Question

A company wants to determine how many units of each of two products, A and B,...

  1. A company wants to determine how many units of each of two products, A and B, they should produce. The profit on product A is $50 and the profit on product B is $45. Applying linear programming to this problem, which of the following is the objective function if the firm wants to make as much money as possible?
  1. Maximize Z = A/45B + B/50A
  2. Minimize Z = 50 A + 45 B
  3. Maximize Z = A + B                       
  4. Minimize Z = A + B
  5. Maximize Z = 50 A + 45 B

  1. An agribusiness company mixes and sells chicken feed to farmers. The costs of the chicken feed ingredients vary throughout the chicken feeding season but the selling price of chicken feed is independent of the ingredients. On August 1, management needs to know how many units of each of three grains (Q, R, and S) should be included in their chicken feed in order to produce the product most economically. The cost of each grain is, for a unit of Q, $30; for a unit of R, $37; and for a unit of S, $78. Applying linear programming to this problem, which of the following is the objective function?
  1. Minimize Z = (Q × R × S)/3
  2. Maximize Z = Q + R + S
  3. Minimize Z = 30 Q + 37 R + 78 S
  4. Minimize Z = Q + R + S
  5. Maximize Z = 30 Q + 37 R + 78 S

  1. Apply linear programming to this problem. A firm wants to determine how many units of each of two products (products D and E) they should produce to make the most money. The profit in the manufacture of a unit of product D is $100 and the profit in the manufacture of a unit of product E is $87. The firm is limited by its total available labor hours and total available machine hours. The total labor hours per week are 4,000. Product D takes 5 hours per unit of labor and product E takes 7 hours per unit. The total machine hours are 5,000 per week. Product D takes 9 hours per unit of machine time and product E takes 3 hours per unit. Which of the following is one of the constraints for this linear program?
  1. 9 D + 3 E = > 4,000
  2. 5 D + 7 E = < 5,000
  3. 5 D + 7 E = 4,000
  4. 5 D + 9 E = < 5,000
  5. 9 D + 3 E = < 5,000
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Q1) The objective function is
e. Maximize Z = 50 A + 45 B

The objective is to maximize the total profit

Q2)
The objective is to minimise the total cost.Therefore, objective function is
c.Minimize Z = 30 Q + 37 R + 78 S

Q3)
The maximum possible machine hours is 5000. Following is a constraint
e.9 D + 3 E = < 5,000

Add a comment
Know the answer?
Add Answer to:
A company wants to determine how many units of each of two products, A and B,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • LINEAR PROGRAMMING PROBLEM 2. A production manager wants to determine how many units of each product...

    LINEAR PROGRAMMING PROBLEM 2. A production manager wants to determine how many units of each product to produce weekly to maximize weekly profits. Production requirements for the products are shown in the following table. Product          Material 1 (lbs.)           Material 2 (lbs.)         Labor (hours) A                         3                                 2                            4 B                         1                                 4                            2 C                         5                                 none                       3.5 Material 1 costs $7 a pound, material 2 costs $5 a pound, and labor costs $15 per hour. Product A sells for $101 a unit,...

  • State the linear programming problem in mathematical terms, identifying the objective function and the constraints A...

    State the linear programming problem in mathematical terms, identifying the objective function and the constraints A firm makes products A and B. Product A takes 3 hours each on machine L and machine M; product B takes 4 hours on L and 3 hours on M. Machine L can be used for 12 hours and M for 10 hours. Profit on product A is $7 and $9 on B. Maximize profit. Maximize 7A 9B Subject to: 3A +4B s 12...

  • Betty DeRose, Inc. produces and sells two products, L and V. Last month, Betty produced and...

    Betty DeRose, Inc. produces and sells two products, L and V. Last month, Betty produced and sold 6,000 units of Product L and 4,000 units of Product V. Cost and revenue information for the two products from last month appears below: selling price per unit ........... variable costs per unit .......... Product L $8.00 $3.00 Product V $9.00 $5.00 For the coming month, Betty would like to use linear programming in order to maximize monthly profits. Each month Betty has...

  • Betty DeRose, Inc. produces and sells two products, L and V. Last month, Betty produced and...

    Betty DeRose, Inc. produces and sells two products, L and V. Last month, Betty produced and sold 6,000 units of Product L and 4,000 units of Product V. Cost and revenue information for the two products from last month appears below: Product L Product V selling price per unit ........... $8.00 $9.00 variable costs per unit .......... $3.00 $5.00 For the coming month, Betty would like to use linear programming in order to maximize monthly profits. Each month Betty has...

  • the question: a firm makes products A and B. Product A takes 2 hours each on...

    the question: a firm makes products A and B. Product A takes 2 hours each on kachine L and machine M; product B takes 4 hours on L and 2 hours on M. Machine L can ve used no more than 12 hours per day and M no longer than 8 hours per day. Profit A is $9 and $6 on B. profit is to be maximized. which of the following correctly identifies the objective function of the constraints? This...

  • Betty DeRose, Inc, produces and sells two products, L and V. Revenue and cost information for...

    Betty DeRose, Inc, produces and sells two products, L and V. Revenue and cost information for the two products from last month appear below: selling price per unit variable costs per unit Product L $15.00 S 8.00 Product V $12.00 $ 7.00 For the coming to maximize monthly profits. month, Betty would like to use linear programming in order Each month Betty has 80,000 direct Labor hours available and 60,000 machine hours avaiLable. Product L requires 5 direct labor hours...

  • Broadway Sports Products wants to determine the number of All-Pro (A) and College (C) footballs to...

    Broadway Sports Products wants to determine the number of All-Pro (A) and College (C) footballs to produce in order to maximize profit over the next four-week planning horizon. Constraints affecting the production quantities are the production capacities in three departments: cutting and dyeing; sewing; and inspection and packaging. For the four-week planning period, 340 hours of cutting and dyeing time, 420 hours of sewing time, and 200 hours of inspection and packaging time are available. All-Pro footballs provide a profit...

  • The Surest Concrete Company produces cement in a continuous process.  Two ingredients in the cement are sand,...

    The Surest Concrete Company produces cement in a continuous process.  Two ingredients in the cement are sand, which Surest purchases for $8 per ton, and gravel, which costs $10 per ton.  The other ingredients are lumped together and referred to as “Other”. The cost of the other ingredients is $7 per ton. No more than 40 percent of the cement can be sand, and at least 30 percent of the cement must be gravel.  The maximum amount of gravel available is 100 tons.  The...

  • Zapit, Inc. manufactures two products, Product A and Product B. Product A yields an incremental profit...

    Zapit, Inc. manufactures two products, Product A and Product B. Product A yields an incremental profit of $2 per unit, and Product B yields an incremental profit of $4. Product A requires four hours of processing at Machine A and two hours at Machine B. Product B requires six hours at Machine A, six hours at Machine B, and one hour at Machine C. Machine A has a maximum of 120 hours of available capacity per day, Machine B has...

  • D. The Smith Company produces four products. The company has limited labor - only 10,000 hours...

    D. The Smith Company produces four products. The company has limited labor - only 10,000 hours are available this month. Product A Product B Product C Product D 240 195 30 100 $110$200$300 Selling price Variable cost per unit Direct labor hours per unit Demand (units) $100 $170 $250 20 10 100 200 300 Required: How many of each product should be sold to maximize profit? E.) The Smith Company produces four products. The company has limited machine time -...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT