Multiple Production Department Factory Overhead Rates
The total factory overhead for Bardot Marine Company is budgeted for the year at $505,500, divided into two departments: Fabrication, $321,000, and Assembly, $184,500. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require two direct labor hours in Fabrication and two direct labor hours in Assembly. The bass boats require two direct labor hours in Fabrication and four direct labor hours in Assembly. Each product is budgeted for 3,000 units of production for the year.
When required, round all per unit answers to the nearest cent.
a. Determine the total number of budgeted direct labor hours for the year in each department.
| Fabrication | direct labor hours |
| Assembly | direct labor hours |
b. Determine the departmental factory overhead rates for both departments.
| Fabrication | $ per dlh |
| Assembly | $ per dlh |
c. Determine the factory overhead allocated per unit for each product using the department factory overhead allocation rates.
| Speedboat: | $ per unit |
| Bass boat: | $ per unit |
| Fabrication: | |||
| Speedboat | Bass boat | Total | |
| Budgeted production | 3000 | 3000 | |
| X Direct labor hours per unit | 2 | 2 | |
| Total direct labor hours | 6000 | 6000 | 12000 |
| Assembly : | |||
| Speedboat | Bass boat | Total | |
| Budgeted production | 3000 | 3000 | |
| X Direct labor hours per unit | 2 | 4 | |
| Total direct labor hours | 6000 | 12000 | 18000 |
| a | |||
| Fabrication | 12000 | direct labor hours | |
| Assembly | 18000 | direct labor hours | |
| b | |||
| Fabrication | 26.75 | per dlh | =321000/12000 |
| Assembly | 10.25 | per dlh | =184500/18000 |
| c | |||
| Speedboat | 74.00 | per unit | =(2*26.75)+(2*10.25) |
| Bass boat | 94.50 | per unit | =(2*26.75)+(4*10.25) |
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted...
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted for the year at $495,000, divided into two departments: Fabrication, $382,500, and Assembly, $112,500. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require four direct labor hours in Fabrication and three direct labor hours in Assembly. The bass boats require two direct labor hours in Fabrication and two direct labor hours in Assembly. Each product is budgeted for 3,000...
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted for the year at $1,365,000, divided into two departments: Fabrication, $1,071,000, and Assembly, $294,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require four direct labor hours in Fabrication and three direct labor hours in Assembly. The bass boats require two direct labor hours in Fabrication and one direct labor hour in Assembly. Each product is budgeted for 7,000...
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted for the year at $1,481,250, divided into two departments: Fabrication, $881,250, and Assembly, $600,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require one direct labor hour in Fabrication and four direct labor hours in Assembly. The bass boats require four direct labor hours in Fabrication and four direct labor hours in Assembly. Each product is budgeted for 7,500...
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted for the year at $810,875, divided into two departments: Fabrication, $453,375, and Assembly, $357,500 Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require one direct labor hour in Fabrication and four direct labor hours in Assembly. The bass boats require two direct labor hours in Fabrication and one direct labor hour in Assembly. Each product is budgeted for 6,500...
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted for the year at $528,750, divided into two departments: Fabrication, $363,750, and Assembly, $165,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require two direct labor hours in Fabrication and two direct labor hours in Assembly. The bass boats require one direct labor hour in Fabrication and one direct labor hour in Assembly. Each product is budgeted for 5,000...
The total factory overhead for Bardot Marine Company is budgeted for the year at $897,000, divided into two departments: Fabrication, $711,000, and Assembly, $186,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require three direct labor hours in Fabrication and three direct labor hours in Assembly. The bass boats require three direct labor hours in Fabrication and one direct labor hour in Assembly. Each product is budgeted for 6,000 units of production for the year....
The total factory overhead for Bardot Marine Company is budgeted for the year at $1,027,000, divided into two departments: Fabrication, $526,500, and Assembly, $500,500. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require one direct labor hour in Fabrication and three direct labor hours in Assembly. The bass boats require two direct labor hours in Fabrication and four direct labor hours in Assembly. Each product is budgeted for 6,500 units of production for the year....
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted for the year at $723,375, divided into two departments: Fabrication, $588,000, and Assembly, 5138,375. Bardot Marine manufactures two types of boats speedboats and bass boats. The speedboatsregione director hour is Fabrication and one director hour in Assembly. The bes t require four direct labor hours in Fabrication and two drector hours in Assembly. Each product is budgeted for 4.500 units of production for the...
2. Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted for the year at $1,238,250, divided into two departments: Fabrication, $1,053,000, and Assembly, $185,250. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require two direct labor hours in Fabrication and two direct labor hours in Assembly. The bass boats require four direct labor hours in Fabrication and one direct labor hour in Assembly. Each product is budgeted for...
BE 4-2 Multiple production department factory overhead rates Obj. 3 The total factory overhead for Bardot Marine Company is budgeted for the year at $600,000 divided into two departments: Fabrication, $420,000, and Assembly, $180,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require 8 direct labor hours in Fabrication and 4 direct labor hours in Assembly. The bass boats require 4 di- rect labor hours in Fabrication and 8 direct labor hours in Assembly. Each...