Question

(b) A company is unable to satisfy customer demand for one of their products. The ratios for mixing the outputs from processe

Please answer step by step.

Thank you.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

i) Bottleneck resource is the one that limits the overall process capacity or output.

We shall analyze how many liters of output from each resource is required for an input of 1 unit to the subsequent department.

Units of output per hour = Capacity/units required

For example,

For Department C,

Capacity = 350 liters/hour

units required = 2

Units of output per hour = 350/2 = 175 liters/hour of output

Department Capacity (liters/hour) Predecessors units required Units of output per hour
A 450 - 1 450
B 450 A 1 450
C 350 B 2 175
D 250 - 1 250
E 250 - 1 250
F 750 C, D, E 3 250
G 300 - 1 300
H 950 F, G 4 237.5
I 350 - 1 350
J 1100 H, I 1 1100
K 1400 J 1 1400

Because the output per hour for department C is the least i.e. 175 liters, Department C is the bottleneck.

For process capacity:

We know C is the bottleneck and can contribute to making 175 liters of input for Department F.

Now, the 3 units of F are required to make 1 unit of H.

Hence, input for H = 175 / 3 = 58.33 Liters/hour

Now, the 4 units of H are required to make 1 unit of J.

Hence, input for J = 58.33 / 4 = 14.58 Liters/hour

Hence, process capacity = 14.58 Liters/Hour

ii) Now, we can add capacity to the existing bottleneck resource until the bottleneck gets shifted to the next limiting capacity of the resource.

Here, C is the existing bottleneck, and D and E are the next limiting resources.

So, we can add capacity to C till it matches the output from D and E.

C currently generates 175 liters of output per hour for which it requires a capacity of 350 liters.

We can increase C's output to 250 liters per hour, for which it will require 250 * 2 = 500 liters per hour of capacity.

Hence, additional capacity requirement = 500 - 350 = 150 liters/hour

Now,

the revised input to F will be 250 liters/hour

Now, the 3 units of F are required to make 1 unit of H.

Hence, input for H = 250 / 3 = 83.33 Liters/hour

Now, the 4 units of H are required to make 1 unit of J.

Hence, input for J = 83.33 / 4 = 20.83 Liters/hour

Hence, revised process capacity = 16.67 Liters/Hour

The gain in process capacity = 20.83 - 14.58

The gain in process capacity = 6.25 liters/hour

Kindly up-vote this answer if it was helpful to you. This will help me in maintaining the quality of my answers. Do reach out to me in case of any queries. Thank you.

Happy Learning!

Add a comment
Know the answer?
Add Answer to:
Please answer step by step. Thank you. (b) A company is unable to satisfy customer demand...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 2: (a) A Muscat Tools company manufactures toolkits and supplies to the local and overseas...

    Question 2: (a) A Muscat Tools company manufactures toolkits and supplies to the local and overseas market within the GCC region. In the assembly line, the kits are packed in the tool boxes. The company produces the specified demand rate of toolkit in 8 hours per daywithtasks, description of tasks, and time for each task shown in Table Q2a. (i) Draw the precedence diagram anddetermine the cycle time,and number of workstations; iii) Balance the line using the longest task time...

  • Please solve this question clearly and step by step. Thank you 2. a. A company is...

    Please solve this question clearly and step by step. Thank you 2. a. A company is planning to install an air compressed system at its manufacturing plant. The compressed air is to be used to operate the instruments and portable tools and maintenance requirements. The compressed air requirements vary from 200 to 400 m/ hr with the pressure requirements vary from 4 to 8 bar i. Propose a feasible air compressed system for the company and explain the function of...

  • please answer in details, thank you The Project below is currently at the end of Week...

    please answer in details, thank you The Project below is currently at the end of Week 6. Use the table below to find the PV, EV, CPI, SPI, and CSI. Use the % Complete column where applicable for these calculations. What conclusions can you make on the project given your calculated CPI, SPI, and CSI values? Activity Predecessors Duration (weeks) Budget, $ $350 $550 $250 $400 $450 $600 Actual Cost, $ $400 $550 $200 $300 $150 А % Complete 100%...

  • Provide step by step please thank you, no exce Assume you have a project with ten...

    Provide step by step please thank you, no exce Assume you have a project with ten activities labeled A-J, as shown. Derive the earliest completion time (or early finish-EF), latest completion time (or late finish-LF), and slack for each of the following tasks (begin at time 0) the critical path on your network diagram. . Which tasks are on the critical path? Highligh Preceding Expected Critical Path? Activity Event Duration EF LF Slack A, D C,E D, E F, G...

  • please do step by step how you got the answer Figure 3-14 Arturo's Production Possibilities Frontier...

    please do step by step how you got the answer Figure 3-14 Arturo's Production Possibilities Frontier Dina's Production Possibilities Frontier durritos durritos 500 500 450 450 400 400 350 350 300 300 250 250 200 + 200 150 150 100 100 50 50 50 100 150 200 250 300 350 400 tacos 50 100 150 200 250 300 350 400 tacos ab Refer to Figure 3-14. Suppose Arturo is willing to trade 6 burritos to Dina for each 10 tacos...

  • Create a precedence diagram from the given table, then find a workstation assignment by taking cycle...

    Create a precedence diagram from the given table, then find a workstation assignment by taking cycle time=17 minutes and assigning in the order of the greatest task time. Task Label Time Predecessors A 2 ------ B 7 A C 5 ------ D 2 ------ E 15 C, D F 7 A, E G 6 ------ H 4 B, G I 9 A J 10 ------- K 4 ------- L 8 J, K M 6 A, L N 15 F, H,...

  • Please type; I have a tough time reading handwriting. Thank you Give the connected components for...

    Please type; I have a tough time reading handwriting. Thank you Give the connected components for the following graph: V = {a, b, c, d, e, f, g, h, i, j}. E = { {f,h}, {e,d}, {c,b}, {i,j}, {a,b}, {i,f}, {f,j} }

  • Specify the reagent you would use in each step of the following synthesis: step 1 step...

    Specify the reagent you would use in each step of the following synthesis: step 1 step 2 step 2 Reagents Available a. LIAIHA f. PBr3 b. H2SO4 c. HCI d. HBO e. SOC2 k. CH3CH MgBr g. Dess-Martin periodinane (DMP) I. CH.MgBr (phenylmagnesium bromide) h. Nah m. (CH3)2CHMgBr 1. NaOH n. Croz J. CH3MgBr Write the letters of the reagents in the boxes below. Reagent for step 1 Reagent for step 2 Submit Answer Retry Entire Group 9 more group...

  • Specify the reagent you would use in each step of the following synthesis: step 1 step...

    Specify the reagent you would use in each step of the following synthesis: step 1 step 2 Cl Reagents Available f. PBr3 g. Dess-Martin periodinane (DMP) . C6H5MgBr h. NaH i. NaOH j. CH3MgBr k. CH3CH2MgBr a. LiAIH4 b. H2SO4 c. HCI d. HBr e. Soci2 (phenylmagnesium bromide) m. (CH3)2CHMgBr n. CrO3 Write the letters of the reagents in the boxes below. Reagent for step 1 Reagent for step 2

  • Construct an Activity-on-branch network from the precedence relationships of activities shown Activity Predecessors Duration 6 7...

    Construct an Activity-on-branch network from the precedence relationships of activities shown Activity Predecessors Duration 6 7 A A A B с D E F 1 14 5 8 9 3 5 3 B C D C, D D H F E, J F GI G, I L, N H I J K L M 12 6

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT