Ending Work in Process Month Beginning Work in Process Units Transferred Out Units % Complete as to Conversion Cost January –0– 36,000 10,000 40 % March –0– 41,000 8,100 70 July –0– 46,000 17,000 20 Compute equivalent units of production for materials and conversion costs, assuming materials are entered at the beginning of the process. Materials Conversion Costs January March July
| Material | Conversion cost | |
| January | 46,000 | 40,000 |
| March | 49,100 | 46,670 |
| July | 63,000 | 49,400 |
Ending Work in Process Month Beginning Work in Process Units Transferred Out Units % Complete as...
Goode Company has the following production data for selected months. Ending Work In Process Beginning Units % Complete as to Month Work in Process Transferred Out Units Conversion Cost January 0 36,100 12,900 40% March 41,200 8,100 75 July 48,900 21,400 25 Compute equivalent units of production for materials and conversion costs, assuming materials are entered at the beginning of the process. Materials Conversion Costs January March July
Goode Company has the following production data for selected
months.
Ending
Work in Process
Month
Beginning
Work in Process
Units
Transferred Out
Units
% Complete as to
Conversion Cost
January
0
36,800
10,700
42
%
March
0
42,700
8,500
70
July
0
46,300
21,700
21
Compute equivalent units of production for materials and conversion
costs, assuming materials are entered at the beginning of the
process.
Materials
Conversion Costs
January
March
July
Cost of Units Transferred Out and Ending Work in Process The costs per equivalent unit of direct materials and conversion in the Rolling Department of Oak Ridge Steel Company are $180 and $62, respectively. The equivalent units to be assigned costs are as follows: Equivalent Units Direct Materials Conversion Inventory in process, July 1 0 225 Started and completed during July 1,900 1,900 Transferred out of Rolling (completed) 1,900 2,125 Inventory in process, July 31 500 200 Total units to...
Question 11 Goode Company has the following production data for selected months. Ending Work in Process Beginning Units % Complete as to Month Work in Process Transferred Out Units January 40,300 10,600 43% March 42,000 8,900 70 July 47,700 20,000 som Compute equivalent units of production for materials and conversion costs, assuming materials are entered at the beginning of the process. is conversion costs January March w lila in Chw Work for this actions One Show work
In Sheridan Company, materials are entered at the beginning of each process. Work in process inventories, with the percentage of work done on conversion costs, and production data for its Sterilizing Department in selected months during 2020 are as follows. Beginning Work in Process Ending Work In Process Units Month Conversion Cost Units Conversion Cost Transferred Out Units 0 January March 11,700 12,300 15,500 11,100 2,900 4,900 7,930 2,500 May July Compute the physical units for January and May. May...
Exercise 3-5 (Video) In Shady Company, materials are entered at the beginning of each process. Work in process inventories, with the percentage of work done on conversion costs, and production data for its Sterilizing Department in selected months during 2020 are as follows. Beginning Work in Process Ending Work in Process Month Units Conversion Cost% Units Transferred Out Units Conversion Cost% January 0 — 11,000 2,000 60 March 0 — 12,000 3,000 30 May 0 — 14,000 7,000 80 July...
In Shady Company, materials are entered at the beginning of each process. Work in process inventories, with the percentage of work done on conversion costs, and production data for its Sterilizing Department in selected months during 2020 are as follows. Ending Work in Process Beginning Work in Process Conversion Units Cost% Units Transferred Out Month Units Conversion Cost% January March May July 11,800 13,600 15,700 10,500 2,400 4,500 7,360 2,200 Compute the physical units for January and May. January May...
Cost of Units Transferred Out and Ending Work in Process The costs per equivalent unit of direct materials and conversion in the Rolling Department of Kraus Steel Company are $0.50 and $1.65, respectively. The equivalent units to be assigned costs are as follows: Equivalent Units Direct Materials Conversion Inventory in process, October 1 0 3,200 Started and completed during October 46,000 46,000 Transferred out of Rolling (completed) 46,000 49,200 Inventory in process, October 31 5,000 2,500 Total units to be...
Exercise 21-05 a-b In Sunland Company, materials are entered at the beginning of each process. Work in process inventories, with the percentage of work done on conversion costs, and production data for its Sterilizing Department in selected months during 2020 are as follows. Ending Work in Process Beginning Work in Process Conversion Units Cost% Conversion Month 60 January March May July Units Transferred Out 11,600 12,600 15,100 10,200 Units 1,900 4,100 7,140 1,700 0 Compute the physical units for January...
0 Cost of Units Transferred Out and Ending Work in Process The costs per equivalent unit of direct materials and conversion in the Rolling Department of Kraus Steel Company are $0.35 and $2.20, respectively. The equivalent units to be assigned costs are as follows: Equivalent Units Direct Materials Conversion Inventory in process, October 1 2,800 Started and completed during October 46,000 46,000 Transferred out of Rolling (completed) 46,000 48,800 Inventory in process, October 31 3,000 1,800 Total units to be...