Question

24) Mongar Corporation applies manufacturing overhead to products on the basis of standard machine-hours. Budgeted and...

24) Mongar Corporation applies manufacturing overhead to products on the basis of standard machine-hours. Budgeted and actual overhead costs for the most recent month appear below:

Original Budget Actual Costs
Variable overhead costs:
Supplies $ 7,980 $ 8,230
Indirect labor 29,820 29,610
Total variable manufacturing overhead cost $ 37,800 $ 37,840

The original budget was based on 4,200 machine-hours. The company actually worked 4,350 machine-hours during the month and the standard hours allowed for the actual output were 4,190 machine-hours. What was the overall variable overhead efficiency variance for the month?

  • $130 Unfavorable

  • $950 Favorable

  • $1,440 Unfavorable

  • $1,310 Favorable

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer- The overall variable overhead efficiency variance for the month = was = $1,440 Unfavorable.

Explanation- Variable overhead efficiency variance=(Standard hours–Actual working hours)*Standard Rate

= ($4190 hours - $4350 hours)*($37800/4200 hours)

= ($4190 hours - $4350 hours)*$9 per hour

= $ 1440 Unfavorable

Add a comment
Know the answer?
Add Answer to:
24) Mongar Corporation applies manufacturing overhead to products on the basis of standard machine-hours. Budgeted and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Lossing Corporation applies manufacturing overhead to products on the basis of standard machine-hours. Budgeted and actual...

    Lossing Corporation applies manufacturing overhead to products on the basis of standard machine-hours. Budgeted and actual overhead costs for the most recent month appear below: Original Budget Actual Costs $ $ 7,800 10,720 7,990 10,070 Variable overhead costs: Supplies Indirect labor Fixed overhead costs: Supervision Utilities Factory depreciation Total overhead cost 15,610 14,900 59,970 $109,000 14,490 14,950 61,040 $108,540 The company based its original budget on 7,800 machine-hours. The company actually worked 7,760 machine-hours during the month. The standard hours...

  • Behring Corporation applies manufacturing overhead to products on the basis of standard machine-hours. Budgeted and actual...

    Behring Corporation applies manufacturing overhead to products on the basis of standard machine-hours. Budgeted and actual fixed manufacturing overhead costs for the most recent month appear below: Original Budget Actual Costs   Fixed overhead cost:   Supervision $4,680     $4,800       Utilities 6,120     5,820       Factory depreciation 21,240     20,720       Total fixed manufacturing overhead cost $32,040     $31,340    The company based its original budget on 3,600 machine-hours. The company actually worked 3,570 machine-hours during the month. The standard hours...

  • Wadding Corporation applies manufacturing overhead to products on the basis of standard machine-hours. For the most...

    Wadding Corporation applies manufacturing overhead to products on the basis of standard machine-hours. For the most recent month, the company based its budget on 4,600 machine-hours. Budgeted and actual overhead costs for the month appear below: Original Budget Based on 4,600 Machine-Hours Actual Costs Variable overhead costs: Supplies $ 11,880 $ 12,830 Indirect labor 40,100 40,800 Fixed overhead costs: Supervision 20,700 20,340 Utilities 6,900 6,870 Factory depreciation 7,900 8,210 Total overhead cost $ 87,480 $ 89,050 The company actually worked...

  • Wadding Corporation applies manufacturing overhead to products on the basis of standard machine hours. For the...

    Wadding Corporation applies manufacturing overhead to products on the basis of standard machine hours. For the most rec overhead costs for the month appear below month the company based its budget on 4000 machine hours, Budgeted and actual Original Budget Based on 4,000 Machine Hours Actual Costs Variable overhead costs: Supplies $11,200 32,000 $12,230 32.200 Fixed overhead costs 20,100 6,300 6,210 Utilities Factory depreciation Total overhead cost 576.900 $77,990 The company actually worked 4320 machine hours during the month. The...

  • rporation applies manufacturing overhead to products on the basis of standard machine-hours. production are shown below:...

    rporation applies manufacturing overhead to products on the basis of standard machine-hours. production are shown below: BudgetActual 778 3,900 720 Units produced Machine-hours 3,600 Variable MOH S 38,160 S39,800 or the month, the variable overhead efficiancy variance was closest to: 1,540 Favorable B. C. D. 3,180 Unfavorable 106 Unfavorable 102 Unfavorable E. None of the above. 20 Skie Inc produces a single product and uses a standard costing system applying manufacturing overhead based or allowed for actual output. At the...

  • Bartoletti Fabrication Corporation has a standard cost system in which it applies manufacturing overhead to products...

    Bartoletti Fabrication Corporation has a standard cost system in which it applies manufacturing overhead to products on the basis of standard machine-hours (MHs) at $9.10 per MH. The company had budgeted its fixed manufacturing overhead cost at $70,000 for the month. During the month, the actual total variable manufacturing overhead was $66,720 and the actual total fixed manufacturing overhead was $72,00O. The actual level of activity for the period was 6,500 MHs. What was the total of the variable overhead...

  • Lancelot Corporation manufactures tennis gear and uses budgeted machine - hours to allocate variable manufacturing over...

    Lancelot Corporation manufactures tennis gear and uses budgeted machine - hours to allocate variable manufacturing overhead. The following information relates to the company's manufacturing overhead data: Budgeted output units Budgeted machine - hours Budgeted variable manufacturing overhead costs for 3,000 units 3,000 units 15,000 hours $172,500 Actual output units produced Actual machine - hours used Actual variable manufacturing overhead costs 3,250 units 14,500 hours $230,000 What is the flexible - budget variance for variable manufacturing overhead? O A. $43,125 favorable...

  • Webb, Inc. uses a flexible budget for manufacturing overhead based on machine hours. Variable manufacturing overhead...

    Webb, Inc. uses a flexible budget for manufacturing overhead based on machine hours. Variable manufacturing overhead costs per machine hour are as follows: $5.00 2.50 Indirect labor Indirect materials Maintenance Utilities .50 .30 Fixed overhead costs per month are: Supervision Insurance Property taxes Depreciation $1,200 400 600 1,800 The company believes it will normally operate in a range of 4,000 to 8,000 machine hours per month. During the month of August, 2019, the company incurs the following manufacturing overhead costs:...

  • Wangerin Corporation applies overhead to products based on machine-hours. The denominator level of activity is 7,700...

    Wangerin Corporation applies overhead to products based on machine-hours. The denominator level of activity is 7,700 machine-hours. The budgeted fixed manufacturing overhead costs are $274,890. In April, the actual fixed manufacturing overhead costs were $280,280 and the standard machine-hours allowed for the actual output were 8,000 machine-hours. Required: a. Compute the budget variance for April. b. Compute the volume variance for April. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no...

  • Wangerin Corporation applies overhead to products based on machine-hours. The denominator level of activity is 8,900...

    Wangerin Corporation applies overhead to products based on machine-hours. The denominator level of activity is 8,900 machine-hours. The budgeted fixed manufacturing overhead costs are $328,410. In April, the actual fixed manufacturing overhead costs were $334,640 and the standard machine-hours allowed for the actual output were 9,200 machine-hours. Required: a. Compute the budget variance for April. b. Compute the volume variance for April. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT