The Shady Farm Milk Company can process milk at a fixed rate of 6800 gallons/hour. The company’s clients request 107000 gallons of milk over the course of one day. This demand is spread out uniformly from 8 a.m. - 6 p.m. The company starts producing at 8 a.m. and continues to work until all of the demand has been satisfied. How long does the client requesting milk at 6pm have to wait to have their _____ hours demand satisfied? (round answer to 2 decimal places
Processing rate, p = 6,800 gallons/hour
Demand rate, d = 107000/10 = 10,700 gallons/hour (from 8 am to 6 pm = 10 hours)
Backlog at 6pm = Total demand over 10 hours - total processing over 10 hours
= 10*(10700-6800)
= 39,000 gallons
Total hours required to complete processing of backlog = 39000/6800
= 5.74 hours
The Shady Farm Milk Company can process milk at a fixed rate of 6800 gallons/hour. The...
uct B, 50 units per day; and product C, 60 units per day. What is the bottleneck? What is the flow rate for each flow unit assuming that demand must be served in the mix described above (i.e., for every four units of A, there are five units of B and six units of C)? (Cranberries) International Cranberry Uncooperative (ICU) is a competitor to the Na- tional Cranberry Cooperative (NCC). At ICU, barrels of cranberries arrive on trucks at a...