1+100/60 =2.67hr
Production =(100/2.67)*3 =112.5 piece/hr
For pickling department =
RT = 4hr/batch
Time per batch =4 hour
Production =200/4=50 piece/hr
For packing department =
Number of individuals =4
RT = 25 piece/hr/individual
Time per batch =1hr
Production =4*25=100 price hr
So the botleneck station of pickling department = with production rate of 50 piece/hr
Please provide the answer and explanation. Thanks. 7. Maruchecks makeshift manufacturing facility had three departments: shaping,...