Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below.
Activity Cost
Activity Base
Procurement $384,800
Number of
purchase orders
Scheduling $227,600
Number of
production orders
Materials handling $472,700
Number of
moves
Product development $703,600
Number of
engineering changes
Production $1,536,300
Machine
hours
Number of
Purchase
Orders
Number of
Production
Orders
Number
of
Moves
Number of
Engineering
Changes
Machine
Hours
Number
of
Units
Disk drives 3,860
310
1,240 10
1,900
1,700
Tape drives 1,700
235
740 4
9,900
3,600
Wire drives 12,200
890
3,500 24
10,100
2,400
Determine the activity rate for materials handling per move.
a.$70.15
b.$158.61
c.$21.67
d.$86.26
Calculate material handling per move
Activity | expected overhead | expected activity | activity rate |
Material handling | 472700 | 1240+740+3500 = 5480 | 472700/5480 = 86.26 per move |
So answer is d) $86.26
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools The budgeted activity cost and activity base data by product are provided below Activity Cost Activity Base Number of purchase orders Number of production orders Number of moves Procurement333,500 Scheduling $245,900 Materials handling Product development Production ,513,200 $424,700 $743,700 Number of engineering changes Machine hours Number Number of Number Number of Number...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Activity Cost Activity Base Procurement $374,100 Number of purchase orders Scheduling $208,600 Number of production orders Materials handling $478,000 Number of moves Product development $798,000 Number of engineering changes Production $1,461,200 Machine hours Number of Purchase Orders Number of...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Activity Cost Activity Base Procurement $368,300 Number of purchase orders Scheduling 205,300 Number of production orders Materials handling 463,200 Number of moves Product development 755,700 Number of engineering changes Production 1,427,300 Machine hours Number of Purchase Orders Number of...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Activity Cost Activity Base Procurement $352,000 Number of purchase orders Scheduling $213,200 Number of production orders Materials handling $454,500 Number of moves Product development $725,300 Number of engineering changes Production $1,401,500 Machine hours Number of Purchase Orders Number of...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Activity Cost Activity Base Procurement $329,900 Number of purchase orders Scheduling 223,700 Number of production orders Materials handling 426,300 Number of moves Product development 762,500 Number of engineering changes Production 1,434,200 Machine hours Number of Purchase Orders Number of...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Procurement Scheduling Materials handling Product development Production Activity Cost Activity Base $347,800 Number of purchase orders 205,800 Number of production orders 491,900 Number of moves 779,400 Number of engineering changes 1,418,700 Machine hours Number of Engineering Machine Changes Hours...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Activity Cost Activity Base Procurement $316,400 Number of purchase orders Scheduling $205,600 Number of production orders Materials handling $499,400 Number of moves Product development $710,900 Number of engineering changes Production $1,565,900 Machine hours Number of Purchase Orders Number of...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Activity Cost Activity Base Procurement $355,800 Number of purchase orders Scheduling $219,600 Number of production orders Materials handling $486,900 Number of moves Product development $756,500 Number of engineering changes Production $1,495,300 Machine hours Number of Purchase Orders Number of...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Activity Cost Activity Base Procurement $345,800 Number of purchase orders Scheduling $231,000 Number of production orders Materials handling $490,100 Number of moves Product development $785,000 Number of engineering changes Production $1,537,000 Machine hours Number of Purchase Orders Number of...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Activity Cost Activity Base Procurement $309,800 Number of purchase orders Scheduling 207,900 Number of production orders Materials handling 427,200 Number of moves Product development 787,800 Number of engineering changes Production 1,508,300 Machine hours Number of Purchase Orders Number of...