Question

uestion 9 Vista Company installed a standard cost system on January 1. Selected transactions for the...

uestion 9 Vista Company installed a standard cost system on January 1. Selected transactions for the month of January are as follows. 1. Purchased 18,600 units of raw materials on account at a cost of $3.50 per unit. Standard cost was $3.20 per unit. 2. Issued 18,600 units of raw materials for jobs that required 18,380 standard units of raw materials. 3. Incurred 15,000 actual hours of direct labor at an actual rate of $4.70 per hour. The standard rate is $5.20 per hour. (Credit Factory Wages Payable.) 4. Performed 15,000 hours of direct labor on jobs when standard hours were 15,200. 5. Applied overhead to jobs at the rate of 100% of direct labor cost for standard hours allowed. Journalize the January transactions. (Credit account titles are automatically indented when amount is entered. Do not indent manually.) No. Account Titles and Explanation Debit Credit 1. 2. 3. 4. 5. Click if you would like to Show Work for this question: Open Show Work

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Journal entries
Event Account title Debit Credit
1 Direct material inventory (18600*3.20)           59,520
Direct material price variance             5,580
Account payable (18600*3.50)                 65,100
(To record direct material price variance with purchased of inventory.)
2 Work in progress inventory (18380*3.20)           58,816
Direct material usage variance                 704
Direct material inventory (18600*3.20)                 59,520
(To record direct material usage variance with inventory used for production.)
3 Factory Labor (15000*5.20)           78,000
Labor rate variance                   7,500
Factory Wages Payable (15000*4.70)                 70,500
(To record Incurred 15,000 actual hours of direct labor at an actual rate of $4.70 per hour. The standard rate is $5.20 per hour.)
4 Work in progress inventory (15200*5.20) 79040
Labor quantity (efficiency) variance                   1,040
Factory Labor (15000*5.20)                 78,000
(To record Performed 15,000 hours of direct labor on jobs when standard hours were 15,200.)
5 Work in progress inventory 79040
Manufacture overhead (or Factory overhead)                 79,040
(To record Manufacture overhead Applied to Job.) (79040*100%)
Summary of Answer
Material
Material price variance             5,580 Unfavorable
Material quantity variance                 704 Unfavorable
Labor
Labor price (rate) variance             7,500 Favorable
Labor quantity (efficiency) variance             1,040 Favorable
Minus sign indicate Favorable variance.
Measure unit
Standard price per unit $            3.20
Actual price per unit $            3.50
Standard quantity in units 18,380
Actual quantity purchased in units 18,600
Actual quantity used in units 18,600
Actual price per unit 3.50
Less Standard price per unit -3.20
Difference 0.30
Multiply Actual quantity purchased in units 18600
Material price variance $          5,580
Indicate Unfavorable
Actual quantity used in units 18600
Less Standard quantity in units -18380
Difference 220
Multiply Standard price per unit 3.20
Material quantity variance $              704
Indicate Unfavorable
Minus sign indicate Favorable variance.
Measure Hour
Standard rate per Hour $              5.20
Actual rate per Hour $              4.70
Standard labor Hours 15,200
Actual labor Hours 15,000
Actual rate per Hour 4.70
Less Standard rate per Hour -5.20
Difference -0.50
Multiply Actual labor Hours 15000
Labor price (rate) variance $          (7,500)
Indicate Favorable
Actual labor Hours 15000
Less Standard labor Hours -15200
Difference -200
Multiply Standard rate per Hour 5.20
Labor quantity (efficiency) variance $          (1,040)
Indicate Favorable
Add a comment
Know the answer?
Add Answer to:
uestion 9 Vista Company installed a standard cost system on January 1. Selected transactions for the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Concord Company installed a standard cost system on January 1. Selected transactions for the month of...

    Concord Company installed a standard cost system on January 1. Selected transactions for the month of January are as follows. 1. Purchased 17,300 units of raw materials on account at a cost of $3.30 per unit. Standard cost was $3.00 per unit. 2. Issued 17,300 units of raw materials for jobs that required 16,890 standard units of raw materials. 3. Incurred 16,000 actual hours of direct labor at an actual rate of $4.00 per hour. The standard rate is $4.50...

  • Problem 11-6A (Part Level Submission) Jorgensen Corporation uses standard costs with its job order cost accounting system. In January, an order (Job No. 12) for 2,000 units of Product B was receiv...

    Problem 11-6A (Part Level Submission) Jorgensen Corporation uses standard costs with its job order cost accounting system. In January, an order (Job No. 12) for 2,000 units of Product B was received. The standard cost of one unit of Product B is as follows. 3 pounds at $1.30 per pound $3.90 Direct materials Direct labor 1.30 hour at $10.00 per hour 13.00 2 hours (variable $4.50 per machine hour; fixed $2.60 per machine hour) 14.20 Overhead $31.10 Standard cost per...

