Consider the bill of materials (BOM) shown to the right.

Consider the bill of materials (BOM) shown to the right.

 a. How many immediate parents (one level above) does item I have? How many immediate parents does item E have? Item I has 2 immediate parent(s) and item E has 2 immediate parent(s) (Enter your responses as integers.)

b. How many unique components does product A have at all levels? Product A has  unique components. (Enter your response as an integer.) c. Which of the components are purchased items?

 Items F, G, H, and I.

 Items B, C, D, E, and J.

 Items B, C, and D.

Item I.

Items F and j.

Items F, G, and H.

image.jpg

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:


a) Item I has 1 immediate parents

i.e Immediate parents of I= E

Item E has 2 immediate parents

i.e Immediate parents of E= B,C

b) Prouduct A has 9 unique components

They are B, C, D, E, F, G, H, I & J respectively.

c) Option- F, G, H & I

The items F, G, H & I components are purchased items


answered by: Subrahmanyam golla
Add a comment
Know the answer?
Add Answer to:
Consider the bill of materials (BOM) shown to the right.
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Based on the BOM shown below, how many of part J will be needed if 40...

    Based on the BOM shown below, how many of part J will be needed if 40 units of end item A are needed? Managers have decided to outsource part G. Revised the BOM for end item A, assuming that item G is now purchase from a supplier. How many of part J will now be needed if 40 units of end item A are needed? Show all work. em A, assuming that item G is now purchased from a suppliet....

  • The bill of materials and the data from the inventory records for product A are shown in the figu...

    The bill of materials and the data from the inventory records for product A are shown in the figure to the right. Assume that the MPS start quantities for A are 100 units in weeks 1, 2, and 7. Derive an MRP plan for the components going into product A using the data in the table below Item Data Category L4L 2 weeks 100 (week 2) 350 L4L 1 week None 215 Lot-sizing rule Lead time Scheduled receipts Beginning inventory...

  • Please give the correct answer and explanation, 10 weeks is incorrect. Product A is made from...

    Please give the correct answer and explanation, 10 weeks is incorrect. Product A is made from components B and C. Item B, in turn, is made from D and E. Item C also is an intermediate item, made from F and H. Finally, intermediate item E is made from H and G. Note that item has two parents. The following are item lead times: Item Lead Time (weeks) A B C G H. 1 1 a. What lead time (in...

  • Product A is made from components B and C. Item B, in turn, is made from...

    Product A is made from components B and C. Item B, in turn, is made from D and E. Item C also is an intermediate item, made from F and H. Finally, intermediate item E is made from H and G. Note that item H has two parents. The following are item lead times: A B D Item Lead Time (weeks) a. What lead time (in weeks) inventories or scheduled receipts?weeks. (Enter your response as an integer.) 4 2 5...

  • 4. Based on the BOM shown below, how many units of part F will be needed...

    4. Based on the BOM shown below, how many units of part F will be needed if 15 units of end item A are needed? If the company decided to purchase part D from suppliers, how would th change? Assuming part D is purchased, how many units of part F are needed to make 15 units of end item A? 2 weeks B (1) 1 week C (4) 1 week D (2) 2 weeks D (3) 2 weeks G (2)...

  • 34. Consider the following product structure diagram, representing a bill of materials required to assemble some...

    34. Consider the following product structure diagram, representing a bill of materials required to assemble some finished good A: 009G CCDD (Items A through FF have been sketched as circles for convenience, but represent the same information as a product structure diagram sketched with squares, or any other shapes.) Please answer the following questions, based on this information a. Who is the parent of item N? b. Who are the children of item B? C. List all raw material items...

  • B. Determine the project’s critical path and duration.(this is number b wuestion) please answer t...

    b. Determine the project’s critical path and duration.(this is number b wuestion) please answer this two b and c questions Reliable Garage is completing production of the J2000 kit car. The following data are available for the project Activity Activity Time (days) Immediate Predecessor(s 10 D, E,G A-B-C-D-H 4 4 A-B-C-F-G-H b. Determine the pr A-B-C-E-H The critical path isand the project duration is I duration. day(s). (Enter your response as a whole number.) c. Calculate the slack for each...

  • 2. The bill of materials for product A with the associated component parts and planning factors...

    2. The bill of materials for product A with the associated component parts and planning factors (in parenthesis) are showed below. How many units of the following components are required to make one unit of the product A? 10 points p. 195 B(2) C (3) ľITRSP-300 H o m ework #3 Fall 2018 (A) Component B (B) Component C (C) Component D (D) Component E (E) Component F (F) Component G

  • Using the BOM shown below, 2 weeks B (4) 1 week C (4) 1 week D(4)...

    Using the BOM shown below, 2 weeks B (4) 1 week C (4) 1 week D(4) 2 weeks F(4) E (2) 4.9 weeks C(4) 1 week E (2) 4.9 weeks 5.9 weeks a. How many of part E will be needed if 24 units of end item A are needed? Number of parts needed b. How many part Cs will be needed? Number of parts needed

  • 3. (30 points) Consider the BOM tree of a sub-assembly, namely A. Land time (LT) consists...

    3. (30 points) Consider the BOM tree of a sub-assembly, namely A. Land time (LT) consists of estimates for setup time, processing time, materials handling time between operations or waiting time, depending on the item type. Items (B,C,D,E,F,G) belong to one of the followings: raw materials, purchased parts of manufactured parts. LT is given in terms of weeks. Suppose that there is no on-hand inventory and no scheduled receipts for all items. How many units of items E, D, and...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT