Answer
|
A |
Sale price per unit |
$ 350.00 |
|
B |
Variable cost per unit |
$ 210.00 |
|
C = A - B |
Contribution margin per unit |
$ 140.00 Answer |
|
D |
Fixed costs |
$ 42,000.00 |
|
E = D/C |
Break Even in Units |
300 = Answer |
|
A |
Contribution margin per unit |
$ 140.00 |
|
B |
Sale price per unit |
$ 350.00 |
|
C = (A/B) x 100 |
Contribution margin ratio |
40% = Answer |
|
D |
Fixed costs |
$ 42,000.00 |
|
E =D/C |
Break Even point in Dollars |
$ 105,000.00 = Answer |
|
A |
Target Net Income |
$ 70,000.00 |
|
B |
Fixed costs |
$ 42,000.00 |
|
C = A+B |
Total Contribution margin required |
$ 112,000.00 |
|
D |
Contribution margin per unit |
$ 140.00 |
|
E = C/D |
Units required to at target income |
800 units = ANSWER |
>NO, it would not be possible for Hip Hop to earn $ 70,000 in Income next year.
>This is because, no. of units required computed above is 800 units. However, the question states that maximum capacity is 700 units. Hence under normal circumstances 800 units cannot be produced and hence cannot earn $ 70,000 Net Income.
*****please note that the instructor modified questions on the spreadsheet so please read the problem and...
5. Slip-Shod Company manufactures and markets several products. Management is considering the future of one product, bootstraps that have not been as profitable as planned. Since this product is manufactu red and marketed independently of the other products, its total costs can be precisely measured. Next year's plans call for an $85 selling price per unit. The fixed costs for the year are expected to be $42,300, up to a capacity of 1,500 units. Forecasted variable costs are $38 per...
Required information Problem 21-3A CVP analysis and charting LO P2, P3 (The following information applies to the questions displayed below.) Praveen Co. manufactures and markets a number of rope products. Management is considering the future of Product XT, a special rope for hang gliding, that has not been as profitable as planned. Since Product XT is manufactured and marketed independently of the other products, its total costs can be precisely measured. Next year's plans call for a $200 selling price...
Hi, Please answer this 2 part question.
Required information [The following information applies to the questions displayed below.) Praveen Co. manufactures and markets a number of rope products. Management is considering the future of Product XT, a special rope for hang gliding, that has not been as profitable as planned. Since Product XT is manufactured and marketed independently of the other products, its total costs can be precisely measured. Next year's plans call for a $240 selling price per 100...
Need help with this accounting problem.
Required information Problem 21-3A CVP analysis and charting LO P2, P3 [The following information applies to the questions displayed below.) Praveen Co. manufactures and markets a number of rope products. Management is considering the future of Product XT, a special rope for hang gliding, that has not been as profitable as planned. Since Product XT is manufactured and marketed independently of the other products, its total costs can be precisely measured. Next year's plans...
Required information [The following information applies to the questions displayed below.] Praveen Co. manufactures and markets a number of rope products. Management is considering the future of Product XT, a special rope for hang gliding, that has not been as profitable as planned. Since Product XT is manufactured and marketed independently of the other products, its total costs can be precisely measured. Next year's plans call for a $230 selling price per 100 yards of XT rope. Its fixed costs...
Required information The following information applies to the questions displayed below.) Praveen Co. manufactures and markets a number of rope products. Management is considering the future of Product XT, a special rope for hang gliding, that has not been as profitable as planned. Since Product XT is manufactured and marketed independently of the other products, its total costs can be precisely measured. Next year's plans call for a $240 selling price per 100 yards of XT rope. Its fixed costs...
Required information The following information applies to the questions displayed below) Praveen Co. manufactures and markets a number of rope products. Management is considering the future of Product XI. a special rope for hang gliding, that has not been as profitable as planned. Since Product XT is manufactured and marketed independently of the other products, its total costs can be precisely measured. Next year's plans cal for a $190 selling price per 100 yards of XT rope. Its fixed costs...
Praveen Co. manufactures and markets a number of rope products. Management is considering the future of Product XT, a special rope for hang gliding, that has not been as profitable as planned. Since Product XT is manufactured and marketed independently of the other products, its total costs can be precisely measured. Next year's plans call for a $200 selling price per 100 yards of XT rope. Its fixed costs for the year are expected to be $270,000, up to a...
H8 5 Unit 2 Cost Volume Profit 6 Read Chapter 18 Problem 3 Frost Fire Company is analyzing two alternative methods of manufacturing is custom snowboards. The Managerial Accountant has performed an analysis that indicates that variable costs can be reduced 40% by installing a machine that would automate production, but fixed costs would increase to $675,000. Analysis 1 shows costs before installing the machine; Analysis 2 shows costs after the machine is installed. If Analysis 2 is selected, Management...
Required information (The following information applies to the questions displayed below) Praveen Co. manufactures and markets a number of rope products. Management is considering the future of Product XT, a special rope for hang gliding, that has not been as profitable as planned. Since Product XT is manufactured and marketed independently of the other products, its total costs can be precisely measured. Next year's plans call for a $190 selling price per 100 yards of XT rope. Its fixed costs...