Jurgen Knudsen has been hired to provide industry expertise to Henrik Sandell, CFA, an analyst for a pension plan managing a global large-cap fund internally. Sandell is concerned about one of the funds larger holdings, auto parts manufacturer Kruspa AB. Kruspa currently operates in 80 countries, with the previous years global revenues at 5.6 billion. Recently, Kruspas CFO announced plans for expansion into China. Sandell worries that this expansion will change the Additional information: 4.82% 4.25% 0.3 900 million 2.4 billion Equity risk premium, Sweden Risk-free rate of interest, Sweden Industry debt-to-equity ratio Market value of Kruspas debt Market value of Kruspas equity Kruspas equity beta Kruspas before-tax cost of debt China credit A2 country risk premium Corporate tax rate Interest payments each companys risk profile and wonders if he should recommend a sale of the position. Sandell provides Knudsen with the basic information. Kruspas global annual free cash flow to the firm is 500 million and earnings are 400 million. Sandell estimates that tt Kruas atter- tax free cash flow to the firm on the China project for next three years is, respectively, 48 million, 52 million, and 54.4 million. Kruspa recently announced a dividend of 4.00 per ts that Knudsen ignore possible currency the Chinese plant to sell only to customers within China for the first Knudsen is asked to evaluate Kruspas planned financing of the required 100 million with a 80 public offering of 10-year debt in Sweden and the remainder with an cash flow will level off f at a 2 percent rate of growth. Sandell also estimates 2 9.25% I .8896 375% Level share of stock. For the initial analysis, Sandell reques uctuations. FHe expects three years. ycar equity offering.

As part of the sensitivity analysis of the effect of the new project on the company’s cost of capital, Sandell is estimating the cost of equity of the China project considering that the China project requires a country equity premium to capture the risk of the project. What is the cost of equity for the project taking into account the country risk? USE THE FOLLOWING FORMULA TO CALCULATE IT:re=risk free rate+\beta _{project}(Equity risk premium}-risk free rate)+Country risk premium

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Project Beta = Equity beta x (1 + (1 - tax) x Debt / Equity)

= 1.3 x (1 + (1 - 37.5%) x 900 / 2400)

= 1.60

Cost of equity = Rf + beta x ERP + CRP

= 4.25% + 1.60 x 4.82% + 1.88%

= 13.86%

Add a comment
Know the answer?
Add Answer to:
As part of the sensitivity analysis of the effect of the new project on the company’s...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Jürgen Knudsen has been hired to provide industry expertise to Henrik Sandell, CFA, an analyst for a pension plan...

    Jürgen Knudsen has been hired to provide industry expertise to Henrik Sandell, CFA, an analyst for a pension plan managing a global large-cap fund internally. Sandell is concerned about one of the fund's larger holdings, auto parts manufacturer Kruspa AB, Kruspa currently operates in 80 countries, with the previous year's global revenues at €5.6 billion. Financial information: market risk premium, Sweden 4.82 percent 4.25 percent Risk-free rate of interest, Sweden Industry debt-to-equity ratio 0.3 Market value of Kruspa's debt €900...

  • Blue Angel, Inc., a private firm in the holiday gift industry, is considering a new project....

    Blue Angel, Inc., a private firm in the holiday gift industry, is considering a new project. The company currently has a target debt–equity ratio of .45, but the industry target debt–equity ratio is .40. The industry average beta is 1.20. The market risk premium is 8 percent, and the risk-free rate is 6 percent. Assume all companies in this industry can issue debt at the risk-free rate. The corporate tax rate is 40 percent. The project requires an initial outlay...

  • Blue Angel, Inc., a private firm in the holiday gift industry, is considering a new project....

    Blue Angel, Inc., a private firm in the holiday gift industry, is considering a new project. The company currently has a target debt–equity ratio of .40, but the industry target debt–equity ratio is .35. The industry average beta is 1.40. The market risk premium is 7 percent, and the risk-free rate is 5 percent. Assume all companies in this industry can issue debt at the risk-free rate. The corporate tax rate is 34 percent. The project requires an initial outlay...

  • Blue Angel, Inc., a private firm in the holiday gift industry, is considering a new project....

    Blue Angel, Inc., a private firm in the holiday gift industry, is considering a new project. The company currently has a target debt-equity ratio of .45, but the industry target debt-equity ratio is .50. The industry average beta is 1.10. The market risk premium is 6.9 percent and the risk-free rate is 4.5 percent. Assume all companies in this industry can issue debt at the risk-free rate. The corporate tax rate is 23 percent. The project requires an initial outlay...

  • Blue Angel, Inc., a private firm in the holiday gift industry, is considering a new project....

    Blue Angel, Inc., a private firm in the holiday gift industry, is considering a new project. The company currently has a target debt-equity ratio of .40, but the industry target debt-equity ratio is .35. The industry average beta is 1.05. The market risk premium is 6.2 percent and the risk-free rate is 4.6 percent. Assume all companies in this industry can issue debt at the risk-free rate. The corporate tax rate is 24 percent. The project requires an initial outlay...

  • Blue Angel, Inc., a private firm in the holiday gift industry, is considering a new project....

    Blue Angel, Inc., a private firm in the holiday gift industry, is considering a new project. The company currently has a target debt–equity ratio of .35, but the industry target debt–equity ratio is .30. The industry average beta is 1.90. The market risk premium is 7 percent, and the risk-free rate is 5 percent. Assume all companies in this industry can issue debt at the risk-free rate. The corporate tax rate is 34 percent. The project requires an initial outlay...

  • Blue Angel, Inc., a private firm in the holiday gift industry, is considering a new project....

    Blue Angel, Inc., a private firm in the holiday gift industry, is considering a new project. The company currently has a target debt-equity ratio of .35, but the industry target debt-equity ratio is .30. The industry average beta is 1.90. The market risk premium is 6 percent, and the risk-free rate is 4 percent. Assume all companies in this industry can issue debt at the risk-free rate. The corporate tax rate is 34 percent. The project requires an initial outlay...

  • Blue Angel, Inc., a private firm in the holiday gift industry, is considering a new project....

    Blue Angel, Inc., a private firm in the holiday gift industry, is considering a new project. The company currently has a target debt-equity ratio of 40, but the industry target debt-equity ratio is 35. The industry average beta is 1.40. The market risk premium is 7 percent, and the risk-free rate is 5 percent. Assume all companies in this industry can issue debt at the risk-free rate. The corporate tax rate is 34 percent. The project requires an initial outlay...

  • Blue Angel, Inc., a private firm in the holiday gift industry, is considering a new project. The company currently has a...

    Blue Angel, Inc., a private firm in the holiday gift industry, is considering a new project. The company currently has a target debt–equity ratio of .45, but the industry target debt–equity ratio is .40. The industry average beta is 1.20. The market risk premium is 8 percent, and the risk-free rate is 6 percent. Assume all companies in this industry can issue debt at the risk-free rate. The corporate tax rate is 40 percent. The project requires an initial outlay...

  • Bil-A-Bong Enterprises is considering taking on a new project. The project itself requires a net investment...

    Bil-A-Bong Enterprises is considering taking on a new project. The project itself requires a net investment of $5 million and is expected to generate net earnings of $1 million per year growing at 2% in perpetuity. The object of the proposed project is to make snowboards. Swoosh, the dominant player in the industry, is a single product company, making snowboards exclusively. Swoosh is all-equity financed. It has a beta of 0.75. The risk-free rate is 10% and the market risk...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT