Acme Company’s production budget for August is 17,600 units and includes the following component unit costs: direct materials, $7.70; direct labor, $10.10; variable overhead, $6.20. Budgeted fixed overhead is $33,000. Actual production in August was 18,810 units. Actual unit component costs incurred during August include direct materials, $8.50; direct labor, $9.10; variable overhead, $6.90. Actual fixed overhead was $34,600. The standard direct material cost per unit consists of 11 pounds of raw material at $0.7 per pound. During August, 319,770 pounds of raw material were used that were purchased at $0.50 per pound. Required: Calculate the materials price variance and materials usage variance for August
Answer:- Material price variance = $63954 F
Material Quantity variance = $79002 U
Explanation-
Material price variance = (Standard price – Actual price) * Actual quantity purchased
= ($0.70 per pound - $0.50 per pound)*319770 pound
= $63954 Favorable
Material Quantity variance = (Standard Quantity- Actual Quantity used)*Standard price
=(206910 pounds – 319770 pounds)* $0.70 per pound
= $79002 Unfavorable
Where:-
Standard Quantity = No. of pound per unit*Actual output
=11 pounds per unit *18810 units =206910 pounds
Acme Company’s production budget for August is 17,600 units and includes the following component unit costs:...
Acme Company’s production budget for August is 17,900 units and includes the following component unit costs: direct materials, $8.00; direct labor, $10.40; variable overhead, $6.00. Budgeted fixed overhead is $36,000. Actual production in August was 18,135 units. Actual unit component costs incurred during August include direct materials, $8.20; direct labor, $9.80; variable overhead, $7.20. Actual fixed overhead was $37,900. The standard direct labor cost per unit consists of 0.5 hour of labor time at $20.8 per hour. During August, $177,723...
Acme Company’s production budget for August is 18,300 units and
includes the following component unit costs: direct materials,
$6.30; direct labor, $10.80; variable overhead, $6.50. Budgeted
fixed overhead is $40,000. Actual production in August was 19,110
units. Actual unit component costs incurred during August include
direct materials, $9.00; direct labor, $10.20; variable overhead,
$7.60. Actual fixed overhead was $42,300.
Required:
Prepare a performance report, including each cost component.
(Indicate the effect of each variance by selecting "F" for
favorable, "U"...
Acme Company’s production budget for August is 19,300 units and
includes the following component unit costs: direct materials,
$9.00; direct labor, $11.80; variable overhead, $5.80. Budgeted
fixed overhead is $50,000. Actual production in August was 21,870
units. Actual unit component costs incurred during August include
direct materials, $10.00; direct labor, $11.20; variable overhead,
$7.00. Actual fixed overhead was $53,300. The standard direct labor
cost per unit consists of 0.5 hour of labor time at $23.6 per hour.
During August, $244,944...
Acme Company’s production budget for August is 19,000 units and includes the following component unit costs: direct materials, $8.0; direct labor, $11.6; variable overhead, $5.6. Budgeted fixed overhead is $47,000. Actual production in August was 20,445 units. Actual unit component costs incurred during August include direct materials, $9.80; direct labor, $10.00; variable overhead, $6.40. Actual fixed overhead was $50,000. The standard variable overhead rate per unit consists of $5.6 per machine hour and each unit is allowed a standard of...
Acme Company's production budget for August is 18,000 units and includes the following component unit costs: direct materials. 58.0 direct labor, 510.5, variable overhead, $6.4. Budgeted fixed overhead is $37,000. Actual production in August was 19.950 units. Actual unit component costs incurred during August include direct materials, $8.70; direct labor, $9.90: variable overhead, 5730. Actual fixed overhead was $39.000. The standard variable overhead rate per unit consists of $6.4 per machine hour and each unit is allowed a standard of...
Acme Company's production budget for August is 18,000 units and includes the following component unit costs: direct materials, $8.0; direct labor, $10.5; variable overhead, $6.4. Budgeted fixed overhead is $37,000. Actual production in August was 19,950 units. Actual unit component costs incurred during August include direct materials, $8.70; direct labor, $9.90; variable overhead, $7.30. Actual fixed overhead was $39,000. The standard fixed overhead application rate per unit consists of $2 per machine hour and each unit is allowed a standard...
Acme Company's production budget for August is 18,500 units and includes the following component unit costs: direct materials, $8.10; direct labor, $11.00; variable overhead, $5.00. Budgeted fixed overhead is $42,000. Actual production in August was 20,250 units. Actual unit component costs incurred during August include direct materials, $9.20; direct labor, $10.40; variable overhead, $5.50. Actual fixed overhead was $44,500. The standard direct labor cost per unit consists of 0.5 hour of labor time at $22 per hour. During August, $210,600...
Acme Company's production budget for August is 18,200 units and includes the following component unit costs: direct materials, $8.00; direct labor, $10.70; variable overhead, $6.70. Budgeted fixed overhead is $39,000. Actual production in August was 19,440 units. Actual unit component costs incurred during August include direct materials, $8.90; direct labor, $9.70; variable overhead, $7.50. Actual fixed overhead was $41,200. The standard direct labor cost per unit consists of 0.5 hour of labor time at $21.4 per hour. During August, $188,568...
Acme Company’s production budget for August is 18,000 units and includes the following component unit costs: direct materials, $8.00; direct labor, $11.20; variable overhead, $6.00. Budgeted fixed overhead is $44,000. Actual production in August was 18,400 units. Required: Prepare a flexible budget that would be used to compare against actual production costs for August. (Round "Cost per unit" to 2 decimal places.) Original Budget Flexed Budget Cost Formula (18,000 units) (18,400 units) Direct materials Direct labor Variable overhead Fixed overhead...
Acme Company's production budget for August is 19,000 units and includes the following component unit costs: direct materials, $8.00; direct labor, $11.60; variable overhead, $5.60. Budgeted fixed overhead is $47,000. Actual production in August was 20,445 units. Actual unit component costs incurred during August include direct materials, $9.80; direct labor, $10.00; variable overhead, $6.40. Actual fixed overhead was $50,000. Required: Prepare a performance report, including each cost component. (Indicate the effect of each variance by selecting "F" for favorable, "U"...