Q1) The objective function is
e. Maximize Z = 50 A + 45 B
The objective is to maximize the total profit
Q2)
The objective is to minimise the total cost.Therefore, objective
function is
c.Minimize Z = 30 Q + 37 R + 78 S
Q3)
The maximum possible machine hours is 5000. Following is a
constraint
e.9 D + 3 E = < 5,000
A company wants to determine how many units of each of two products, A and B,...
LINEAR PROGRAMMING PROBLEM 2. A production manager wants to determine how many units of each product to produce weekly to maximize weekly profits. Production requirements for the products are shown in the following table. Product Material 1 (lbs.) Material 2 (lbs.) Labor (hours) A 3 2 4 B 1 4 2 C 5 none 3.5 Material 1 costs $7 a pound, material 2 costs $5 a pound, and labor costs $15 per hour. Product A sells for $101 a unit,...
State the linear programming problem in mathematical terms, identifying the objective function and the constraints A firm makes products A and B. Product A takes 3 hours each on machine L and machine M; product B takes 4 hours on L and 3 hours on M. Machine L can be used for 12 hours and M for 10 hours. Profit on product A is $7 and $9 on B. Maximize profit. Maximize 7A 9B Subject to: 3A +4B s 12...
Betty DeRose, Inc. produces and sells two products, L and V. Last month, Betty produced and sold 6,000 units of Product L and 4,000 units of Product V. Cost and revenue information for the two products from last month appears below: selling price per unit ........... variable costs per unit .......... Product L $8.00 $3.00 Product V $9.00 $5.00 For the coming month, Betty would like to use linear programming in order to maximize monthly profits. Each month Betty has...
Betty DeRose, Inc. produces and sells two products, L and V. Last month, Betty produced and sold 6,000 units of Product L and 4,000 units of Product V. Cost and revenue information for the two products from last month appears below: Product L Product V selling price per unit ........... $8.00 $9.00 variable costs per unit .......... $3.00 $5.00 For the coming month, Betty would like to use linear programming in order to maximize monthly profits. Each month Betty has...
the question: a firm makes products A and B. Product A takes 2
hours each on kachine L and machine M; product B takes 4 hours on L
and 2 hours on M. Machine L can ve used no more than 12 hours per
day and M no longer than 8 hours per day. Profit A is $9 and $6 on
B. profit is to be maximized. which of the following correctly
identifies the objective function of the constraints?
This...
Betty DeRose, Inc, produces and sells two products, L and V. Revenue and cost information for the two products from last month appear below: selling price per unit variable costs per unit Product L $15.00 S 8.00 Product V $12.00 $ 7.00 For the coming to maximize monthly profits. month, Betty would like to use linear programming in order Each month Betty has 80,000 direct Labor hours available and 60,000 machine hours avaiLable. Product L requires 5 direct labor hours...
Broadway Sports Products wants to determine the number of All-Pro (A) and College (C) footballs to produce in order to maximize profit over the next four-week planning horizon. Constraints affecting the production quantities are the production capacities in three departments: cutting and dyeing; sewing; and inspection and packaging. For the four-week planning period, 340 hours of cutting and dyeing time, 420 hours of sewing time, and 200 hours of inspection and packaging time are available. All-Pro footballs provide a profit...
The Surest Concrete Company produces cement in a continuous process. Two ingredients in the cement are sand, which Surest purchases for $8 per ton, and gravel, which costs $10 per ton. The other ingredients are lumped together and referred to as “Other”. The cost of the other ingredients is $7 per ton. No more than 40 percent of the cement can be sand, and at least 30 percent of the cement must be gravel. The maximum amount of gravel available is 100 tons. The...
Zapit, Inc. manufactures two products, Product A and Product B. Product A yields an incremental profit of $2 per unit, and Product B yields an incremental profit of $4. Product A requires four hours of processing at Machine A and two hours at Machine B. Product B requires six hours at Machine A, six hours at Machine B, and one hour at Machine C. Machine A has a maximum of 120 hours of available capacity per day, Machine B has...
D. The Smith Company produces four products. The company has limited labor - only 10,000 hours are available this month. Product A Product B Product C Product D 240 195 30 100 $110$200$300 Selling price Variable cost per unit Direct labor hours per unit Demand (units) $100 $170 $250 20 10 100 200 300 Required: How many of each product should be sold to maximize profit? E.) The Smith Company produces four products. The company has limited machine time -...