the soil in a borrow pit has a water content of 11.7% and a dry unit weight of 16.65 kN/m^3. If 2,070 m^3 of this soil is excavated and compacted in an embankment at a porosity of 0.33, compute the compacted volume of the embankment that can be constructed with this soil. The specific gravity of solids is 2.7

0 0
Add a comment Improve this question Transcribed image text
Answer #1

​​​​​​In both the cases volume of soil solids will remains same, only due to change in void ratio of two state natural volume of soil will get changed

Add a comment
Know the answer?
Add Answer to:
the soil in a borrow pit has a water content of 11.7% and a dry unit...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • An embankment is to be constructed using a sandy soil from a borrow pit. In a standard compaction test on a soil (grain specific gravity of 2.7) the following results were obtained: Water content...

    An embankment is to be constructed using a sandy soil from a borrow pit. In a standard compaction test on a soil (grain specific gravity of 2.7) the following results were obtained: Water content (%) Y  kN/m3 6.2 16.9 8.1 18.7 9.8 19.5 11.5 20.5 12.3 20.4 13.2 20.1 The volume of the mould is 1000 cm3 Determine the maximum dry density obtainable under standard test conditions and the water content at which this occurs Discuss the techniques of quality...

  • Problem Description A 20 m wide, 2km long, and Im thickness embankment should be constructed for...

    Problem Description A 20 m wide, 2km long, and Im thickness embankment should be constructed for a railway project in Melbourne city. The required soil for the embankment construction will be transported from a borrow pit located in a rural site. The borrow pit has loosely compacted sandy loam soil. Porosity of this borrow pit's soil is 0.40 and the specific gravity is 2.7. Part A; In order to maintain the stability of the railway project the embankment needs to...

  • the only question to answer are 2-5 2-7 2-10 2-17 2-19 thank you CHAPTER Two 2-3....

    the only question to answer are 2-5 2-7 2-10 2-17 2-19 thank you CHAPTER Two 2-3. An undisturbed chunk of soil has a wet weight of 62 lb and a volume of o.s6 ft. When dried out in an oven, the soil weighs S0 Ib. If the specific gravity o solids is found to be 2.64, determine the water con- tent, wet unit weight of soil, dry unit soil. 2-13. The wet unit weight of a soil sample is 18.55...

  • Zin 2. The Undisturbed soil at a given borrow pit is found to have the following...

    Zin 2. The Undisturbed soil at a given borrow pit is found to have the following parameters. The water content is 15%, the void ratio is 0.60 and the specific gravity of the solids is 2.70. soil from this borrow pit is to be used to construct a rolled fill having a finished volume of s0.0 The soil is excavated by means of a shovel and dumped on trucks. When loaded to trucks are found to contain, on average, a...

  • 2. [10] A segment of interstate highway requires the construction of an embankment of 500,000 yds. The embankment fills to be compacted to a minimum of 90% of Modified Proctor maximum dry den...

    2. [10] A segment of interstate highway requires the construction of an embankment of 500,000 yds. The embankment fills to be compacted to a minimum of 90% of Modified Proctor maximum dry density. A source of suitable borrow has been located for construction of the embankment. Tests showed that the required dry density can be achieved with the existing moisture content of the borrow pit material. The following data is provided: Dry unit weight of soil in the borrow pit...

  • B. The moist weight of 0.028 m3 of a soil is 52 kg. The moisture content...

    B. The moist weight of 0.028 m3 of a soil is 52 kg. The moisture content and the specific gravity of the soil solids are determined in the laboratory to be 11% and 2.7 , respectively. Calculate the following: Moist unit weight (kg/m3) i. Dry unit weight (kg/m3) ii. Void ratio d. Porosity iii. iv. Degree of saturation (%) Volume occupied by water (m3) v. ngle C. For the soil sample in A (above) represent the following on a soil...

  • A moist soil packed into a volume of 0.1 m2 has a dry weight of 1.5...

    A moist soil packed into a volume of 0.1 m2 has a dry weight of 1.5 KN and a water content of 12%. The average specific gravity of the grains comprising the soil is 2.65. Determine: a. The dry unit weight of the soil b. The moist unit weight of the soil c. The void ratio d. The porosity e. The degree of saturation f. The volume occupied by the water in the soil.

  • 1. A soil sample is taken from a small test hole in a soil borrow pit....

    1. A soil sample is taken from a small test hole in a soil borrow pit. The volume of the test hole is 5 ft. The wet mass of the soil is 18 kg and the dry mass is 21 kg. The specific gravity of the soil solids is 2.65. ( m 35. 3147ft)(1 kge 2.205 lb) ( 1 lb= 0.2248 N) Determine: a. Wet and dry density (Mg/m) b. Wet and dry unit weight (pcf) C. Water content (%)...

  • A sandy soil has a maximum void ratio (emax) of 0.63 and a minimum void ratio...

    A sandy soil has a maximum void ratio (emax) of 0.63 and a minimum void ratio (emin) of 0.36. The soil is compacted to a dry unit of 17.8 Kn/m at a moisture content of 1896. The specific gravity of the solids is 2.7. What is the relative density of the soil after compaction?

  • A proposed embankment fill requires 5000 m3 of compacted soil. The void ratio of the compacted...

    A proposed embankment fill requires 5000 m3 of compacted soil. The void ratio of the compacted fill is specified as 0.75. Soil can be transported from one of the four borrow pits as shown in the table below. The void ratio, specific gravity of soil solids, and the cost per cubic meter for moving the soil to the proposed construction site are provided in the table. a. Determine the volume of each borrow pit soil required to meet the specification...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT