Question

A company's prime costs total $4,100,000 and its conversion costs total $8,100,000. If direct materials are...

A company's prime costs total $4,100,000 and its conversion costs total $8,100,000. If direct materials are $1,550,000 and factory overhead is $5,550,000, then direct labor is: $16,200,000. $2,550,000. $1,000,000. $4,000,000. $4,100,000.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
W.N
Calculation of Direct Labor
Conversion cost Direct labor+Factory OH
$8100000 Direct Labor+$5550000
Direct Labor $8100000-$5550000
                             $2550000
Hence the correct option is B
Add a comment
Know the answer?
Add Answer to:
A company's prime costs total $4,100,000 and its conversion costs total $8,100,000. If direct materials are...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT