Question

Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...

Sultan Company uses an activity-based costing system.

At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools:

Activity Cost Pool

Activity Measure

Expected
Overhead Cost

Expected Activity

Labor-related

Direct labor-hours

$

400,000

40,000

DLHs

Purchase orders

Number of orders

$

11,150

223

orders

Parts management

Number of part types

$

82,820

101

part types

Board etching

Number of boards

$

73,800

1,640

boards

General factory

Machine-hours

$

279,500

21,500

MHs

Required:

1. Compute the activity rate for each of the activity cost pools.

2. The expected activity for the year was distributed among the company’s four products as follows:

Expected Activity

Activity Cost Pool

Product A

Product B

Product C

Product D

Labor-related (DLHs)

6,700

23,300

4,300

5,700

Purchase orders (orders)

63

39

36

85

Parts management (part types)

37

15

38

11

Board etching (boards)

300

760

580

0

General factory (MHs)

3,900

8,800

2,500

6,300

Using the ABC data, determine the total amount of overhead cost assigned to each product.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer

  • All working forms part of the answer
  • Requirement 1

Activity Cost Pool

Activity Measure

Expected Overhead cost

Expected Activity

Activity Rates = ANswer

[A]

[B]

[A/B]

Labor-related

Direct labor-hours

$                400,000.00

                                               40,000

DLHs

$                   10.00

per DLHs

Purchase orders

Number of orders

$                  11,150.00

                                                     223

orders

$                   50.00

per orders

Parts management

Number of part types

$                  82,820.00

                                                     101

part types

$                 820.00

per part types

Board etching

Number of boards

$                  73,800.00

                                                 1,640

boards

$                   45.00

per boards

General factory

Machine-hours

$                279,500.00

                                               21,500

MHs

$                   13.00

per MHs

  • Requirement 2

Overhead allocated to each product is provided in sequence

--Product A

Expected Activity

Activity Rates

Overhead Allocated

Activity Cost Pool

Product A

Labor-related (DLHs)

                                               6,700

$                           10.00

per DLHs

$         67,000.00

Purchase orders (orders)

                                                     63

$                           50.00

per orders

$           3,150.00

Parts management (part types)

                                                     37

$                        820.00

per part types

$         30,340.00

Board etching (boards)

                                                  300

$                           45.00

per boards

$         13,500.00

General factory (MHs)

                                               3,900

$                           13.00

per MHs

$         50,700.00

Amount of Overhead Cost assigned

$       164,690.00

---Product B

Expected Activity

Activity Rates

Overhead Allocated

Activity Cost Pool

Product B

[A/B]

Labor-related (DLHs)

                                            23,300

$                           10.00

per DLHs

$       233,000.00

Purchase orders (orders)

                                                     39

$                           50.00

per orders

$           1,950.00

Parts management (part types)

                                                     15

$                        820.00

per part types

$         12,300.00

Board etching (boards)

                                                  760

$                           45.00

per boards

$         34,200.00

General factory (MHs)

                                               8,800

$                           13.00

per MHs

$       114,400.00

Amount of Overhead Cost assigned

$       395,850.00

---Product C

Expected Activity

Activity Rates

Overhead Allocated

Activity Cost Pool

Product C

[A/B]

Labor-related (DLHs)

                                               4,300

$                           10.00

per DLHs

$         43,000.00

Purchase orders (orders)

                                                     36

$                           50.00

per orders

$           1,800.00

Parts management (part types)

                                                     38

$                        820.00

per part types

$         31,160.00

Board etching (boards)

                                                  580

$                           45.00

per boards

$         26,100.00

General factory (MHs)

                                               2,500

$                           13.00

per MHs

$         32,500.00

Amount of Overhead Cost assigned

$       134,560.00

---Product D

Expected Activity

Activity Rates

Overhead Allocated

Activity Cost Pool

Product D

[A/B]

Labor-related (DLHs)

                                               5,700

$                           10.00

per DLHs

$         57,000.00

Purchase orders (orders)

                                                     85

$                           50.00

per orders

$           4,250.00

Parts management (part types)

                                                     11

$                        820.00

per part types

$           9,020.00

Board etching (boards)

                                                      -  

$                           45.00

per boards

$                        -  

General factory (MHs)

                                               6,300

$                           13.00

per MHs

$         81,900.00

Amount of Overhead Cost assigned

$       152,170.00

Add a comment
Answer #2
1)Calculation of Activity Rates




















Activity Cost pool Expected OH  Expected Activity  Activity Rate 






Labour related           400,000             40,000               10.00per DLH





Purchase Orders             11,150                   223               50.00per ORDER





Parts Management             82,820                   101             820.00per part type





Board Etching             73,800               1,640               45.00per board





General Factory           279,500             21,500               13.00per MH















2)Overehad cost assigned to each   product



















Activity Cost pool Activity Rate  Product A Activity  Cost assigned to product A  Product B Activity  Cost assigned to product B  Product C Activity  Cost assigned to product C  Product D Activity  Cost assigned to product D 

Labour related               10.00               6,700             67,000             23,300           233,000               4,300             43,000               5,700             57,000

Purchase Orders               50.00                     63               3,150                     39               1,950                     36               1,800                     85               4,250

Parts Management             820.00                     37             30,340                     15             12,300                     38             31,160                     11               9,020

Board Etching               45.00                   300             13,500                   760             34,200                   580             26,100                        -                          -  

General Factory               13.00               3,900             50,700               8,800           114,400               2,500             32,500               6,300             81,900












Total Cost assigned

           164,690
           395,850
           134,560
           152,170



source: managerial accounting
answered by: anonymous
Add a comment
Know the answer?
Add Answer to:
Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Cost Pool Labor-related Purchase orders Parts management Board etching General factory Activity Measure Direct labor-hours Number of orders Number of part types Number of boards Machine-hours Expected Overhead Cost $ 311,500 $ 8,840 $ 71,280 $ 63,700 $ 148,000 Expected Activity 44,500 DLHS 221 orders 99 part types 1,820 boards...

  • Sultan Company uses an activity-based costing system.         At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system.         At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for Its five activity cost pools: Activity Measure Expected Overhead Expected Activity DLHS Activity Cost Pool Cost 135,600 24 Labor-related Direct labor-hours 22,600 $ 8,400 $ 68,870 240...

  • Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Cost Pool Labor-related Purchase orders Parts management Board etching General factory Activity Measure Direct labor-hours Number of orders Number of part types Number of boards Machine-hours Expected Overhead Cost $ 311,500 $ 8,840 $ 71,280 $ 63,700 $ 148,000 Expected Activity 44,500 DLHS 221 orders 99 part types 1,820 boards...

  • Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Expected Measure Overhead Expected Activity Cost Pool Cost Activity Labor-related Direct labor-hours $380,000 38.000 DLHS Purchase orders Number of orders $11.935 217 orders Parts Number of part $ 79,500 1 06 part types management types Board etching Number of boards $93.000 1,860 boards General factory Machine-hours $240,500 18.500 MHS Required:...

  • Sultan Company uses an activity-based costing system At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Expected Measure Overhead Expected Activity Cost Pool Cost Activity Labor-related Direct labor-hours $ 148,000 29,600 DLHs Purchase orders Number of orders $ 15,180 253 orders Parts management Number of part types $ 85,680 102 part types Board etching General factory Number of boards Machine-hours $ 99,550 $ 162,400 1,810 boards...

  • Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools Activity Measure Expected Overhead Expected Activity Activity Cost Pool Labor-related Purchase orders Parts management Cost Direct labor-hours Number of orders Number of part types S 284,000 35,500 DLHs $ 6,790 S 194 orders 71,340 82 part types Number of boards Machine-hours S 57,900 $ 229,900 20,900 MH:s 1,930 boards Board etching...

  • Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Cost Pool Labor-related Purchase orders Parts management Board etching General factory Activity Measure Direct labor-hours Number of orders Number of part types Number of boards Machine-hours Expected Overhead Cost $ 231,600 $ 15,015 $ 95,200 $ 106,800 $ 184,500 Expected Activity 38,600 DLHS 231 orders 112 part types 1,780 boards...

  • Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Cost Pool Activity Measure Expected Overhead Cost Expected Activity Labor-related Direct labor-hours $ 174,000 34,800 DLHs Purchase orders Number of orders $ 7,200 240 orders Parts management Number of part types $ 66,500 95 part types Board etching Number of boards $ 64,800 1,620 boards General factory Machine-hours $ 115,200...

  • Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Cost Pool Activity Measure Expected Overhead Cost Expected Activity Labor-related Direct labor-hours $ 284,000 35,500 DLHs Purchase orders Number of orders $ 6,790 194 orders Parts management Number of part types $ 71,340 82 part types Board etching Number of boards $ 57,900 1,930 boards General factory Machine-hours $ 229,900...

  • Sultan Company uses an activity-based costing system. At the beginning of the year, the company made...

    Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools: Activity Cost Pool Activity Measure Expected Overhead Cost Expected Activity Labor-related Direct labor-hours $ 174,000 34,800 DLHs Purchase orders Number of orders $ 7,200 240 orders Parts management Number of part types $ 66,500 95 part types Board etching Number of boards $ 64,800 1,620 boards General factory Machine-hours $ 115,200...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT