Question

what is the risk management strategy of the procurement of Italian GSM-R technical equipment, In order...

what is the risk management strategy of the procurement of Italian GSM-R technical equipment, In order to help RFI Procurement Department in better anticipating unpleasant and dangerous circumstances that a GSM-R procurement initiative may face, specify 4 risks that are seen highly relevant in the procurement scenario of GMS-R technical equipment. For each of them, provide (in a tabular format): • Likelihood rating (1-5 scale) • Impact rating (1-5 scale) • One possible mitigation measure

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The risk management strategy of the procurement of Italian GSM-R technical equipment are-

  • Considering all the different train types which travel intercity, suburban, goods transportation or freight etc.
  • Checking out language capability as it is essential for all business communications- meetings, presentations, visits, etc.
  • Monitoring the design and construction of the technical equipment.
  • Operations and maintenance of such technical equipment is to be determined as well.
  • The railway must define its radio system before such procurement. Radio settings of all the trains and necessary back-up plans in case of radio problems.
  • Checking the reasons behind cancelled trains. Majorly it is seen that such problem happens due to network problem, accidents, etc.
  • Speed of the train- There should be reduced speed (up to 60 meter per hour) for safety.

4 risks that are seen highly relevant in the procurement scenario of GMS-R technical equipment are:

  • Increased procurement cost
  • Misuse of resources
  • Impractical Timeframe
  • Insufficient funding

Likelihood rating

Likelihood rating

Likelihood rating

Likelihood rating

Risk

Increased procurement cost

Misuse of resources

Impractical timeframe

Insufficient funding

High- High cost of less useful product

Medium- Resources being mis -utilised

High- Inadequate response from tenderers, delivery schedule not met, less competition

Medium- Re-tender requirement for additional cost, delay in purchase of the equipment

Impact Rating

Medium- Could result in significant financial loss

High- Could result in delay in procurement

High- Could result in major damage in terms of loss to the mission

High- Could result in major significant loss to operations and procurement of the equipment

Add a comment
Know the answer?
Add Answer to:
what is the risk management strategy of the procurement of Italian GSM-R technical equipment, In order...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT