Question

Lueckenhoff Corporation uses a job-order costing system with a single plant wide predetermined overhead rate based...

Lueckenhoff Corporation uses a job-order costing system with a single plant wide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $497,000, variable manufacturing overhead of $2.40 per direct labor hour, and 70,000 direct labor hours. The company has provided the following data concerning job T498 which was recently completed:

Number of units in the job 40

Total direct labor hours 80

Direct materials $950

Direct labor cost $2,720

The predetermined overhead rate is closest to: A.)$9.50 per direct labor hour B.) $11.90 per direct labor hour C.). $2.40 per direct labor hour. D.). $7.10 per direct labor hour

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Predetermined overhead rate = ( Estimated fixed manufacturing overhead cost / Estimated direct labor hours ) + Estimated variable manufacturing overhead per direct labor hour = ( 497000 / 70000 ) + 2.40 9.50 per direct labor hour Option A
Add a comment
Know the answer?
Add Answer to:
Lueckenhoff Corporation uses a job-order costing system with a single plant wide predetermined overhead rate based...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Lueckenhoff Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lueckenhoff Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $497,000, variable manufacturing overhead of $2.40 per direct labor-hour, and 70,000 direct labor-hours. The company has provided the following data concerning Job T498 which was recently completed: 40 Number of units in the job Total direct labor-hours Direct materials Direct labor cost 80 $...

  • Lueckenhoff Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lueckenhoff Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $497,000, variable manufacturing overhead of $2.40 per direct labor-hour, and 70,000 direct labor hours. The company has provided the following data concerning Job T498 which was recently completed: 40 80 Number of units in the job Total direct labor-hours Direct materials Direct labor cost...

  • Lueckenhoff Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lueckenhoff Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $497,000, variable manufacturing overhead of $2.40 per direct labor-hour, and 70,000 direct labor-hours. The company has provided the following data concerning Job T498 which was recently completed: Number of units in the job 40 Total direct labor-hours 80 Direct materials $ 950 Direct labor...

  • A Corporation uses a job-order costing system with a single plant-wide predetermined overhead rate based on...

    A Corporation uses a job-order costing system with a single plant-wide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $249,000, variable manufacturing overhead of $3.80 per machine-hour, and 30,000 machine-hours. The company has provided the following data concerning Job X784 which was recently completed: Job E's manufacturing cost: Total machine-hours 250 Direct materials $ 470 Direct labor cost $ 5,500 If the company marks...

  • Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data Total direct labor-hours Total fixed manufacturing overhead cost Variable nanufacturing overhead per direct labor-hour 40,000 96,000 $ 3.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job Total direct labor-hours Direct materials Direct labor cost 20 100 두 755 $4,000 The...

  • Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor- hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 40,000 Total fixed manufacturing overhead cost $96,000 Variable manufacturing overhead per direct labor-hour $ 3.00 Recently, Job P951 was completed with the following characteristics Number of units in the job Total direct labor-hours Direct materials Direct labor cost 20 100 $ 755 $4,000...

  • Kostelnik Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Kostelnik Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $480,000, variable manufacturing overhead of $2.40 per machine-hour, and 64,000 machine-hours. The company has provided the following data concerning Job A496 which was recently completed: Number of units in the job 10 Total machine-hours 80 Direct materials $ 1,000 Direct labor cost $ 2,000 The...

  • Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following datar Total direct labor-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per direct labor-hour 70,000 $273, eee $ 6.00 Recently, Job P951 was completed with the following characteristics Number of units in the job Total direct labor-hours Direct materials Direct labor cost se 100 $ 680 $7,000...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine- hour 31,000 $310,000 $ 4.00 Recently, Job T587 was completed with the following characteristics: 10 Number of units in the job Total machine-hours Direct materials Direct labor cost 30 $ 730 $1,460 The total job cost...

  • Dehner Corporation uses a job order costing system with a single plantwide predetermined overhead rate based...

    Dehner Corporation uses a job order costing system with a single plantwide predetermined overhead rate based on direct labor hours. The company based its predetermined overhead rate for the current year on the following data Total direct labor-hours 70,000 Total fixed manufacturing overhead cost $273,000 Variable manufacturing overhead per direct labor-hour $ 6.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job 50 Total direct labor-hours 100 Direct materials Direct labor cost $7,000 The...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT