Question
hi can you solve and explain this Q?
Qs: Consider the project of PERT Network in the following table. Activity (a, m, b) Activity (a, m, b) (5,6, 8) (1,3,4) (2, 4
0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
hi can you solve and explain this Q? Qs: Consider the project of PERT Network in...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Construct a Gantt chart and project network for the following set of activities, compute the length of each path in the network, and indicate the critical path: Activity Activity Predecessor Time (months) 1 ___ 4

    . Construct a Gantt chart and project network for the following set of activities, compute the length of each path in the network, and indicate the critical path: Activity Activity Predecessor Time (months) 1 ___ 4 2 ___ 7 3 1 8 4 1 3 5 2 9 6 3 5 7 3 2 8 4,5,6 6 9 2 5

  • Use a PERT network to establish the expected duration for the project described in the table...

    Use a PERT network to establish the expected duration for the project described in the table below:    (SHOW the PERT NETWORK) Activity Predecessors Duration a        m       b Exp. Duration Var. Crash Week 1 Crash Week 2 A - 3 6 9 700 100 B A 6 7 14 600 200 C A 4 6 14 400         600 D B, C 4 6 8 200                             600 E B, C 6 9 12 400 300 F C 4 6 14...

  • NETWORK: PERT 4 - Consider the following table: ACTIVITY PREC. ACT. TIME ESTIMATES tml - 2...

    NETWORK: PERT 4 - Consider the following table: ACTIVITY PREC. ACT. TIME ESTIMATES tml - 2 (days) tp c D, E 1) Construct a PERT network. [NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.) 2) By using ES, EF, LF, LS, find the slack of each activity and the critical path. 3) Find the completion time (x) and the standard deviation (6) for the project-...

  • PART I: PERT Consider the following table: ACTIVITY      PREC. ACT.              TIME ESTIMATES     (days)       &n

    PART I: PERT Consider the following table: ACTIVITY      PREC. ACT.              TIME ESTIMATES     (days)         to                       tml                 tp                       te     A                      ---                           2                      3                      4                          B                      A                            2                      4                      6     C                      A                            4                      6                      8     D                      A                            4                      5                      6     E                       B                            6                      7                      8     F                       D                            1                      3                      5     G                 E, C, F                        3                      5                      7 1.   Construct a PERT network. (20 points) [NOTE: This...

  • Consider the following network for a small maintenance project (all times are in days). [7 Marks]...

    Consider the following network for a small maintenance project (all times are in days). [7 Marks] Activity Immediate Predecessor [s] Optimistic Time Most Likely Time Pessimistic Time A - 2 3 4              B - 5 6 7 C - 5 6 7 D A 3 4 5 E A 2 3 4 F C 3 4 5 G C 8 10 16 H B, E, F 5 6 7 I B, E, F 7 11 15 J B, E,...

  • Pert project method Activity Predecessors A group 5 optimistic Most likely Pessimistic Expected Variance a m...

    Pert project method Activity Predecessors A group 5 optimistic Most likely Pessimistic Expected Variance a m b Time (t) o 2 3 2 1 B с D NWN mlm A 1 A,B 2 4 1 6 7 9 F 1 с с DE F,G 4 2 5 3 G 4 12 H 2 4 From the table above find the flowing answers. 1. Construct the project Network 2. Find the expected duration and Variance of each activity 3. Find the...

  • A partially solved PERT problem is detailed in the table below. Times are given in weeks....

    A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Preceding Optimistic Time Probable Time Pessimistic Time Expected Time Variance A -- 7 9 14 1.361 B A 2 2 8 0 C A 8 12 16 0 D A 3 5 10 1.361 E B 4 6 8 0 F B 6 8 10 0 G C, F 2 3 4 0 H D 2 2 8 1.000 I H 6 8...

  • Microsoft Project Assignment Description A system development project has been defined to contain the following list of...

    Microsoft Project Assignment Description A system development project has been defined to contain the following list of activities along with their estimated times for completion. The project will start on 5/1/2019. Project Data Provided: Activity ID Activity Name Days Predecessors Optimistic(O) Realistic(R) Pessimistic(P) 1 Gather Requirement 1 2 3 2 Analyze processes 1 2 6 1 3 Define DFDs 0.5 1 1.5 2 4 Design Processes 2 7 12 2 5 Design database 4 7 22 3 6 Design UI...

  • If the contracted duration for a project with the following network is 120 days, what is the prob...

    If the contracted duration for a project with the following network is 120 days, what is the probability (in percent) of meeting the schedule based on PERT analysis? Then, assume that the owner delays the start by 5 days while keeping the end date as originally scheduled. What is the probability (in percent) that the project will still finish at the originally scheduled completion date? The requested probabilities should be determined based on the entire network and not just one...

  • Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J --...

    Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7 L J 10 6 5 M J 3 3 3 N K, M 9 5 1 O K, M 10 7 4 P L, N 10 8 3 Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT