Suppose a manufacturer has identified the following options for obtaining a machine part: Buying the part at $200 per unit. Making the part on a numerically controlled machine at $75 per unit (including materials), in which the machine costs $80,000. Making the part in a machining center at $15 per unit (including materials), in which the machining center costs $200,000. What is the break even value in terms of dollar-value ($) and volumes of units sold?
Option 1: Buying
Total cost = $200 * Units
Option 2: Making part on numerically controlled machine
Total cost = $80000 + $75 * Units
Option 3: Making part in machining center
Total cost = $200,000 + $15 * Units
First we have to find the breakeven point of Option 1 and Option
2.
Option 1 = Option 2
$200 * Units = $80,000 + $75 * Units
$125 * Units = $80,000
Units = $80,000 / $125 = 640 units
Here if production in less than 640 units then it should be purchased otherwise make in numerically controlled machine
Now we have to find the breakeven point of Option 2 and Option
3.
Option 2 = Option 3
$80,000 + $75 * Units = $200,000 + $15 * Units
$60 * Units = $120,000
Units = $120,000 / $60 = 2000 units
Here if production in less than 2000 units then Option 2 should be used otherwise Option 3 for units more than 2000.
Conclusion:
If units is less than 640 than Option 1 is best i.e. purchasing at
$200.
If units are in between 640 and 2000 then Option 2 is best i.e.
making in numerically controlled machine.
If units are more than 2000 then Option 3 is best i.e. making in
machining centre.
Suppose a manufacturer has identified the following options for obtaining a machine part: Buying the part...
Joe’s Machine Shop has identified the grinding station as its key bottleneck and has identified two options for expansion. The Grinder 1000 has fixed costs of $20,000 and $10 per unit variable costs. The Grinder 2000 has fixed costs of $40,000 and $8 per unit variable costs. Revenue per unit is projected to be $16. a. Determine the break-even point for each alternative. b. At what volume of output would the two alter- natives yield the same profit? c. If...
X Company is considering buying a part in 2020 that it has been
making for the past several years. A company has offered to supply
this part for $18.03 per unit. Budgeted production in 2020 is
52,000 units, and budgeted per-unit production costs are:
Materials
$6.50
Direct labor [all variable]
5.80
Total overhead
5.30
Total
$17.60
$78,000 of X Company's total overhead costs are fixed; $50,700 of
the $78,000 are unavoidable even if it buys the part. Also, if X...
X Company is considering buying a part in 2020 that it has been making for the past several years. A company has offered to supply this part for $15.93 per unit. Budgeted production in 2020 is 54,000 units, and budgeted per-unit production costs are: Materials $5.90 Direct labor [all variable] 5.70 Total overhead 4.40 Total $16.00 $102,600 of X Company's total overhead costs are fixed; $73,872 of the $102,600 are unavoidable even if it buys the part. Also, if X...
X Company is considering buying a part in 2020 that it has been making for the past several years. A company has offered to supply this part for $16.47 per unit. Budgeted production in 2020 is 53,000 units, and budgeted per-unit production costs are: $6.10 4.60 Materials Direct labor (all variable] Total overhead Total 5.70 $16.40 $90,100 of X Company's total overhead costs are fixed; $62,169 of the $90,100 are unavoidable even if it buys the part. Also, if X...
X Company is considering buying a part in 2020 that it has been making for the past several years. A company has offered to supply this part for $16.47 per unit. Budgeted production in 2020 is 53,000 units, and budgeted per-unit production costs are: Materials $6.10 Direct labor 4.60 [all variable] Total 5.70 overhead Total $16.40 $90,100 of X Company's total overhead costs are fixed; $62,169 of the $90,100 are unavoidable even if it buys the part. Also, if X...
X Company is considering buying a part in 2020 that it has been making for the past several years. A company has offered to supply this part for $14.87 per unit. Budgeted production in 2020 is 55,000 units, and budgeted per-unit production costs are: Materials Direct labor [all variable] Total overhead Total $5.30 4.80 4.30 $14.40 $77,000 of X Company's total overhead costs are fixed; $61,600 of the $77,000 are unavoidable even if it buys the part. Also, if X...
X Company is considering buying a part in 2020 that it has been making for the past several years. A company has offered to supply this part for $17.02 per unit. Budgeted production in 2020 is 51,000 units, and budgeted per-unit production costs are: Materials Direct labor (all variable] Total overhead Total $6.30 4.70 5.60 $16.60 $71,400 of X Company's total overhead costs are fixed; $44,268 of the $71,400 are unavoidable even if it buys the part. Also, if X...
X Company is considering buying a part in 2020 that it has been making for the past several years. A company has offered to supply this part for $14.43 per unit. Budgeted production in 2020 is 57,000 units, and budgeted per-unit production costs are: Materials Direct labor (all variable] Total overhead Total $5.70 4.30 4.30 $14.30 $102,600 of X Company's total overhead costs are fixed; $71,820 of the $102,600 are unavoidable even if it buys the part. Also, if X...
struggling with question 4
X Company is considering buying a part in 2020 that it has been making for the past several years. A company has offered to supply this part for $16.47 per unit. Budgeted production in 2020 is 53,000 units, and budgeted per-unit production costs are: Materials $6.10 Direct labor 4.60 [all variable] Total 5.70 overhead Total $16.40 $90,100 of X Company's total overhead costs are fixed; $62,169 of the $90,100 are unavoidable even if it buys the...
X Company is considering buying a part in 2020 that it has been making for the past several years. A company has offered to supply this part for $17.49 per unit. Budgeted production in 2020 is 50,000 units, and budgeted per-unit production costs are: Materials $6.60 Direct labor all variable) 5.20 Total overhead 5.90 Total $17.70 Company's total overhead costs are fixed; $77,000 of the $100,000 are unavoidable even if it buys the part Patiy buys the part, it can...