  • Jorgensen Corporation uses standard costs with its job order cost accounting system. In January, an order...

    Jorgensen Corporation uses standard costs with its job order cost accounting system. In January, an order (Job No. 12) for 1,000 units of Product B was received. The standard cost of one unit of Product B is as follows. 3 pounds at $1.00 per pound Direct materials $3.00 Direct labor 1.50 hour at $10.00 per hour 15.00 2 hours (variable $4.30 per machine hour; fixed $3.30 per machine hour) Overhead 15.20 $33.20 Standard cost per unit Normal capacity for the...

  • Bovar Company began the manufacture of new paging machines. The company installed a standard costing system...

    Bovar Company began the manufacture of new paging machines. The company installed a standard costing system to account for manufacturing costs. The standard cost per unit is:               Direct materials   3 pound @ $5 per pound               Direct labor         .5 hours @ $20 per direct labor hour               Variable overhead       75% of direct labor cost Actual production was 4,000 units; actual sales were 2,500 units. There is no beginning inventory for direct materials. Other data are: Materials price variance is...

  • The Schock Manufacturing Company uses a standard cost system. The standards are set January 1 each...

    The Schock Manufacturing Company uses a standard cost system. The standards are set January 1 each year and remain unchanged until December 31 The standard costs set for the next year are: Diret materials S10.00 per unit Direct labor Overhead 7.50 per unit 600 per unit The labor standard above includes a methods change from 2 hours to 1% bours per unit, effective February 28, and a change in labor rates from $4.00 to $5,00 per hour effective February 28....

  • 27 Hurren Corporation makes a product with the following standard costs: Standard Cost Standard Quantity or Standard...

    27 Hurren Corporation makes a product with the following standard costs: Standard Cost Standard Quantity or Standard Price or Per Unit Rate Hours $22.40 $4.00 per gram 5.6 grams Direct materials $36.10 $19.00 per hour 1,9 hours Direct labor $7.60 $4.00 per hour 1.9 hours Varlable overhead The company reported the following results concerning this product in June. Originally budgeted output 5,400 units Actual output 5,300 units Raw materials used in production 28,500 grams Actual direct labor-hours 5,700 hours Purchases...

  • Hurren Corporation makes a product with the following standard costs: Standard Standard Price Standard Cost Quantity...

    Hurren Corporation makes a product with the following standard costs: Standard Standard Price Standard Cost Quantity or Per Unit or Rate Hours $8.00 per gram Direct materials 4.0 grams $32.00 $7.20 $12.00 per hour Direct labor 0.6 hours Variable $8.00 per hour $4.80 0.6 hours overhead The company reported the following results concerning this product in June. 7,300 Originally budgeted output units Actual output 7,200 units Raw materials used in production 28,340 grams 4,100 Actual direct labor-hours hours Purchases of...

  • Oddo Corporation makes a product with the following standard costs: Standard Quantity or Hours Standard Cost...

    Oddo Corporation makes a product with the following standard costs: Standard Quantity or Hours Standard Cost Per Unit Standard Price or Rate Direct Materials Direct Labor Variable Overhead 3.0 ounces 0.7 hours 0.7 hours $7.00 per ounce $20.00 per hour $5.00 per hour $21.00 $14.00 $ 3.50 The company reported the following results concerning this product in December: Originally budgeted output Actual output Raw materials used in production Actual direct labor-hours Purchases of raw materials Actual price of raw materials...

  • Jorgensen Corporation uses standard costs with its job order cost accounting system. In January, an order (Job No. 12) for 2,000 units of Product B was received. The standard cost of one unit of Produ...

    Jorgensen Corporation uses standard costs with its job order cost accounting system. In January, an order (Job No. 12) for 2,000 units of Product B was received. The standard cost of one unit of Product B is as follows. Direct materials 3 pounds at $1.10 per pound $3.30 Direct labor 1.70 hour at $8.00 per hour 13.60 Overhead 2 hours (variable $4.40 per machine hour; fixed $2.70 per machine hour) 14.20 Standard cost per unit $31.10 Normal capacity for the...

  • DACA NEXT Problem 23-6A (Part Level Submission) Jorgensen Corporation uses standard costs with its job order...

    DACA NEXT Problem 23-6A (Part Level Submission) Jorgensen Corporation uses standard costs with its job order cost accounting system. In January, an order (ob No. 12) for 1,400 units of Product B was received. The standard cost of one unit of Product B is as follows. Direct materials Direct labor $3.90 11.70 3 pounds at $1.30 per pound 1.30 hour at $9.00 per hour 2 hours (variable $4.00 per machine hour; fixed $3.00 per machine hour) Overhead 14.00 Standard cost...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT