Question

Describe a master production schedule (MPS) and compute available-to-promise quantities.

Describe a master production schedule (MPS) and compute available-to-promise quantities.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The MPS in an organization forms the basis of communication between sales and manufacturing. Using the MPS as a contract between sales and production means that sales can make valid order promises. MPS is a dynamic plan and can be changed when there are changes in demand or capacity. It decides what products are manufactured and when
MPS integrated with an ERP helps in planning, extracting actual supply and demand data, forecasting, delivering accurate and timely production plans that help manufacturers achieve their production objectives and reduce costs.

The functions of Master Production Schedule are:
1.   To translate aggregate plans into specific end items
2.   Evaluate alternative schedules
3.   Generate material requirement:
4.   Generate capacity requirements:
5.   Facilitate information processing
6.   Effective utilization of capacity
The inputs to MPS are
•   Capacity constraint
•   Production Policies
•   Product Characteristics
•   Planned Orders
•   Forecast demand
•   Current and planned
•   Availability
•   Planning Horizon
•   Calendar

Output of MPS
•   When and how much to produce each product
•   Capacity planning

Available-to-Promise is a report for each MPS line item. The report is time-phased, and reports are generated monthly

Its is a tool used to show the inventory that is not reserved for existing customer orders and is available for the sales team to Promise to other customers
The Available to Promise formula is:

on hand = quantity on hand
supply = planned orders,
demand = sales orders, component demand

Add a comment
Know the answer?
Add Answer to:
Describe a master production schedule (MPS) and compute available-to-promise quantities.
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Quantities in the MPS row of the master production schedule correspond to ________ in the requirements...

    Quantities in the MPS row of the master production schedule correspond to ________ in the requirements schedules of their immediate inputs in the bill of materials. a. Scheduled Receipts b. Planned Order Receipts c. Gross Requirements d. None of the above

  • Prepare a master schedule and an available to promise table given customer orders below. MPS is...

    Prepare a master schedule and an available to promise table given customer orders below. MPS is 85 units, and the company has 150 units to begin with. Forecast for the eight-period work duration is 75 units.                 Week 1 2 3 4 5 6 7 8 Customer Order 75 85 90 48 55 72 88 90

  • Q1. Develop a Master Production Schedule (MPS) The Forecast is 84 units for first period and...

    Q1. Develop a Master Production Schedule (MPS) The Forecast is 84 units for first period and 80 for the second period, and 60 units for each of the next three periods. The starting Inventory is 20 units. The company uses lot size of 50 units. Committed Orders are as follows: What is the available to promise? Period Customer Orders 1 82 2 82 3 58 4 40 5 20 Q2 Complete the following problem. There are 20 on hand and...

  • The Master Production Schedule quantity ________. a. Is equal to Customer Orders b. Is equal to...

    The Master Production Schedule quantity ________. a. Is equal to Customer Orders b. Is equal to the higher of the Forecast and Customer Orders quantities c. Depends on the Available to Promise quantity d. None of the above

  • Prepare a master production schedule for industrial pumps in the manner of the following ta Use...

    Prepare a master production schedule for industrial pumps in the manner of the following ta Use the MPS rule to "schedule production when the projected on-hand inventory would be le than 10 without production". Suppose that there are currently 64 pumps in inventory and a production lot size of 70 pumps is used. 30 33 Week Forecast Customer orders (committed) Projected on- hand inventory MPS 0 Available to promise (ATP) 70 51 Question 29 (3 points) What is the projected...

  • needing help with Excel 3. Complete the master production schedule based on the following information: 1...

    needing help with Excel 3. Complete the master production schedule based on the following information: 1 4 9 2 3 320 100 30 60 50 80 110 5 6 7 40 240 290 60 60 60 410 20 Week Forecast Customer Orders Projected On-Hand Inventory MPS Released MPS Due Available to Promise (ATP) Additional Information: On-hand inventory: 600 Schedule production whenever projected on-hand inventory drops below 30 MPS lot size: 300 Production lead time or lead time for MPS releases:...

  • Prepare a master production schedule for industrial pumps in the manner of the following table. U...

    Prepare a master production schedule for industrial pumps in the manner of the following table. Use the MPS rule to "schedule production when the projected on-hand inventory would be less than 10 without production, Suppose that a production lot size of 70 pumps is used (Leave no cells blank- be certain to enter "O wherever required.) June 64 Forecast Customer orders (commitied) Projected on-hand inventory MPS ATP 30 30 40 40 30 20 30 10 References eBook & Resources Worksheet...

  • i need help with 32-35 ASAP CONSIDER THE FOLLOWING PARTIALLY COMPLETED TIME-PHASED MASTER PRODUCTION SCHEDULE FOR...

    i need help with 32-35 ASAP CONSIDER THE FOLLOWING PARTIALLY COMPLETED TIME-PHASED MASTER PRODUCTION SCHEDULE FOR OUESTIONS 32-35 MPS QTY 20 On Hand 20 Lead Time 1 period 2 3 6 4 10 Forecast 10 10 10 10 10 10 Orders 12 5 9 5 Available 2 10 Available to Promise MPS 2 O (Received) 20 Ordered 32 The available value for week 1 should be 6 h 3 10 20 33 The available value for period 2 is 20...

  • Assignment 8 is due on Sunday 8/2 at 11:00 AM Complete the following MPS record and...

    Assignment 8 is due on Sunday 8/2 at 11:00 AM Complete the following MPS record and find out what is the available-to-promise. There are 20 units in beginning inventory and the lot size is 50. Answer in Excel and submit your answer in the drop box. Period 1 2 3 4 5 6 Forecast 20 22 23 20 25 20 Customers order (committed) 21 20 21 23 208 POH (Projected on hand) MPS (Master production schedule) ATP (Available-to-promise)

  • . Canvas ©OSA The master production schedule (MPS) translates the sales & operationsplan (SOP) into: Specific...

    . Canvas ©OSA The master production schedule (MPS) translates the sales & operationsplan (SOP) into: Specific production orders Forecast demand Specific production plan Efficient lot sizes Question 25 A precedent relationship shows... The number of components required to produce an item The order in which production steps must be accomplished Only the first step of the production process Only the final step of the production process Question 26 In a material requirements planning (MRP) system, gross requirements are time phased,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT