Following on from Distribution Requirements Planning Tutorial Question 3 (MVA Pet Food)
Update all four records as of the start of Week 2, assuming the following transactions occurred during week 1
Receipts | Order Releases | Sales (Distributions) | Inventory Adjustment | Open Order Scrap | |
Gro-Pup Seattle | 0 | 0 | 19 | -3 | 0 |
Gro-Pup Portland | 15 | 15 | 20 | +3 | 0 |
Gro-Pup Plant | 0 | 50 | 15 | 0 | 0 |
Gro-Pup Packaging | 90 | 100 | 50 | +4 | 10 |
Hint for above:
Calculate the Ending inventory for Wk 1 for all first, then follow same steps as previously outlined in the Tutorial.
So For example:
Gro-pup Seattle, for Period 1 Sales were 19 not 20, Inventory was down 3, from a projected 23 to 20.
Therefore the ending inventory or Available Balance at the end of Week 1 is 43-3-19 = 21
Which you will see in the Table below.
Gro-Pup Seattle Warehouse | Period | ||||||||
2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | ||
forecast Requirements | 20 | 20 | 20 | 20 | 20 | 20 | 20 | 20 | |
In Transit | |||||||||
Projected Available Balance | 21 | ||||||||
Planned Shipments | |||||||||
Q = 60 lead time = 1 Safety stock =0 | |||||||||
Gro-Pup Portland Warehouse | Period | ||||||||
2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | ||
forecast Requirements | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | |
In Transit | |||||||||
Projected Available Balance | |||||||||
Planned Shipments | |||||||||
Q = 15 lead time = 1 Safety stock =0 | |||||||||
Gro-Pup Plant Warehouse | Period | ||||||||
2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | ||
Gross Requirements | |||||||||
Scheduled Receipts | |||||||||
Projected Available Balance | -10 | ||||||||
Planned Order Release | |||||||||
Q = 50 lead time = 2 Safety stock =0 | |||||||||
Gro-Pup Packaging Material | Period | ||||||||
2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | ||
Gross Requirements | |||||||||
Scheduled Receipts | |||||||||
Projected Available Balance | |||||||||
Planned Order Release | |||||||||
Q = 100 lead time = 4 Safety stock =0 | |||||||||
10 have requested this problem solution
The more requests, the faster the answer.
please give step by step calculation as to how an answer is calculated.
Case #2 MGT2315 There are two (2) Parts to this case. The First part (Part 1) requires you to use the information to:1. Build a Bill of Material (BOM) form the given information2. Determine the Master Production Schedule (MPS) and3. Complete the MRP for all parts including the product. The Second Part (Part 2) will require you to use an indexed BOM to 1. Create the correct MPS from the provided information2. create the MRP for the unit and all of...
Product XYZ is described as follows: Quantity of each assembly/component is in (brackets) XYZ are made up of assemblies A(3), B, & C(2) Assembly A contains D(2), E(2), & F(3) Assembly B contains part H(2) Assembly C contains parts G(2) & E(2) Inventory Lead- time and Lot Size Information: XYZABCDEFGHLead Time121112222Projected On Hand93125329252039160012568Lot SizeLFLLFL2010LFL10020010050Scheduled Receipts500000001000Safety Stock 105025 **Note** all scheduled receipts are in week 1 Create a product structure tree (Multilevel BOM): (5 marks) Using Blank MRP sheets, Create a level loaded (discreet, with no remnants) plan ...
One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time of...
One unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time...
1. Develop an MRP record for six periods using the following information: period 1 2 3 4 5 6 gross requirements 20 20 40 30 30 27 scheduled receipts 50 projected available balance 2 planned order receipt planned order release Lead time = 1 period, lot size = 50 units, safety stock = 0 units, current inventory (prior to period 1) = 2 units, scheduled receipts = 50 units in period 1. What is the ending value of the projected...
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...
Assume that Product Z is made of two units of A and three units of B. A is made of four units of C and four of D. D is made of two units of E Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty one units of Product Z are required in Period 10. (Assume that...
Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E. Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty units of Product Z are required in Period 10. (Assume that there...
Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and three of D. D is made of three units of E Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty seven units of Product Z are required in Period 10. (Assume that...
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...