If we know a project’s IRR is 11%, and provides annual cash-flows of $15,000 for six years, how much is the maximum that the project could have cost assuming the investors are rational decision makers and what to maximize income?
Let initial cost be P
IRR = 11%
Annual cash flow= 15000
t = 6 yrs
At IRR net present value of cash flow is zero, therefore
-P + 15000(P/A,11%,6) = 0
P = 15000*4.2305378
P = 63458.07
maximum value of the initial cost can be 63458
If we know a project’s IRR is 11%, and provides annual cash-flows of $15,000 for six...
IRR, investment life, and cash inflows Oak Enterprises accepts projects earning more than the firm's 11% cost of capital. Oak is currently considering a 10-year project that provides annual cash inflows of $50,000 and requires an initial investment of $304,600. (Note: All amounts are after taxes.) a. Determine the IRR of this project. Is it acceptable? b. Assuming that the cash inflows continue to be $50,000 per year, how many additional years would the flows have to continue to make...
A project that provides annual cash flows of $18,000 for 6 years costs $61,000 today. A. If the required return is 11 percent, what is the NPV for this project? B. Determine the IRR for this project. Show work please.
Find the Net Present Value of a project’s cash flow which costs $75,000 and provides cash flows of $9,200 per year for six years with annual escalations of 2.5% per year. Assume an 8% annual rate of return.
2. A project that provides annual estimated cash flows of $120 for eight years costs $600 today. Suppose the financial manager has a required return of 8%. (a) By the NPV rule, is this a good project to the financial manager? What if the required return is 24%? At what discount rate would you be indifferent between accepting the project and rejecting it? he/she accept the project? the decisions consistent using both the NPV and IRR rules? Why? (b) What...
2. A project that provides annual estimated cash flows of $120 for eight years costs $600 today. Suppose the financial manager has a required return of 8% (a) By the NPV rule, is this a good project to the financial manager? What if the required return is 24%? At what discount rate would you be indifferent between accepting the project and rejecting it? he/she accept the project? the decisions consistent using both the NPV and IRR rules? Why? (b) What...
A project that provides annual cash flows of $10,400 for 10 years costs $58,762 today. a. If the required return is 5 percent, what is the NPV for this project? b. Determine the IRR for this project.
A project that provides annual cash flows of $11,200 for 7 years costs $51,114 today. a. If the required return is 7 percent, what is the NPV for this project? b. Determine the IRR for this project.
A project that provides annual cash flows of $13,000 for 8 years costs $69,354 today. a. If the required return is 15 percent, what is the NPV for this project? b. Determine the IRR for this project.
A project that provides annual cash flows of $12,300 for 7 years costs $59,882 today. a. If the required return is 7 percent, what is the NPV for this project? b. Determine the IRR for this project.
A project that provides annual cash flows of $21,000 for 5 years costs $67,000 today. a. If the required return is 15 percent, what is the NPV for this project? b. Determine the IRR for this project.