| The Internal rate of return (IRR) is the discount rate for which the net present value (NPV) is zero. | |||||||||||||||||||||
| Using the IRR we can calculate the initial investment of the project. | |||||||||||||||||||||
| IRR | 0.1031 | ||||||||||||||||||||
| Initial investment | 49637.58 | ||||||||||||||||||||
| Present Value = Future value/ ((1+r)^t) | |||||||||||||||||||||
| where r is the interest rate that is 9% and t is the year | |||||||||||||||||||||
| NPV = Initial investment + sum of present values of future cash flows | |||||||||||||||||||||
| WACC/r | 0.09 | ||||||||||||||||||||
| Year | 0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 |
| cash flow | -49637.58 | 5000 | 5000 | 5000 | 5000 | 5000 | 5000 | 5000 | 5000 | 5000 | 5000 | 8500 | 8500 | 8500 | 8500 | 8500 | 8500 | 8500 | 8500 | 8500 | 8500 |
| Present value using IRR | 4532.68 | 4109.04 | 3724.99 | 3376.84 | 3061.23 | 2775.11 | 2515.74 | 2280.61 | 2067.45 | 1874.22 | 2888.39 | 2618.43 | 2373.70 | 2151.84 | 1950.72 | 1768.40 | 1603.12 | 1453.29 | 1317.46 | 1194.32 | |
| Present value using WACC | 4587.156 | 4208.4 | 3860.917 | 3542.126 | 3249.657 | 2981.337 | 2735.171 | 2509.331 | 2302.139 | 2112.054 | 3294.029 | 3022.045 | 2772.518 | 2543.595 | 2333.573 | 2140.893 | 1964.122 | 1801.947 | 1653.162 | 1516.663 | |
| NPV | 5493.26 | ||||||||||||||||||||
| The net present value of the project is $5493.3 | |||||||||||||||||||||
Click here to read the eBook: Net Present Value (NPV) Click here to read the eBook:...
Click here to read the eBook: Net Present Value (NPV) NPV Project L costs $50,000, its expected cash inflows are $11,000 per year for 7 years, and its WACC is 10%. What is the project's NPV? Round your answer to the nearest cent. Do not round your intermediate calculations.
7. Problem 11.07 Click here to read the eBook: Net Present Value (NPV) Click here to read the eBook: Internal Rate of Return (IRR) Click here to read the eBook: Modified Internal Rate of Return (MIRR) Click here to read the eBook: Payback Period CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 1 2 3 4 5 Project M Project N -$3,000...
1. Problem 11.01 Click here to read the eBook: Net Present Value (NPV) NPV Project L costs $50,000, its expected cash inflows are $12,000 per year for 9 years, and its WACC is 11%. What is the project's NPV? Round your answer to the nearest cent. Do not round your intermediate calculations.
Attempts: Keep the Highest: /1 1. Problem 11.01 Click here to read the eBook: Net Present Value (NPV) NPV Project L costs $35,000, its expected cash inflows are $15,000 per year for 10 years, and its WACC is 14%. What is the project's NPV? Round your answer to the nearest cent. Do not round your intermediate calculations. Grade It Now Save & Continue Continue without saving
1. Problem 11.18 Click here to read the eBook: Net Present Value (NPV) Click here to read the eBook: Internal Rate of Return (IRR) NPV AND IRR A store has 5 years remaining on its lease in a mall. Rent is $2,000 per month, 60 payments remain, and the next payment is due in 1 month. The mall's owner plans to sell the property in a year and wants rent at that time to be high so that the property...
Ck here to read the EDUK! Ne preselil value (NPV) Click here to read the eBook: Internal Rate of Return (IRR) NPV AND IRR A store has 5 years remaining on its lease in a mall. Rent is $2,100 per month, 60 payments remain, and the next payment is due in 1 month. The mall's owner plans to sell the property in a year and wants rent at that time to be high so that the property will appear more...
A project has annual cash flows of $5,000 for the next 10 years and then $7,000 each year for the following 10 years. The IRR of this 20-year project is 13.74%. If the firm's WACC is 12%, what is the project's NPV? Do not round intermediate calculations. Round your answer to the nearest cent.
complete this right please
11. Problem 11.18 Click here to read the eBook: Net Present Value (NPV) Click here to read the eBook: Internal Rate of Return (IRR) A-2 NPV AND IRR A store has 5 years remaining on its lease in a mall. Rent is $1,900 per month, 60 payments remain, and the next payment is due in 1 month. The mail's owner plans to sell the property in a year and wants rent at that time to be...
12. Problem 11.19 Click here to read the eBook: Multiple Internal Rates of Return Click here to read the eBook: Modified Internal Rate of Return (MIRR) MULTIPLE IRRS AND MIRR A mining company deciding whether to open a strip mine, which costs $2.5 million. Cash inflows of $13.5 million would occur at the end of Year 1. The land must be returned to its natural state at a cost of $12 million, payable at the end of Year 2 a....
Click here to read the eBook: Future Values Click here to read the eBook: Semiannual and Other Compounding Periods FUTURE VALUE FOR VARIOUS COMPOUNDING PERIODS Find the amount to which $600 will grow under each of these conditions: a. 9% compounded annually for 5 years. Do not round intermediate calculations. Round your answer to the nearest cent. b. 9% compounded semiannually for 5 years. Do not round intermediate calculations. Round your answer to the nearest cent. c. 9% compounded quarterly...