1. A product has a market estimate of 97,000 components and requires three processing steps (turning, milling, and drilling) having scrap estimates of P1 = 0.04, P2 = 0.01, and P3 = 0.03. If each component’s cycle is 3.15 minutes, Determine:
2. Given below is a worksheet developed from an activity relationship diagram of a company’s departments. Use the information to develop the dimensionless block diagram that depicts maximum efficiency for the company’s operations. Your diagram must show direction of flow.
|
Dept. |
A |
E |
I |
O |
U |
X |
|
01 |
3,5 |
2.4 |
6. |
7 |
8 |
|
|
02 |
1,3,4 |
5,7,8 |
6 |
|||
|
03 |
1,5 |
2, |
4,6, 7 |
8 |
||
|
04 |
7 |
1,2,6 |
3,5 |
8 |
||
|
05 |
1,3,6 |
2, 4 |
7,8 |
|||
|
06 |
5 |
4 |
1, 3 |
2,7,8 |
||
|
07 |
4 |
2, 3, |
6, |
5,1,8 |
||
|
08 |
2 |
3,6, |
4,5,7 |
1 |
1.
a) Market estimate = 97,000 units
Amount needed at beginning of P3 = 97000/(1-0.03) = 100000
Amount needed at beginning of P2 = 100000/(1-0.01) = 101010
Amount needed at beginning of P1 = 101010/(1-0.04) = 105219
Amount needed to produce the market-estimaed units = 105,219
b) Standard time = 3.15/(1-12%) = 3.58 minutes
Number of workers required = 97000*3.58/(8*60) = 724 workers
1. A product has a market estimate of 97,000 components and requires three processing steps (turning,...