CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS
A firm with a WACC of 10% is considering the following mutually exclusive projects:
0 | 1 | 2 | 3 | 4 | 5 |
Project 1 | -$400 | $45 | $45 | $45 | $230 | $230 |
Project 2 | -$650 | $200 | $200 | $40 | $40 | $40 |
Which project would you recommend?
Select the correct answer.
|
|||
|
|||
|
|||
|
|||
|
Project 1:
Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)
=45/1.1+45/1.1^2+45/1.1^3+230/1.1^4+230/1.1^5
=411.81
NPV=Present value of inflows-Present value of outflows
=411.81-$400
=$11.81(Approx).
Project 2:
Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)
=200/1.1+200/1.1^2+40/1.1^3+40/1.1^4+40/1.1^5
=429.32
NPV=Present value of inflows-Present value of outflows
=429.32-$650
=$(220.68)(Approx).(Negative).
Hence Project 1 must be selected having higher and positive NPV.
Hence the correct option is:
d. Project 1, since the NPV1 > NPV2.
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the...
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$200 $60 $60 $60 $225 $225 Project 2 -$500 $200 $200 $50 $50 $50 Which project would you recommend? Select the correct answer. I. Project 1, since the NPV1 > NPV2. II. Neither A or B, since each project's NPV < 0. III. Both Projects 1 and 2, since both projects have...
A firm with a WACC of 10% is considering the following mutually exclusive projects: o 1 2 3 4 5 Project 1 Project 2 -$200 -$700 $75 $350 $75 $350 $75 $100 $230 $100 $230 $100 Which project would you recommend? Select the correct answer. a. Both Projects 1 and 2, since both projects have NPV's > 0. Ob. Project 2, since the NPV2 > NPV1. Oc. Neither Project 1 nor 2, since each project's NPV < 0. O d....
aptel Ed-or-Chapter Problems Problem 11-10 Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the following mutually exclusive projects: 2 3 5 Project 1 Project 2 -$400 $65 $65 $65 $200 $200 -$400 $250 $250 $50 $50 $50 Which project would you recommend? Select the correct answer. 1. Project 1, since the NPV1> NPV2 II. Both Projects 1 and 2, since both projects have IRR's> 0. III. Project 2, since the NPV2> NPV1 IV....
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$400 $55 $55 $55 $205 $205 Project 2 -$650 $250 $250 $150 $150 $150 Which project would you recommend? Select the correct answer. a. Project 1, since the NPV1 > NPV2. b. Both Projects 1 and 2, since both projects have IRR's > 0. c. Both Projects 1 and 2, since both projects have NPV's > 0. d....
A firm with a WACC of 10% is considering the following mutually exclusive projects: $55 $120 $215 $120 $215 $120 Project 1 - $500 $55 $55 Project 2 - $650 $300 $300 Which project would you recommend? Select the correct answer. O O O a. Both Projects 1 and 2, since both projects have NPV's > 0. b. Project 2, since the NPV2 > NPV1. c. Neither Project 1 nor 2, since each project's NPV < 0. O d. Project...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$450 $40 $40 $40 $165 $165 Project 2 -$450 $350 $350 $110 $110 $110 Which project would you recommend? Select the correct answer. a. Both Projects 1 and 2, since both projects have IRR's > 0. b. Project 2, since the NPV2 > NPV1. c. Neither Project 1 nor 2, since each project's NPV < 0. d. Project...
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project A -$250 $80 $80 $80 $215 $215 Project B -$550 $350 $350 $40 $40 $40 Which project would you recommend? Select the correct answer. I. Project A, since the NPVA > NPVB. II. Neither A or B, since each project's NPV < 0. III. Project B, since the NPVB > NPVA. IV. Both...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 Project 2 -$200 -$700 $80 $200 $80 $200 $80 $120 $170 $120 $170 $120 Which project would you recommend? Select the correct answer. a. Both Projects 1 and 2, since both projects have NPV's > 0. O b. Project 1, since the NPV1 > NPV2. O c. Both Projects 1 and 2, since both projects have IRR's >...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 12 3 4 5 $40 $150 $165 $150 $165 $150 Project 1 -$450 $40 $40 Project 2 -$600 $200 $200 Which project would you recommend? Select the correct answer. O O O O O a. Project 1, since the NPV, > NPV2. b. Both Projects 1 and 2, since both projects have IRR's > 0. c. Both Projects 1 and 2, since both projects have NPV's...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$500 $70 $70 $70 $215 $215 Project 2 -$400 $300 $300 $65 $65 $65 Which project would you recommend? Select the correct answer. a. Project 2, since the NPV2 > NPV1. b. Neither Project 1 nor 2, since each project's NPV < 0. c. Both Projects 1 and 2, since both projects have NPV's > 0. d. Project...