Question

You developed the WBS of multiple levels, including work packages at the low- est level based...

You developed the WBS of multiple levels, including work packages at the low- est level based on the initial project requirements below, which were further elaborated. Building a single-family, partially custom-designed home as required by Mrs. and Mr. John Thomas on Strath Dr., Alpharetta, Georgia. The single-family home will have the following features: 3,200 square-feet home with 4 bedrooms and 2.5 bath- rooms Flooring hard wood in the first floor, tiles in the kitchen and bathrooms, carpet in bedrooms Granite kitchen countertops, GE appliances in the kitchen 3-car garage and external landscaping Ceiling 10 in first floor and vaulted 9 ceilings in bed- rooms High-level Assumptions and Constraints The list of options is limited and the cost of the house would vary based on options selected. The client must choose one from among the models offered. 7-year warranty for structure and 2-year warranty for finish- ing components After the WBS was developed, it is necessary to identify risks associated with the project and include prioritized risks in revising cost and schedule estimates. For this purpose, you were asked to develop a comprehensive risk manage- ment plan.

TASK TO COMPLETE:

Develop a risk breakdown structure in Microsoft Excel or in Microsoft word (using tables).

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Risk Breakdown Structure for single-family, partially custom-designed home Risk Breakdown Structure for single-family, partially custom-designed home
People Deliverables Time Costs Quality Contract Market Category wise - Internal Risk Category wise - External Risk
Labor Shortage Probability of Technical Success Schedule Delays Estimating Errors Warranty Exposure and Issues with approved Warranty Lack of Clarity Various Opportunity in the Current Market Labour, Materials, Site, Sub- Contractor Economic, Physical
Labor strike Issues with parts and Components Issue may arise with Schedules changes Exchange Rates Performance Issue Disputes Threats in current Market Construction, Client, Design Political
Skill Deficiency Design not released officially and Under Approval Process, Force Majeure Issue may arise with Scope changes Defect and Defective for various parts and Components/ Subcontractor Items Failure and Performance issues with Subcontractor Probability for the project success Contractual, Internal Environmental Technological Changes and Legal Obligation
Issue with Unions Design those approved need review over time, Penalty consideration Funding Company and Project Finance
Performance issue with Subcontractor People Problem Escalation Location and Management
Add a comment
Know the answer?
Add Answer to:
You developed the WBS of multiple levels, including work packages at the low- est level based...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT