Question

Suppose a manufacturer has identified the following options for obtaining a machine part: Buying the part...

Suppose a manufacturer has identified the following options for obtaining a machine part: Buying the part at $200 per unit. Making the part on a numerically controlled machine at $75 per unit (including materials), in which the machine costs $80,000. Making the part in a machining center at $15 per unit (including materials), in which the machining center costs $200,000. What is the break even value in terms of dollar-value ($) and volumes of units sold?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Option 1: Buying
Total cost = $200 * Units

Option 2: Making part on numerically controlled machine
Total cost = $80000 + $75 * Units

Option 3: Making part in machining center
Total cost = $200,000 + $15 * Units

First we have to find the breakeven point of Option 1 and Option 2.
Option 1 = Option 2
$200 * Units = $80,000 + $75 * Units
$125 * Units = $80,000
Units = $80,000 / $125 = 640 units

Here if production in less than 640 units then it should be purchased otherwise make in numerically controlled machine

Now we have to find the breakeven point of Option 2 and Option 3.
Option 2 = Option 3
$80,000 + $75 * Units = $200,000 + $15 * Units
$60 * Units = $120,000
Units = $120,000 / $60 = 2000 units

Here if production in less than 2000 units then Option 2 should be used otherwise Option 3 for units more than 2000.

Conclusion:
If units is less than 640 than Option 1 is best i.e. purchasing at $200.
If units are in between 640 and 2000 then Option 2 is best i.e. making in numerically controlled machine.
If units are more than 2000 then Option 3 is best i.e. making in machining centre.

Add a comment
Know the answer?
Add Answer to:
Suppose a manufacturer has identified the following options for obtaining a machine part: Buying the part...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Joe’s Machine Shop has identified the grinding station as its key bottleneck and has identified two...

    Joe’s Machine Shop has identified the grinding station as its key bottleneck and has identified two options for expansion. The Grinder 1000 has fixed costs of $20,000 and $10 per unit variable costs. The Grinder 2000 has fixed costs of $40,000 and $8 per unit variable costs. Revenue per unit is projected to be $16. a. Determine the break-even point for each alternative. b. At what volume of output would the two alter- natives yield the same profit? c. If...

  • X Company is considering buying a part in 2020 that it has been making for the...

    X Company is considering buying a part in 2020 that it has been making for the past several years. A company has offered to supply this part for $18.03 per unit. Budgeted production in 2020 is 52,000 units, and budgeted per-unit production costs are: Materials $6.50 Direct labor [all variable] 5.80 Total overhead 5.30 Total $17.60 $78,000 of X Company's total overhead costs are fixed; $50,700 of the $78,000 are unavoidable even if it buys the part. Also, if X...

  • X Company is considering buying a part in 2020 that it has been making for the...

    X Company is considering buying a part in 2020 that it has been making for the past several years. A company has offered to supply this part for $15.93 per unit. Budgeted production in 2020 is 54,000 units, and budgeted per-unit production costs are: Materials $5.90 Direct labor [all variable] 5.70 Total overhead 4.40 Total $16.00 $102,600 of X Company's total overhead costs are fixed; $73,872 of the $102,600 are unavoidable even if it buys the part. Also, if X...

  • X Company is considering buying a part in 2020 that it has been making for the...

    X Company is considering buying a part in 2020 that it has been making for the past several years. A company has offered to supply this part for $16.47 per unit. Budgeted production in 2020 is 53,000 units, and budgeted per-unit production costs are: $6.10 4.60 Materials Direct labor (all variable] Total overhead Total 5.70 $16.40 $90,100 of X Company's total overhead costs are fixed; $62,169 of the $90,100 are unavoidable even if it buys the part. Also, if X...

  • X Company is considering buying a part in 2020 that it has been making for the...

    X Company is considering buying a part in 2020 that it has been making for the past several years. A company has offered to supply this part for $16.47 per unit. Budgeted production in 2020 is 53,000 units, and budgeted per-unit production costs are: Materials $6.10 Direct labor 4.60 [all variable] Total 5.70 overhead Total $16.40 $90,100 of X Company's total overhead costs are fixed; $62,169 of the $90,100 are unavoidable even if it buys the part. Also, if X...

  • X Company is considering buying a part in 2020 that it has been making for the...

    X Company is considering buying a part in 2020 that it has been making for the past several years. A company has offered to supply this part for $14.87 per unit. Budgeted production in 2020 is 55,000 units, and budgeted per-unit production costs are: Materials Direct labor [all variable] Total overhead Total $5.30 4.80 4.30 $14.40 $77,000 of X Company's total overhead costs are fixed; $61,600 of the $77,000 are unavoidable even if it buys the part. Also, if X...

  • X Company is considering buying a part in 2020 that it has been making for the...

    X Company is considering buying a part in 2020 that it has been making for the past several years. A company has offered to supply this part for $17.02 per unit. Budgeted production in 2020 is 51,000 units, and budgeted per-unit production costs are: Materials Direct labor (all variable] Total overhead Total $6.30 4.70 5.60 $16.60 $71,400 of X Company's total overhead costs are fixed; $44,268 of the $71,400 are unavoidable even if it buys the part. Also, if X...

  • X Company is considering buying a part in 2020 that it has been making for the...

    X Company is considering buying a part in 2020 that it has been making for the past several years. A company has offered to supply this part for $14.43 per unit. Budgeted production in 2020 is 57,000 units, and budgeted per-unit production costs are: Materials Direct labor (all variable] Total overhead Total $5.70 4.30 4.30 $14.30 $102,600 of X Company's total overhead costs are fixed; $71,820 of the $102,600 are unavoidable even if it buys the part. Also, if X...

  • struggling with question 4 X Company is considering buying a part in 2020 that it has...

    struggling with question 4 X Company is considering buying a part in 2020 that it has been making for the past several years. A company has offered to supply this part for $16.47 per unit. Budgeted production in 2020 is 53,000 units, and budgeted per-unit production costs are: Materials $6.10 Direct labor 4.60 [all variable] Total 5.70 overhead Total $16.40 $90,100 of X Company's total overhead costs are fixed; $62,169 of the $90,100 are unavoidable even if it buys the...

  • X Company is considering buying a part in 2020 that it has been making for the...

    X Company is considering buying a part in 2020 that it has been making for the past several years. A company has offered to supply this part for $17.49 per unit. Budgeted production in 2020 is 50,000 units, and budgeted per-unit production costs are: Materials $6.60 Direct labor all variable) 5.20 Total overhead 5.90 Total $17.70 Company's total overhead costs are fixed; $77,000 of the $100,000 are unavoidable even if it buys the part Patiy buys the part, it can...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT