Question

The controller of Rather Production has collected the following monthly expense data for analyzing the cost...

The controller of Rather Production has collected the following monthly expense data for analyzing the cost behavior of electricity costs.

Total
Electricity Costs
Total
Machine Hours
January $2,500 300
February 3,000 350
March 3,600 500
April 4,500 690
May 3,200 400
June 4,900 700
July 4,100 650
August 3,800 520
September 5,100 680
October 4,200 630
November 3,300 350
December 5,860 720

a) Determine the fixed- and variable-cost components using the high-low method.

b) What electricity cost does the cost equation estimate for a level of activity of 500 machine hours? By what amount does this differ from March’s observed cost for 500 machine hours?

c) What electricity cost does the cost equation estimate for a level of activity of 700 machine hours? By what amount does this differ from June’s observed cost for 700 machine hours?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:-a)- Variable Cost per machine hour = $8 per hour.

Total Fixed Cost =$100

Explanation:-

High-Low Method:-

Variable Cost per Unit

Variable cost per unit (b) is calculated using the following formula:

Variable cost per unit = (Y2-Y1)/(X2-X1)

Where,
y2 is the total cost at highest level of activity;
y1 is the total cost at lowest level of activity;
x2 are the number of units/miles/ labor ,machine hours etc. at highest level of activity; and
x1 are the number of units/miles/ labor, machine hours etc. at lowest level of activity

The variable cost per unit is equal to the slope of the cost volume line (i.e. change in total cost ÷ change in number of machine hours).

Total Fixed Cost

Total fixed cost (a) is calculated by subtracting total variable cost from total cost, thus:

Total Fixed Cost = (y2 – b)*x2 = (y1 – b*x1)

We have,
at highest activity: x2 = 720 Machine hours; y2 = $5860
at lowest activity: x1 = 300 Machine hours; y1 = $2500

Variable Cost per delivery = ($5860-$2500) /(720 hours −300 hours)  

= $3360/420 hours

= $8 per machine hour
Total Fixed Cost = $5860 − ($8 per hour*720 hours)

= $5860-$5760

=$100

b)- Electricity costs for a level of activity of 500 machine hours = ($8 per hour*500 hours)+$100

= $4000+$100

= $4100

The amount differ from March’s observed cost for 500 machine hours = $4100-$3600

= $500

c)- Electricity costs for a level of activity of 700 machine hours = ($8 per hour*700 hours)+$100

= $5600+$100

= $5700

The amount differ from March’s observed cost for 700 machine hours = $5700-$4900

= $800

Add a comment
Know the answer?
Add Answer to:
The controller of Rather Production has collected the following monthly expense data for analyzing the cost...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The controller of Standard Industries has collected the following monthly expense data for analyzing the cost...

    The controller of Standard Industries has collected the following monthly expense data for analyzing the cost behavior of electricity costs. Total Total Electricity Costs Machine Hours January $2,500 300 February   3,000 350 March   3,600 500 April   4,500 690 May   3,200 400 June   4,900 700 July   4,100 650 August   3,800 520 September   5,100 680 October   4,200 630 November   3,300 350 December   6,100 720 Instructions (a)   Determine the fixed- and variable-cost components using regression analysis (We recommend the use of Excel.) (b)  ...

  • 2. The controller of Hall Industries has collected the following monthly expense data for use in...

    2. The controller of Hall Industries has collected the following monthly expense data for use in analyzing the cost behavior of maintenance costs. total total Month Maintenance Costs Machine Hours 1 2460 3500 2 3000 4000 3 3600 6000 4 4500 7900 5 3200 5000 6 4620 8000 (a) Determine the fixed- and variable-cost components using the high-low method. ................................. 500 P18.1A (LO1, 2) The controller of Rather Production has collected the following monthly expense data for analyzing the cost...

  • The controller of Rather Production has collected the following monthly expense data for analyzing the cost behavior of electricity costs.

    The controller of Rather Production has collected the following monthly expense data for analyzing the cost behavior of electricity costs. Total Electricity Costs. Instructions a. Determine the fixed- and variable-cost components using the high-low method. b. What electricity cost does the cost equation estimate for a level of activity of 500 machine hours? By what amount does this differ from March's observed cost for 500 machine hours? c. What electricity cost does the cost equation estimate for a level of activity of 700 machine...

