8. You are managing a project with a total budget of $600,000. According to the schedule, your team should have completed 50% of the work by now. But at the latest status meeting, the team reported that 55% of the work has actually been completed. The team has spent $360,000 so far on the project. How would you BEST describe this project?
a. The project is ahead of schedule and within its budget
b. The project is behind schedule and within its budget
c. The project is ahead of schedule and over its budget
d. The project is behind schedule and over its budget
c. The project is ahead of schedule and over its budget
As per the schedule of the project, the project is ahead of the schedule although behind the budget.
Budget status = 0.55*600000
= $330000
Hence the project is over budget
8. You are managing a project with a total budget of $600,000. According to the schedule,...
A given task was estimated to cost $15,750 to complete. Currently, the project team has completed approximately 65% of the task, and have spent $10,500. a. Determine the indices: AC, PV, and EV b. Derive the values for cost and schedule variances, as well as cost performance and schedule performance indices. Is this project ahead or behind on schedule, and is it ahead or behind on budget? c. How much additional money will be required to finish this project? d....
A given task was estimated to cost $15,750 to complete. Currently, the project team has completed approximately 65% of the task, and have spent $10,500. a. Determine the indices: AC, PV, and EV b. Derive the values for cost and schedule variances, as well as cost performance and schedule performance indices. Is this project ahead or behind on schedule, and is it ahead or behind on budget? c. How much additional money will be required to finish this project? d....
Canyouhelpme with this questionYou are managing a project to expand a major county road in your area. The project is expected to take 1 year and the expenses are budgeted to be $12,500 per month. Six months after the project started, you find out that the project is 50% complete, and that you have spent $70,000. Fill in the information in the table below: Item Value BAC PV EV AC CV = EV-AC SV = EV – PV CPI =...
A project has just completed its 87th task of a total of 150 tasks in its project plan. The project has a total budget of $1,500,000. It was scheduled to have spent $500,000 at this point in the plan, but has actually spent only $400,000. The project manager estimates that the value of the work actually finished is $300,000. What are the spending and schedule variances for the project? What are the SPI and CPI? What is the EAC, assuming...
Miles Wilder, project manager for the Cybersonic project, considers himself a “project manager’s project manager.” He claims to use the principles of good project management, starting with having a plan and using it to carefully track the project. He announces to his team leaders that status meetings will be held on alternate Mondays throughout the expected year-long project. All 18 project team leaders must attend and give rundowns of the tasks they are currently working on.All the team leaders show...
Your company was hired as a subcontractor for a client's "Destiny project and awarded two main work packages within that project. Your company refers to this project internally using the cost code "P2 2019". You're given the table below that lists the work packages, their cost code, their budget, and their scheduled start day and end day (as agreed upon with the main contractor). The start and end days are measured in working days after the main project's start. So,...
You are a software project manager for a software firm budgeted at 650,000$. As of today, the project should be 42% complete, but after reviewing the status of the scheduled tasks involved in the project, it is clear that only 30% of the work has been completed. The team has spent 425,000$ thus far. What is the current status of the project? 1)calculate PV, AC, EV, SPI, CPI, CV, CV%, SV, SV%, EAC, ETC. 2)write a short description of what...
Javier is a senior project manager that is managing the next major software release for the company’s gaming system. The project has fallen behind schedule and Javier has asked you if he could use a couple of your software engineers over the next two weeks to catch up. Your project is on time and is not as visible to the executive team. Javier has helped you out on your project in the past with advice and resources. He is also...
You are currently working on a project that had an original budget of $300,000 and an original schedule of 27 weeks. You currently have spent $100,000 and are over budget by $15,000. Your boss comes into your office and wants to discuss your project. Specifically, she wants to know how much more money it is going to take to complete the project. Assuming you have completed $78,000 of the deliverables. What do you tell her?
6. Your project is expected to run for three consecutive years. Your organization is introducing earned value management as part of the planning and managing of this project. The project budget Php 50,000.000. The budget is consistent across the three years. You are exactly 18 months into the project, 30 % of the total budget has been spent, and 40 % of the work is complete. Regarding its schedule and budget, by what extent your project status stand? 7. Due...