Work is our business (WOB) has a shop with three (3) work centers (WC). Each of the three WCs are available to work 8 hours a day 5 days a week. WOB worked 20 days last month. WOB does a variety of jobs, but last month they did a special order for their best customer and that was the only work they did. Assume that WOB works Monday through Friday and that the truck arrives to take shipments after the WCs finish processing for the day, so that all the work on Friday is available to ship on Friday. Last month they produced only a product called PXXX for this customer. PXXX required processing time (T1) at WC! of 2.2 hours for a single PXXX. After leaving WC1, job PXXX went to WC2 where it's processing time (T2) was about 1 hours. Job PXXX then went to WC3 were it's processint time (T3) was 1.5 hours. When job PXXX completed processing at WC3 it returned to WC2 for one final pass, where its processing time was again, 1 hours. When it finished the second time on WC2 it went to shipping. Shipping accumulated the completed PXXX into pallets and prepared to ship on Friday afternoon. WOB has 2 machines at WC1 and it has 2 machines at WC@ and it has 3 machines at WC3.
1. The total processing time (Tprocess) for each individual product PXXX from its start at WC1 through completion on WC2 (i.e., after the second time at WC2) was:
a. 2 hours
b. 3 hours
c. 4.5 hours
d. 5 hours
e. 5.5 hours
f. 6 hours
g. 8 hours
2. If each work center has 100% uptime on all of its machines, what would be the maximum number of PXXX that can be produced by WOB last month?
3. if 20 jobs were started and completed last week by WOB, what was the utilization of the machines at Work Center 2?
4. Which workstation is the bottleneck when producing 20 jobs a week?
Answer 1. Total processing time Tprocess = T1+T2+T3+T4 = 2.2+1+1.5+1 = 5.7 hours. None of the options provided here match the answer, however the concept is to add all the time required to process one product.
Answer 2. In the above process, at 100% utilization, the bottleneck is at WC1 because it is taking the maximum time to finish the process. This means that there will be one product coming out of this processing line every 2.2 hours.
Therefore, to calculate the maximum number of PXXX produced last month:
No. of days (D) = 20 days
Hours per day (H) = 8 hours
Hours worked last month = D x H = 20 x 8 = 160 Hours
Total PXXX produced last month = 160 / 2.2 = 72.7 units
Answer 3. Days per week = 5
Jobs done last week = 20
Hours of work done at WC2 = 20 x (1+1) = 40 hours
Available hours at WC2 last week = 5 days x 8 hours per day = 40 hours
Utilization of machines at WC2 = (40/40) x 100 = 100%
Answer 4. When producing 20 jobs a week, the
bottleneck will remain at WC1 because it is still taking 2.2 hours
for one job although it is working at
= 110% efficiency.
Work is our business (WOB) has a shop with three (3) work centers (WC). Each of...
An assembly line has three operations in sequence. The work-centers take 5, 3, and 2 minutes per job. (So job 1 enters the first work-center, where it takes 5 minutes; then it is moved to the second work center where it takes 3 minutes while job 2 enters the first work-center, etc.) In the above line, if the second work-center operation time is reduced by ten percent, what is the throughput of this line (as number of jobs completed per hour...
Saved Help Whitley Construction Company is in the home remodeling business. Whitley has three teams of highly skilled employees, each of whom has multiple skills involving carpentry, painting, and other home remodeling activities. Each team is led by an experienced employee who coordinates the work done on each job. As the needs of different jobs change, some team members may be shifted to other teams for short periods of time. Whitley uses a job costing system to determine job costs...
Respondents to the household survey end up in one of three primary categories: employed, unemployed, or not in the labor force. • An employed person is someone who worked for pay, worked for his or her own business, or was on temporary leave from a paid position during the week of the survey. • An unemployed person is someone who did not work during the survey week but was available to work and had searched for employment at some point...
Based on the criteria used by the Bureau of Labor Statistics (BLS), identify each person's status as Employed, Unemployed, "Not in the labor force" but still part of the civilian noninstitutional population, or "Not in the civilian noninstitutional population" if not in the civilian noninstitutional population.PersonKevin is a 49 -year-old autoworker who was laid off from his job 6 months ago. He is frustrated with his inability to find a new full-time position. Last week, he took a part-time job...
John operates a motorcycle repair shop from his home but finds that his business is limited by the small size of his garage. Driving by a neighbor's property, he notices a for-sale sign on a large, metal-sided garage. John contacts the neighbor and offers to buy the building, hoping that it can be dismantled and moved to his own property. The neighbor accepts John's payment and makes a generous offer in return: if John will help him dismantle the garage,...
Waterways has two major public-park projects to provide with comprehensive irrigation in one of its service locations this month. Job J57 and Job K52 involve 15 acres of landscaped terrain, which will require special-order, sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December. Raw materials were requisitioned from the company’s inventory on December 2 for $5,064; on December 8 for $1,068; and on December 14...
P3-3 Labor Time Record, Direct vs. Indirect Labor LO2 Adam Amos, SS# 123-45-6789, is a Grade 2 Machinist who earns $18 per hour. On Monday, June 10 through Wednesday, June 12, he worked four hours per day on each of Jobs AX20 and AX25. On Thursday, he worked six hours on Job AX25 and two hours on maintenance, while on Friday he worked four hours on AX25 and four hours on maintenance. His supervisor is Emma Nyaondo, who signs off...
Waterways has two major public park projects to provide with comprehensive irrigation in one of its service locations this month. Job J57 and Job K52 involve 15 acres of landscaped terrain, which will require special-order, sprinkler heads to meet the specifications of the project. Using a job cost system to produce these parts, the following events occurred during December. Raw materials were requisitioned from the company's inventory on December 2 for $5,094; on December 8 for $1,056; and on December...
Check my work Waymouth Manufacturing operates a contract manufacturing plant located in Dublin, Ireland. The plant provides a variety of electronics products and components to consumer goods manufacturers around the world. Cycle time is a critical success factor for Waymouth, which has developed a number of measures of manufacturing speed. Waymouth has studied the matter and found that competitive contract manufacturers have manufacturing cycle times (MCE) of about 37%. When last calculated, Waymouth's MCE was 32% 0.31 points Key measures...
The Fitzgerald Machine Company is a $25MM per year custom metal fabrication shop. It has a work force of 30 machinists and 15 office personnel Don Bradish was hired from Peptine Corporation three months ago as Fitzgerald’s production scheduler. His background includes an undergraduate industrial engineering degree and three years of purchasing experience with Peptine immediately after college. This made him a good fit for Fitzgerald’s needs. He was hired by Jane Fitzgerald, Vice President of Operations and daughter of the company president. Recently the company...