Question

IT Project Management: Chapter 7 Project Cost Management: 1. If the cost estimate will be the...

IT Project Management:

Chapter 7 Project Cost Management:

1. If the cost estimate will be the basis for contract awards and performance reporting, it should be a ____ and as accurate as possible.

a. budgetary estimate

b. definitive estimate

c. rough order of magnitude estimate

d. final estimate

2. The main outputs of the ____________________ process are activity cost estimates, basis of estimates, and project document updates.

3. It’s important for the team to ____________________ assumptions they made when developing the cost baseline and have several experts review it.

4. ____ are costs that are not directly related to the products or services of the project, but are indirectly related to performing the project.

a. Intangible costs

b. Tangible costs

c. Direct costs

d. Indirect costs

5. When deciding what projects to invest in or continue, you should include sunk costs.

True or False

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1)  definitive estimate
2)  cost estimating
3)  document
4)  Indirect costs
5)  False
Add a comment
Know the answer?
Add Answer to:
IT Project Management: Chapter 7 Project Cost Management: 1. If the cost estimate will be the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • IT Project Management: Chapter 7 Project Cost Management: 1. In general, ____________________ numbers for cost and...

    IT Project Management: Chapter 7 Project Cost Management: 1. In general, ____________________ numbers for cost and schedule variance indicate problems in those areas. 2. ____ is a project performance measurement technique that integrates scope, time, and cost data. a. Cost baseline b. Earned value management c. Constructive cost modeling d. Parametric modeling 3. Information technology project managers need to be able to present and discuss project information in ____________________ terms as well as in technical terms. 4. Project managers should...

  • As the project manager of a large project, you have just completed the Estimate Costs process....

    As the project manager of a large project, you have just completed the Estimate Costs process. As you begin the Determine Budget process, which of the following would you require as inputs? A. Activity cost estimates, Basis of estimates B. Activity cost estimates, Activity resource estimates C. Resource breakdown structure, Agreements D. Activity cost estimates, Staff management plan

  • 1. Given the statement, “Project Quality Management therefore addresses both the management of the project and...

    1. Given the statement, “Project Quality Management therefore addresses both the management of the project and the product of the project (and its component parts), including the assessment and determination of how the different project management processes interact to fulfill the needs of the project and whether changes or improvements are needed to accomplish the objectives of the project”; discuss how this is applied in quality planning, performing quality assurance, and performing quality control. 2. Given the statement, "There is...

  • Sample Questions (Midterm Exam) Chapter 5 Initiating and Planning Systems Development Projects 1) Who is typically...

    Sample Questions (Midterm Exam) Chapter 5 Initiating and Planning Systems Development Projects 1) Who is typically responsible for performing the PIP process? A) Managers B) Users C) Systems analyst D) The basiness unit 2) What is an example of a project assumption? A) Size B) Potential problems C) Soope D) Complexity Answer: B Difficulty: Difficult AACSB: Information Technology LO: 5.1 Deseribe the steps involved in the project initiation and planning process Classification: Concept 3) What is the tem that describes...

  • IT Project Management: Chapter 13 Project Stakeholder Management 1. One of the main outputs of the...

    IT Project Management: Chapter 13 Project Stakeholder Management 1. One of the main outputs of the _____ process are the issue logs. a. Controlling stakeholder engagement b. Planning stakeholder management c. Identifying stakeholders d. Managing stakeholder engagement 2.  The project team must take corrective action if stakeholders with high interest and high power are categorized as _____. a. leading b. neutral c. supportive d. resistant 3. After identifying and analyzing stakeholders, the project manager and team should develop a(n) ______ to...

  • QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an...

    QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. It describes how the project costs will be planned, structured, and controlled. It is based on project cost estimates and is separate from the project management plan. It may specify the level of precision, which is the...

  • (----Project Management----) Node diagram and an estimated cost The project consists of a 10-story building with...

    (----Project Management----) Node diagram and an estimated cost The project consists of a 10-story building with 100 lamps per floor. The floors are completed in ascending order, and only when the floor is completed can the next one begin. Its brigade consists of experts and electrical assistants with the following characteristics: 1) Costs: Electrician expert ($ 16 / hour) 2)Electrician expert assistant ($ 10 / hour) Production: An electrician expert with an electrician expert assistant can install: Perito installs 16...

  • 1 Which statement describes best why you should document assumptions? a Assumptions might prove to be...

    1 Which statement describes best why you should document assumptions? a Assumptions might prove to be wrong. Knowing which assumptions were incorrect allows baseline adjustments in case of project crisis. b Assumption analysis is a valuable tool and technique to explore the validity of assumptions during risk identification. c Assumptions limit the project management team's options for decision making because they can not be controlled by the team. d In case of schedule or budget overruns, the documentation of assumptions...

  • Identification and explanation of the main cost management problem using the cost management theory, a.   Identification...

    Identification and explanation of the main cost management problem using the cost management theory, a.   Identification of (5) external or internal causes that originates the proposed main cost management problem, b.   What should be Bay Area Health Network’s mission in the context of the proposed main cost management problem and internal and external causes? c.   Propose an adequate ABC analysis for Bay Area Health Network’s situation to answer the questions presented in the case d.   Define (5) cost management strategies...

  • 1) bomar imorgan x > Project Management in Practice x + 532 Project Management in_Practice_6th_6bf4.pdf C...

    1) bomar imorgan x > Project Management in Practice x + 532 Project Management in_Practice_6th_6bf4.pdf C A SE Friendly Assisted Living Facility Project Budget Development-4 Fred Splient gave his ALF Project Steering Committee 2 months to develop a project plan for their area of respon sibility in the project. Each member was told to include the tasks predecessors and successors, resources needed, responsible person, and an estimated cost. He asked that these be presented to the steering team on August...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT