Smith Construction Homework Assignment
Smith’s Construction firm currently has three project sites underway in various counties in Iowa. Each requires a specific supply of gravel. Three gravel pits are available to provide for the company’s needs, but shipping costs vary by location. The following table summarizes the data. The $costs shown in the table are the unit shipping costs to ship a ton of the gravel from a specific pit location to a specific project site.
|
TO FROM |
Project Site 1 |
Project Site 2 |
Project Site 3 |
Pit Capacity (Tons) |
|
Ames pit |
$9 |
$8 |
$7 |
1,500 |
|
Davenport pit |
$7 |
$11 |
$6 |
1,750 |
|
Des Moines pit |
$4 |
$3 |
$12 |
2,750 |
|
Project Requirements (Tons) |
2,000 |
3,000 |
1,000 |
6,000 |
Please submit an Excel file containing your work. Your work must include the following:
Please show formulas and calculations step by step
a)
First let’s solve the simple one
The model is shown below

The formulas are shown below

The solver parameters are shown below

The result is shown below. The second table shows the optimal shipping plan and cost.

b)
Now, if we ship from Ames and Davenport to Des Moines and consolidate it then we need to consider the inflow and outflow of the De Moines pit. In order to do that we need to make a few modifications to our older model. The new model will be a 4x3 matrix instead of 3x3.
The new model is shown below. The modified formula for the total cost is seen in the formula bar.

The formulas for total cost and the total extraction for Des Moines site has been modified. They are shown below

The solver parameters are shown below.

The result is shown below.

c)
There are various factors that could change the decisions. These are
The cost coefficients or the shipping cost. For example, if the shipping cost between Davenport and Site 2 reduced to $2 then it would definitely change the solution.
The requirements. If the requirements in sites changes, it changes the solution
The capacity. If the capacity of the pits change, it changes the solution as well
d)
One key information that is missing is the extraction cost. The shipping cost are one component of the overall cost but we may also need to consider the extraction cost (or setup cost) in practical scenarios.
Smith Construction Homework Assignment Smith’s Construction firm currently has three project sites underway in various counties...
A contractor, Susan Mayer, has to haul gravel to three building sites. She can purchase as much as 18 tons at a gravel pit in the north of the city and 14 tons at one in the south. She needs 10, 5 and 10 tons at sites 1, 2, and 3 respectively. The purchase price per ton at each gravel pit and the hauling cost per ton are given in the table below. 2 Pit North South Hauling Cost per...
Location Section Project A small logistic company named LogTransit currently has 3 manufacturing facilities (suppliers) called Supplier #1, #2 and #3 to supply for goods of its 3 retail stores (customers) called Customer A, B, and C. Due to customer demands at stores are increasing, the company is considering to construct a new manufacturing facility. The new factory will have a supply capacity of 200 units per week. After screening many potential sites, Toledo and Cincinnati have been determined to...