  • The controller of Cullumber Production has collected the following monthly expense data for analyzing the cost...

    The controller of Cullumber Production has collected the following monthly expense data for analyzing the cost behavior of electricity costs. January February March April May June July August September October November December Total Total Electricity Costs Machine Hours $2,700 290 2,980 350 3,590 480 4,620 690 3,160 460 5,000 780 4,110 620 3,910 510 5,120 680 4,200 620 3,200 350 7,290 800 (a) Determine the fixed- and variable-cost components using the high-low method. Fixed-costst 4 Variable-costs जी (b) What electricity...

  • The controller of Wildhorse Production has collected the following monthly expense data for analyzing the cost...

    The controller of Wildhorse Production has collected the following monthly expense data for analyzing the cost behavior of electricity costs. January February March April May June July August September October November December Total Total Electricity Costs Machine Hours $2,450 230 3,060 380 3,520 480 4,760 685 3,190 410 4,910 800 4,030 650 3,870 5,040 680 4,260 3,250 6,580 820 540 610 380 (a) Determine the fixed- and variable-cost components using the high-low method. Fixed-costs Variable costs (b) What electricity cost...

  • Problem 22-01A a-c The controller of Pharoah Production has collected the following monthly expense data for...

    Problem 22-01A a-c The controller of Pharoah Production has collected the following monthly expense data for analyzing the cost behavior of electricity costs Total Total Electricity Costs Machine Hours anuary February March April May June July August September October November December $2,570 2,910 3,580 4,590 3,210 4,910 4,140 3,880 5,090 4,270 3,260 6,490 250 320 460 690 420 790 625 520 675 630 320 810 Determine the fixed- and variable-cost components using the high-low method Fixed-costs Variable-costs What electricity cost...

  • Question 3 The controller of Sheridan Production has collected the following monthly expense data for analyzing...

    Question 3 The controller of Sheridan Production has collected the following monthly expense data for analyzing the cost behavior of electricity costs. January February March April 470 May June July August September October November December Total Total Electricity Costs Machine Hours $2,370 210 2,920 390 3,580 4,530 3,210 4,980 4,150 3,850 5,160 665 4,240 3,240 7,770 (a) Determine the fixed- and variable-cost components using the high-low method. Fixed-costs Variable-costs (b) What electricity cost does the cost equation estimate for a...

  • The controller of Wildhorse Production has collected the following monthly expense data for analyzing the cost behavior of electricity costs.

    The controller of Wildhorse Production has collected the following monthly expense data for analyzing the cost behavior of electricity costs. (a) Determine the fixed- and variable-cost components using the high-low method.(b) What electricity cost does the cost equation estimate for a level of activity of 460 machine hours?(c) What electricity cost does the cost equation estimate for a level of activity of 790 machine hours? 

  • The controller of Norton Industries has collected the following monthly expense data for use in analyzing...

    The controller of Norton Industries has collected the following monthly expense data for use in analyzing the cost behavior of maintenance costs. Month Total Maintenance Costs Total Machine Hours January $2,550 300 February 2,850 350 March 3,450 500 April 4,350 690 May 3,050 500 June 5,460 700 Incorrect answer iconYour answer is incorrect. Determine the variable cost components using the high-low method. (Round variable cost to 3 decimal places e.g. 12.250.) Variable cost per machine hour $ 7.3 eTextbook and...

  • The controller of Norton Industries has collected the following monthly expense data for use in analyzing...

    The controller of Norton Industries has collected the following monthly expense data for use in analyzing the cost behavior of maintenance costs. Month Total Maintenance Costs Total Machine Hours January $2,550 300 February 2,850 350 March 3,450 500 April 4,350 690 May 3,050 500 June 5,460 700 Determine the variable cost components using the high-low method. (Round variable cost to 3 decimal places e.g. 12.250.) Variable cost per machine hour $ LINK TO TEXT LINK TO TEXT Determine the fixed...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT