Question

Madtack Company uses a job-order costing system and started the month of March with only one...

Madtack Company uses a job-order costing system and started the month
of March with only one job in process (Job #359). This job had $5,000
of total cost assigned to it at the beginning of March. Madtack applies
overhead to jobs at a rate of 175% of direct labor cost. During March,
Madtack assigned production costs as follows to the jobs worked on
during the month:

                             Job #359      Job #360      Job #361
direct materials ..........   $1,000         $5,000       $3,000
direct labor ..............    2,000          3,000        2,000

During March, Madtack completed and sold Job #360. Job #361 was also
completed but was not sold by the end of March. Job #359 was not
completed by the end of March. Madtack Company had total actual
overhead cost of $10,700 for the month of March. 

Calculate the amount of work in process inventory reported in Madtack
Company's March 31 balance sheet.
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Correct answer------------$11,500

Working

Work in process
Job 359
Beginning cost $   5,000.00
Cost added during month
Direct material $   1,000.00
Direct labor $   2,000.00
Overhead applied $   3,500.00
Total cost of work in process at the end of March 31 $ 11,500.00

Job 361 is under finished goods and Job 360 is under cost of goods sold. Only incomplete jobs remain under work in process account.

Add a comment
Know the answer?
Add Answer to:
Madtack Company uses a job-order costing system and started the month of March with only one...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Madtack Company uses a job-order costing system and started the month of March with three jobs...

    Madtack Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #359 Job #360 Job #361 beginning work in process ..... $4,800 $3,500 $6,300 COSTS ADDED DURING MARCH: direct materials .............. $4,100 $3,900 $6,400 direct labor .................. 5,000 3,000 4,000 Madtack applies overhead to jobs at a rate of 85% of direct materials used. During March,...

  • Madtack Company uses a job-order costing system and started the month of March with three jobs...

    Madtack Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #359 Job #360 Job #361 beginning work in process ..... $4,800 $3,500 $6,300 COSTS ADDED DURING MARCH: direct materials .............. $4,100 $3,900 $6,400 direct labor .................. 5,000 3,000 4,000 Madtack applies overhead to jobs at a rate of 85% of direct materials used. During March,...

  • Madtack Company uses a job-order costing system and started the month of March with three jobs...

    Madtack Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #359 Job #360 Job #361 beginning work in process ..... $4,800 $6,300 $3,500 COSTS ADDED DURING MARCH direct materials .............. $3,300 $4,100 $4,600 direct labor .................. 5,000 3,000 4,000 Madtack applies overhead to jobs at a rate of 70% of direct materials used. During March,...

  • QUESTION 2 Leija Manufacturing Company uses a job-order costing system and started the month of March...

    QUESTION 2 Leija Manufacturing Company uses a job-order costing system and started the month of March with one job in process (Job #359). This job had $500 of cost assigned to it at this time. During March, Leija assigned production costs as follows to the jobs worked on during the month: - Job #359 $6,000 Job #360 $8,100 Job #361 $2,400 Total cost assigned to jobs during March .... During March, Leija completed and sold Job #359. Job #360 was...

  • Jackson Company applies overhead to products using a pre-determined rate of $11.20 per direct labor hour....

    Jackson Company applies overhead to products using a pre-determined rate of $11.20 per direct labor hour. During 2019, Jackson Company began work on three jobs. Information relating to these three jobs appears below: Job #359 Job #360 Job #361 direct materials .............. $98,000 $75,000 $91,000 direct labor cost ............. $98,600 $79,900 $86,700 direct labor hours ............ 5,100 4,700 5,800 By the end of 2019, job #359 and job #361 had been completed. Job #360 was not completed by the end...

  • Jackson Company applies overhead to products using a pre-determined rate of $11.20 per direct labor hour....

    Jackson Company applies overhead to products using a pre-determined rate of $11.20 per direct labor hour. During 2019, Jackson Company began work on three jobs. Information relating to these three jobs appears below: Job #359 Job #360 Job #361 direct materials .............. $98,000 $75,000 $91,000 direct labor cost ............. $98,600 $79,900 $86,700 direct labor hours ............ 5,800 4,700 5,100 By the end of 2019, job #359 and job #361 had been completed. Job #360 was not completed by the end...

  • Kapanga Manufacturing Corporation uses a job-order costing system and started the month of October with a...

    Kapanga Manufacturing Corporation uses a job-order costing system and started the month of October with a zero balance in its work in process and finished goods inventory accounts. During October Kapanga worked on three jobs and incurred the following direct costs on those jobs Direct materials Direct labor Job 318 $ 12,000 $ 8,000 Job 319 $ 25,000 $ 10,000 Job C11 $ 18,000 $ 5,000 Kapanga applies manufacturing overhead at a rate of 150% of direct labor cost. During...

  • The Film Company uses a job-order costing system. The following information pertains to the company's activities...

    The Film Company uses a job-order costing system. The following information pertains to the company's activities for the month of December: On December 1, the company had two jobs in work in process as follows: Job 6 $20,000 and Job 8 $14,000 On December 1, the company had job in Finished Goods as follows: Job 10 $50,000 Jobs 12 and 13 were started during the month. Materials were purchased on account in December for $54,000 Materials were requisitioned for use...

  • Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...

    Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...

  • Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...

    Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT