Question

DRAW PERT NETWORK DIAGRAM (urgent)

Amrit Kaul, a web designer, got a contract for developing a website for GSRTC.

Here, is the major task to be completed before the proposal round.

Draw the network diagram for him:


ACTIVITIES

PREVIOUSLY FINISHED ACTIVITIES

A

None   (It does not depend on any prior activity)

B

A

C

A

D

A

E

A, C

F

A, C, E

G

A, C, F

H

C, F, G



0 0
Add a comment Improve this question Transcribed image text
Answer #1

A,B,C,B,D,D,F,F,AS,SDA

source: Cheng
answered by: anonymous
Add a comment
Know the answer?
Add Answer to:
DRAW PERT NETWORK DIAGRAM (urgent)
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • NETWORK SCHEDULING Using the PDM, draw the network diagram, identify the critical path and calculate the...

    NETWORK SCHEDULING Using the PDM, draw the network diagram, identify the critical path and calculate the total project duration. Feel free to verify your answer using MS Project or a similar tool. Activity Dependency Activity Duration (weeks) A B None None AB B F G H 8 9 DE F, G, HI 7 8 5 Draw the Network Diagram using the convention discussed in the class. (If challenged with drawing tools, you can hand draw, take a picture, and paste...

  • CHAPTER 13 / Developing and implementing Effective Accounting Information Systems 431 14 FIGURE 13-11 PERT network...

    CHAPTER 13 / Developing and implementing Effective Accounting Information Systems 431 14 FIGURE 13-11 PERT network diagram for a systems implementation project. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 Activity Prepare the Physical site 3958 Determine functional changes Select and assign personnel Train personnel Acquire and install computer equipment Establish...

  • Given is a PERT project network diagram as shown below: Start End ctivity |StarA KEnd 15...

    Given is a PERT project network diagram as shown below: Start End ctivity |StarA KEnd 15 me 10 13 12 20 a) The Project Completion time = b) The Earliest Start time, ES, of Activity F- c) The Earliest Start time, ES, of Activity K = d) The Latest Start time, LS, of Activity. E = e) The non-critical activities are comma, no space) (ex. type in critical activities as ABCD, no

  • Please help me with this question (( clear draw Please)) Draw the network diagram, including all...

    Please help me with this question (( clear draw Please)) Draw the network diagram, including all calculations of nodes using the following format: Early Start Duration Early Finish Task Name Late Sta rt Slack Late Finish List the networkpaths below: Determine the criticalpath(s). What is it and what is its duration? Activity Duration Dependency Start 0 A 6 Start B 1 A C 3 A,B D 5 A, B E 12 Start F 4 D, E G 2 C, F...

  • Hi, Please draw the network diagram. Activity D on a CPM network has predecessors B and...

    Hi, Please draw the network diagram. Activity D on a CPM network has predecessors B and C, and has successor F. D has duration 6. B's earliest finish is 18, while C's is 20. F's late start is 26. Which of the following is definitely true? A) B is a critical activity. B) C is completed before B. C) D has no slack but is not critical. D) D is critical, and has zero slack. E) F is critical, and...

  • For the activities given in the table: Draw the AOA network diagram Find the critical activities...

    For the activities given in the table: Draw the AOA network diagram Find the critical activities Find the critical path Find the project completion time Time (days) Predecessors Activity Description Initial Paperwork A 3 Build Body B A 3 C Build Frame A 2 Finish Body 3 D E Finish Frame C Final Paperwork B,C 3 G Mount Body to Frame D,E 6 Install Skirt on Frame C 2 H A FLO For the activities given in the table: Draw...

  • Given is a PERT project network diagram as shown below. Start D Activity Start ABCDEFGH End...

    Given is a PERT project network diagram as shown below. Start D Activity Start ABCDEFGH End Time 0 1.35 3.65 4.327 .36 8.25 1.394 .68 3.250 a) The Project Completion time = (in 2 decimal places) b) The Earliest Start time, Es, of Activity G- (in 2 decimal places) c) The Latest Finish time, LF, of Acitivity C (in 2 decimal places) d) The critical activities are (ex. type in critical activities as ABCD no comma, no space)

  • 1. Draw the network diagram Precedences and Durations for a Seven Activity Project Activity Description Predecessors...

    1. Draw the network diagram Precedences and Durations for a Seven Activity Project Activity Description Predecessors Duration Preliminary design Evaluation of design Contract negotiation Preparation of fabrication plantC Final design Fabrication of Product D B, C D, E 12 G Shipment of Product to ownerF

  • 1. For the following schedule, Draw the AON network diagram for the project and calculate the...

    1. For the following schedule, Draw the AON network diagram for the project and calculate the schedule. а. Summarize the schedule in a tabular form, showing ES, EF, LS, LF, TF, and FF for each activity b. Denote the critical path on the network. C. d. Perform a cost analysis based on an early start, late start, and target schedule for the project. Plot the cumulative cost distribution for the three S-curves on one graph. e. f. Plot the cumulative...

  • 1. Draw the network diagram Precedences and Durations for a Seven Activity Project Activity Description Predecessors Du...

    1. Draw the network diagram Precedences and Durations for a Seven Activity Project Activity Description Predecessors Duration Preliminary design Evaluation of design Contract negotiation Preparation of fabrication plantC Final design Fabrication of Product D B, C D, E 12 G Shipment of Product to ownerF

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT