Deb Bishop Health and Beauty Products has developed a new shampoo, and you need to develop its aggregate schedule. The cost accounting department has supplied you the costs relevant to the aggregate plan, and the marketing department has provided a four-quarter forecast. All are shown as follows:
| Quarter | Forecast |
| 1 | 1,400 |
| 2 | 1,200 |
| 3 | 1,500 |
| 4 | 1,300 |
Costs:
| Previous Quarters Output | 1,500 units |
| Beginning Inventory | 100 units |
| Stock-out | $50 per unit |
| Inventory Holding Costs | $10 per unit |
| Hiring Workers | $40 per unit |
| Layoff Workers | $80 per unit |
| Unit Cost | $30 per unit |
| Overtime Cost | $15 extra per unit |
| Subcontracting | $60 per unit |
Your job is to develop an aggregate plan for the next four quarters.
Plan A - First, try hiring and layoffs based on the prior quarter (to meet the forecast) as necessary. What is the cost of this plan? $ [ Select ] ["215,900", "220,500", "178,000", "214,000"]
Plan B - Then try a plan that holds employment steady. What is the cost of this plan? $ [ Select ] ["178,000", "169,500", "195,600", "212,225"]
Plan A

Result:
| Quarter | Forecast | Output | Hire | Layoff |
| 1,500 | ||||
| 1 | 1,400 | 1,400 | 0 | 100 |
| 2 | 1,200 | 1,200 | 0 | 200 |
| 3 | 1,500 | 1,500 | 300 | 0 |
| 4 | 1,300 | 1,300 | 0 | 200 |
| Totals | 5,400 | 300 | 500 | |
| Cost/ unit | $30 | $40 | $80 | |
| Costs | $162,000 | $12,000 | $40,000 | |
| $214,000 |
Plan B

| Quarter | Forecast | Output | Hire | Layoff | Ending inventory |
| 1,500 | 100 | ||||
| 1 | 1,400 | 1,350 | 0 | 150 | 50 |
| 2 | 1,200 | 1,350 | 0 | 0 | 200 |
| 3 | 1,500 | 1,350 | 0 | 0 | 50 |
| 4 | 1,300 | 1,350 | 0 | 0 | 100 |
| Totals | 5,400 | 0 | 150 | 400 | |
| Cost/ unit | $30 | $40 | $80 | $10 | |
| Costs | $162,000 | $0 | $12,000 | $4,000 | |
| $178,000 |
Plan C

| Quarter | Forecast | Regular output | Hire | Layoff | Overtime output | Subcontracted output |
| 1,500 | ||||||
| 1 | 1,400 | 900 | 0 | 600 | 200 | 200 |
| 2 | 1,200 | 900 | 0 | 0 | 200 | 100 |
| 3 | 1,500 | 900 | 0 | 0 | 200 | 400 |
| 4 | 1,300 | 900 | 0 | 0 | 200 | 200 |
| Totals | 3,600 | 0 | 600 | 800 | 900 | |
| Cost/ unit | $30 | $40 | $80 | $45 | $60 | |
| Costs | $108,000 | $0 | $48,000 | $36,000 | $54,000 | |
| $246,000 |
Deb Bishop Health and Beauty Products has developed a new shampoo, and you need to develop...
Southeast Soda Pop, Inc., has a new fruit drink for which it has high hopes. John Mittenthal, the production planner, has assembled the following cost data and demand forecast: QUARTER FORECAST 1 1,800 2 1,100 3 1,600 4 900 COSTS/OTHER DATA Previous quarter’s output = 1,300 cases Beginning inventory = 0 cases Stock-out cost = $150 per case Inventory holding cost = $40 per case at end of quarter Hiring employees = $40 per case Terminating employees = $80 per...
The following forecast constitutes the demand for relay switches. John Smith, the production planner, has assembled the following cost data and the quarterly demand forecast: QUARTER FORECAST 1,800 1 2 1,100 3 1,600 900 4 Costs/Other Data Previous quarter's output = 1300 cases Beginning inventory 350 cases Stockout cost = $110 per case Inventory holding cost $30 per case at the end of quarter Hiring employees = $40 per case Terminating employees = $75 per case Subcontracting cost = $60...
Summer-Fun, Inc., produces a various commodities related to recreation and leisure. The production manager has developed an aggregate forecast: Apr May Aug Sep Total Mar June July Demand 50 1 44 | 55 | 59 | 50 | 41 51 350 Use the following information to develop aggregate plans. Regular production cost $ 80 per unit Overtime(OT) production cost $ 120 per unit Subcontracting(SC) cost $ 140 per unit Regular capacity 40 units per month Overtime capacity 8 units per...
Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 11,000; winter, 7,700; spring, 6,700; summer, 13,000. Inventory at the beginning of fall is 550 units. At the beginning of fall you currently have 30 workers, but you plan to hire temporary workers at the beginning of summer and lay them off at the end of summer. In addition, you have negotiated with the union an option to use the regular workforce on...
Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 10,500; winter, 8,000; spring, 7,000; summer, 12,500. Inventory at the beginning of fall is 525 units. At the beginning of fall you currently have 35 workers, but you plan to hire temporary workers at the beginning of summer and lay them off at the end of summer. In addition, you have negotiated with the union an option to use the regular workforce on...
Problem 8-7 Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 10,700; winter, 8,300; spring, 6,900; summer, 12,700. Inventory at the beginning of fall is 535 units. At the beginning of fall you currently have 35 workers, but you plan to hire temporary workers at the beginning of summer and lay them off at the end of summer. In addition, you have negotiated with the union an option to use the regular...
The owner of a small mill-working plant that builds cabinets is
developing his aggregate plan for the next year. The relevant cost
data and forecast for the next 4 quarters is provided below. The
company currently has 20 employees and works one 8 hour shift each
day with 2 paid 15 minute breaks. Assume each quarter has 65
working days, and that it currently has no units in stock. Use this
information and the information from the table to answer...
The Baily Corporation has developed a specialized software program that improves inventory control capability. The following table/information provides the necessary data to evaluate: quarter forecast(units) regular time overtime sub-contract 1 500 400 80 100 2 750 400 80 100 3 900 800 160 100 4 450 400 80 100 Initial Inventory = 200 units Regular Time Cost = $2.50/unit Overtime Cost = $1.00/extra per unit Subcontracting Cost = $4.00/unit Carrying Cost = $.50/unit Back-Order Cost = $.75/unit The company decides...
makes skis, unow boar and high end sledding equsipment As shown below,t Slopes & S the demand for its peoducts is highly seasonal. The company empleys 10 workers who can each produce 200 units of various eqipmest per s limaited to regla production each period Subcontracting is unlimined Haring and fxing costs are $500 per workn laventory holding coss are $2 per unit per month Grven the estimates of demand below, a. the current workforce level (uapplemented with overtime and...
A manager has projected demand for the next six months (below). Given this information, prepare a LEVEL aggregate plan for production. Assume maximum regular time production is 350 units per month. Overtime is limited to 75 units per month. The limit for subcontracting is 400 per month. The company has a zero beginning inventory and cannot have ending inventory or a backlog at the end of the 6th period. Unit costs are as noted below. Regular Time Cost: $10/unit Overtime...