The controller of Rather Production has collected the following
monthly expense data for analyzing the cost behavior of electricity
costs.
| Total Electricity Costs |
Total Machine Hours |
|||||||
| January | $2,500 | 300 | ||||||
| February | 3,000 | 350 | ||||||
| March | 3,600 | 500 | ||||||
| April | 4,500 | 690 | ||||||
| May | 3,200 | 400 | ||||||
| June | 4,900 | 700 | ||||||
| July | 4,100 | 650 | ||||||
| August | 3,800 | 520 | ||||||
| September | 5,100 | 680 | ||||||
| October | 4,200 | 630 | ||||||
| November | 3,300 | 350 | ||||||
| December | 5,860 | 720 | ||||||
a) Determine the fixed- and variable-cost components using the high-low method.
b) What electricity cost does the cost equation estimate for a level of activity of 500 machine hours? By what amount does this differ from March’s observed cost for 500 machine hours?
c) What electricity cost does the cost equation estimate for a level of activity of 700 machine hours? By what amount does this differ from June’s observed cost for 700 machine hours?
Answer:-a)- Variable Cost per machine hour = $8 per hour.
Total Fixed Cost =$100
Explanation:-
High-Low Method:-
Variable Cost per Unit
Variable cost per unit (b) is calculated using the following formula:
|
Variable cost per unit = (Y2-Y1)/(X2-X1) |
|
Where,
y2 is the total cost at highest level of activity;
y1 is the total cost at lowest level of activity;
x2 are the number of units/miles/ labor ,machine hours etc. at
highest level of activity; and
x1 are the number of units/miles/ labor, machine hours etc. at
lowest level of activity
The variable cost per unit is equal to the slope of the cost volume line (i.e. change in total cost ÷ change in number of machine hours).
Total Fixed Cost
Total fixed cost (a) is calculated by subtracting total variable cost from total cost, thus:
|
Total Fixed Cost = (y2 – b)*x2 = (y1 – b*x1) |
We have,
at highest activity: x2 = 720 Machine
hours; y2 = $5860
at lowest activity: x1 = 300 Machine
hours; y1 = $2500
Variable Cost per delivery = ($5860-$2500) /(720 hours −300 hours)
= $3360/420 hours
= $8 per machine hour
Total Fixed Cost = $5860 − ($8 per hour*720 hours)
= $5860-$5760
=$100
b)- Electricity costs for a level of activity of 500 machine hours = ($8 per hour*500 hours)+$100
= $4000+$100
= $4100
The amount differ from March’s observed cost for 500 machine hours = $4100-$3600
= $500
c)- Electricity costs for a level of activity of 700 machine hours = ($8 per hour*700 hours)+$100
= $5600+$100
= $5700
The amount differ from March’s observed cost for 700 machine hours = $5700-$4900
= $800
The controller of Rather Production has collected the following monthly expense data for analyzing the cost...
The controller of Standard Industries has collected the following monthly expense data for analyzing the cost behavior of electricity costs. Total Total Electricity Costs Machine Hours January $2,500 300 February 3,000 350 March 3,600 500 April 4,500 690 May 3,200 400 June 4,900 700 July 4,100 650 August 3,800 520 September 5,100 680 October 4,200 630 November 3,300 350 December 6,100 720 Instructions (a) Determine the fixed- and variable-cost components using regression analysis (We recommend the use of Excel.) (b) ...
2. The controller of Hall Industries has collected the following
monthly expense data for use in analyzing the cost behavior of
maintenance costs.
total
total
Month
Maintenance Costs
Machine Hours
1
2460
3500
2
3000
4000
3
3600
6000
4
4500
7900
5
3200
5000
6
4620
8000
(a) Determine the fixed- and variable-cost components using the
high-low method.
.................................
500 P18.1A (LO1, 2) The controller of Rather Production has collected the following monthly expense data for analyzing the cost...
The controller of Rather Production has collected the following monthly expense data for analyzing the cost behavior of electricity costs. Total Electricity Costs. Instructions a. Determine the fixed- and variable-cost components using the high-low method. b. What electricity cost does the cost equation estimate for a level of activity of 500 machine hours? By what amount does this differ from March's observed cost for 500 machine hours? c. What electricity cost does the cost equation estimate for a level of activity of 700 machine...
The controller of Cullumber Production has collected the following monthly expense data for analyzing the cost behavior of electricity costs. January February March April May June July August September October November December Total Total Electricity Costs Machine Hours $2,700 290 2,980 350 3,590 480 4,620 690 3,160 460 5,000 780 4,110 620 3,910 510 5,120 680 4,200 620 3,200 350 7,290 800 (a) Determine the fixed- and variable-cost components using the high-low method. Fixed-costst 4 Variable-costs जी (b) What electricity...
The controller of Wildhorse Production has collected the following monthly expense data for analyzing the cost behavior of electricity costs. January February March April May June July August September October November December Total Total Electricity Costs Machine Hours $2,450 230 3,060 380 3,520 480 4,760 685 3,190 410 4,910 800 4,030 650 3,870 5,040 680 4,260 3,250 6,580 820 540 610 380 (a) Determine the fixed- and variable-cost components using the high-low method. Fixed-costs Variable costs (b) What electricity cost...
Problem 22-01A a-c The controller of Pharoah Production has collected the following monthly expense data for analyzing the cost behavior of electricity costs Total Total Electricity Costs Machine Hours anuary February March April May June July August September October November December $2,570 2,910 3,580 4,590 3,210 4,910 4,140 3,880 5,090 4,270 3,260 6,490 250 320 460 690 420 790 625 520 675 630 320 810 Determine the fixed- and variable-cost components using the high-low method Fixed-costs Variable-costs What electricity cost...
Question 3 The controller of Sheridan Production has collected the following monthly expense data for analyzing the cost behavior of electricity costs. January February March April 470 May June July August September October November December Total Total Electricity Costs Machine Hours $2,370 210 2,920 390 3,580 4,530 3,210 4,980 4,150 3,850 5,160 665 4,240 3,240 7,770 (a) Determine the fixed- and variable-cost components using the high-low method. Fixed-costs Variable-costs (b) What electricity cost does the cost equation estimate for a...
The controller of Wildhorse Production has collected the following monthly expense data for analyzing the cost behavior of electricity costs. (a) Determine the fixed- and variable-cost components using the high-low method.(b) What electricity cost does the cost equation estimate for a level of activity of 460 machine hours?(c) What electricity cost does the cost equation estimate for a level of activity of 790 machine hours?
The controller of Norton Industries has collected the following monthly expense data for use in analyzing the cost behavior of maintenance costs. Month Total Maintenance Costs Total Machine Hours January $2,550 300 February 2,850 350 March 3,450 500 April 4,350 690 May 3,050 500 June 5,460 700 Incorrect answer iconYour answer is incorrect. Determine the variable cost components using the high-low method. (Round variable cost to 3 decimal places e.g. 12.250.) Variable cost per machine hour $ 7.3 eTextbook and...
The controller of Norton Industries has collected the following
monthly expense data for use in analyzing the cost behavior of
maintenance costs.
Month
Total
Maintenance Costs
Total
Machine Hours
January
$2,550
300
February
2,850
350
March
3,450
500
April
4,350
690
May
3,050
500
June
5,460
700
Determine the variable cost components using the high-low
method. (Round variable cost to 3 decimal places e.g.
12.250.)
Variable cost per machine hour
$
LINK TO TEXT
LINK TO TEXT
Determine the fixed...