Answer 1: B: Grilling, 12
Explanation: Processes in last step are done simultaneously, therefore, the bottleneck operation is Grilling with 5 mins process time, the capacity of grilling= 60/process time= 60/5 mins= 12 units per hour
The bottleneck of the process is Grilling with an hourly capacity of 12 units
Answer 2: A)48
Explanation: Production in 4 hours= Hourly capacity*4 hours= 12*4= 48
Answer 3: A)11 mins
Explanation: Throughput time is sum of all process times= Pealing +filling +grilling +splashing = 1+2+5+3= 11 mins
Steven Starr has an idea for a desert he is preparing to sell via food truck...