On December 31, 2017, Tri-State Construction Inc. signs a contract with the state of West Virginia Department of Transportation to manufacture a bridge over the New River. State anticipates the construction will take three years. The company’s accountants provide the following contract details relating to the project:
|
Contract price |
$780 million |
|
Estimated construction costs |
$600 million |
|
Estimated total profit |
$180 million |
During the three-year construction period, Tri-State incurred costs as follows:
|
2018 |
$ 60 million |
|
2019 |
$360 million |
|
2020 |
$180 million |
Compute the revenue recognized, construction costs expensed, and income earned for each year using the cost-to-cost method.
Cost to cost method
Step 1
Calcuation of percentage completion
Percentage completion = Cost incured to date / Estimated total cost
For year 2018;
Percenatge completion = $ 60 million / $ 600 million
= 10 %
For year 2019;
Percentage completion = $ 360 million / $ 600 million
= 60%
For year 2020;
Percentage completion = $ 180 million / $ 600 million
= 30%
| YEAR | PERCENTAGE COMPLETION ( %) |
| 2018 | 10 |
| 2019 | 60 |
| 2020 | 30 |
Step 2
Calculation of revenue recognized, construction cost expensed & income earned for each year
For Year 2018;
Revenue recognized = Contract price * percentage completed
= $ 780 million * 10%
= $ 78 million
Construction cost expensed = $ 60 million ( given in question)
Income earned = Revenue recognized for the year - construction cost expensed for the year
= $ 78 million - $ 60 million
= $ 18 million
For year 2019;
Revenue recognized = $ 780 million * 60%
= $ 468 million
Construction cost expensed = $ 360 million
Income earned = $ 468 million - $ 360 million
= $ 108 million
For year 2020;
Revenue recognized = $ 780 million * 30%
= $ 234 million
Construction cost expensed = $ 180 million
Income earned = $ 234 million - $ 180 million
= $ 54 million
On December 31, 2017, Tri-State Construction Inc. signs a contract with the state of West Virginia...
In 2010, Concrete Inc. began a three year construction contract for $3,500,000. Cement uses the percentage-of-completion method. The income to be recognized each year is based on the proportion of costs incurred to total estimated costs for completing the contract. The financial statement presentation relating to this contract for calendar 2010 follow: Statement of Financial Position Current Assets: Accounts receivable $150,000 Contract asset/liability 105,000 (Contract cost $425,000 less Billings of $320,000) Income Statement Income (before tax) on the contract recognized...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 60 $ 120 $ 70 Estimated costs to complete as of...
Question 2 Ivanhoe Construction entered into a contract to construct a bridge for a contract price of $2.80 million. Construction began in 2019 and was completed in 2021. Below are the details of the transactions related to the contract: 2019 2020 $653,000 $806,000 1,436,600 541,000 2021 $709,900 Costs incurred during the year Estimated costs to complete Calculate the revenue, expenses and gross profit to be recognized each year using the percentage-of-completion method. (Round the percentage completion to 2 decimal places,...
On June 15, 2021, Sanderson Construction entered into a
long-term construction contract to build a baseball stadium in
Washington, D.C., for $370 million. The expected completion date is
April 1, 2023, just in time for the 2023 baseball season. Costs
incurred and estimated costs to complete at year-end for the life
of the contract are as follows ($ in millions):
2021
2022
2023
Costs incurred during the year
$
70
$
110
$
80
Estimated costs
to complete as of...
In 2020, Cement Inc. began a three year construction contract for $3,500,000. Cement uses the percentage-of-completion method. The income to be recognized each year is based on the proportion of costs incurred to total estimated costs for completing the contract. The financial statement presentation relating to this contract for calendar 2020 follow: Statement of Financial Position Current Assests: Accounts receivable $150,000 Contract asset/liability 105,000 (Contract costs $425,000 less Billings of $320,000) Income Statement Income (before tax) on the contract recognized...
Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It is estimated that the complex will take 3 years to construct. Additional information follows. Estimated cost of complex Contract price AA 600,000 900,000 The following data pertain to the construction period. 2019 610,000 $ 6100 A 2017 270,000 330,000 270,000 240,000 2018 450,000 150,000 550,000 500,000 Costs to date Estimated costs to complete Progress billings to date Cash collected to date $...
In 2018, the West $10,000,000. gate Construction Company entered into a contract to construct a road for Santa Clara County for The road was completed in 2020. Information related to the contract is as follows: 2020 2018 2,542,000 $3,772,000 $2,074,600 5, 658,000 1,886,000 2,020,000 4,294,000 3,686,000 1,810,000 3,800,000 4,390,000 2019 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of...
Queens Construction Company commences construction of a harbour on 1 July 2020. It signs a fixed-price contract for total revenue of $400 million. The project is expected to be completed by the end of June 2023. The expected cost at the commencement of construction was $300 million. The expected costs to complete a construction project can change throughout the project. The following data relates to the project: 2021 2022 2023 ($ M) ($ M) ($ M) Costs for the year...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year Estimated costs to complete as of December 31 S 30 140 $40...
n 2016, Long Construction Corporation began construction work under a three-year contract. The contract price is $1,600,000. Long recognizes revenue over time according to percentage of completion for financial reporting purposes. The financial statement presentation relating to this contract at December 31, 2016, is as follows: Balance Sheet Accounts receivable (from construction progress billings) $ 30,000 Construction in progress $ 100,000 Less: Billings on construction contract (94,000 ) Cost and profit of uncompleted contracts in excess of billings 6,000 Income...