Expected Duration of each activity = ( a + 4*m + b ) / 6
Variance of Each activity = σ2 = { (b - a) / 6 }2
Standard Deviation of each activity = √σ2 = (b - a) / 6
Calculating using above formula -
| Activity | a | m | b | Expected Time | Variance | Standard Deviation |
| A | 11 | 16 | 18 | 15.50 | 1.36 | 1.17 |
| B | 28 | 32 | 41 | 32.83 | 4.69 | 2.17 |
| C | 17 | 17 | 17 | 17.00 | 0.00 | 0.00 |
| D | 8 | 13 | 20 | 13.33 | 4.00 | 2.00 |
| E | 18 | 19 | 20 | 19.00 | 0.11 | 0.33 |
| F | 17 | 20 | 21 | 19.67 | 0.44 | 0.67 |
whats the standard deviation for A,B,C,D,E,F 13 of 19 (14 complete) Problem 3.18 A renovation of...
If someone could help me with my Operations Management homework
that would be great!
A renovation of the gift shop at Orlando Amway Center has six activities (in hours). In the following table, the estimates of a, m, and b times for each of the activities are listed Activity 31 18 13 18 19 27 18 18 19 20 17 16 Based on the activity time estimates, the expected times for each of the activities are (round your responses to...
Answer next 3 questions using following information: A project has three activities A, B, and C that must be carried out sequentially. The probability distributions of the times required to complete each of the activities A, B, and C have uniform probability distribution in the following ranges:. Activity Completion Time A 1 to 5 B 2 to 3 C 3 to 6 Find the total project completion time and run 500 simulation trials in Excel. 1/ The “project completion time”...