14.1 The construction cost for a building in 1999 was $184,971. If the ENR construction cost index was 6059 at that time and is 11213 today, then what is cost of constructing a similar building?
construction cost = 184971 in 1999
construction cost index in 1999 is 6059 and 11213 today
Construction cost today = 184971 * 11213 / 6059 = 342313.88
14.1 The construction cost for a building in 1999 was $184,971. If the ENR construction cost index...
An engineering project manager is preparing a preliminary cost estimate for a design and construction wants to use the ENR construction cost index to update the cost. If the index value in 2014 in 9,417, estimate the cost of construction for a similar-size project in 2014 Do NOT (ype the dollar sign $') or any commas .) in your answer Round to two decimals (money maage s prepa ng a preimn y cost estimate for a design and construct pr...
2. A construction index was 100 in 1967 and in 2018 had a value of 1071. If a 186,000 square foot building cost $150 million to build in 2018, what would a 98,000 square foot building have cost in 1967? Assume 0.7 is the power sizing exponent. (15 points)
2. A construction index was 100 in 1967 and in 2018 had a value of 1071. If a 186,000 square foot building cost $150 million to build in 2018, what would...
Which of the following is included in the cost of constructing a building? Interest incurred during construction. Cost of grading the land on which the building is to be constructed. Cost of removing the demolished building that existed on the land when it was purchased. Cost of paving a parking lot.
2. A construction index was 100 in 1967 and in 2018 had a value of 1071. If a 186,000 square foot building cost $150 million to build in 2018, what would a 98,000 square foot building have cost in 1967? Assume 0.7 is the power sizing exponent. (15 points)
In 1993, Nash Company completed the construction of a building at a cost of $2,040,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $59,200 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $510,000. At that time, it was estimated that the remaining life of the building would be, as originally...
In 1993, Crane Company completed the construction of a building at a cost of $2,020,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $60,000 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $505,000. At that time, it was estimated that the remaining life of the building would be, as originally...
In 1993, Nash Company completed the construction of a building at a cost of $2,040,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $59,200 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $510,000. At that time, it was estimated that the remaining life of the building would be, as originally...
In 1993, Nash Company completed the construction of a building at a cost of $2,040,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $59,200 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $510,000. At that time, it was estimated that the remaining life of the building would be, as originally...
In 1993, Bramble Company completed the construction of a
building at a cost of $2,280,000 and first occupied it in January
1994. It was estimated that the building will have a useful life of
40 years and a salvage value of $68,800 at the end of that
time.
Early in 2004, an addition to the building was constructed at a
cost of $570,000. At that time, it was estimated that the remaining
life of the building would be, as originally...
In 1993, Waterway Company completed the construction of a building at a cost of $2,380,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $71,200 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $595,000. At that time, it was estimated that the remaining life of the building would be, as originally...