You have 3 projects to consider.
Project A with current and projected future rate of return
Discount Factor at 17%.
|
Yr |
Inflows |
Outflows |
Netflow |
Discounted netflow |
Discounted rate |
|
0 |
-$450,000 |
-$450,000 |
-$450,000 |
1.0000 |
|
|
1 |
$150,000 |
$150,000 |
$128,205 |
0.8547 |
|
|
2 |
$150,000 |
$150,000 |
$109,577 |
0.7305 |
|
|
3 |
$150,000 |
$150,000 |
$93,656 |
0.6244 |
|
|
4 |
$150,000 |
$150,000 |
$80,048 |
0.5337 |
|
|
5 |
$150,000 |
$150,000 |
$68,417 |
0.4561 |
Project B with current and projected future rate of return
Discount Factor 17%
|
Yr |
Inflows |
Outflows |
Netflow |
Discounted netflow |
Discounted rate |
|
0 |
-$400,000 |
-$400,000 |
-$400,000 |
1.0000 |
|
|
1 |
$0 |
$0 |
$0 |
0.8547 |
|
|
2 |
$50,000 |
$50,000 |
$36,526 |
0.7305 |
|
|
3 |
$200,000 |
$200,000 |
$124,874 |
0.6244 |
|
|
4 |
$300,000 |
$300,000 |
$160,095 |
0.5337 |
|
|
5 |
$200,000 |
$200,000 |
$91,222 |
0.4561 |
Project C: with current and projected future rate of return
Discount Factor 17%
|
Yr |
Inflows |
Outflows |
Netflow |
Discounted netflow |
Discounted rate |
|
0 |
-$105,250 |
-$105,250 |
-$105,250 |
1.0000 |
|
|
1 |
$25,000 |
$25,000 |
$21,368 |
0.8547 |
|
|
2 |
$25,000 |
$25,000 |
$18,263 |
0.7305 |
|
|
3 |
$25,000 |
$25,000 |
$15,609 |
0.6244 |
|
|
4 |
$25,000 |
$25,000 |
$13,341 |
0.5337 |
answer the following questions.
| 1. |
Project A NPV. You do not include the initial $XXXXX cost as one of the values, because the payment occurs at the beginning of the first period is $29,902 |
|
| 2. |
the highest project is A. |
|
| 3. |
Project C NPV. You include the initial $XXXXX cost as one of the values, because the payment occurs at the end of the first period is not $18,180 |
|
| 4. |
Project B NPV. You do not include the initial $XXXXX cost as one of the values, because the payment occurs at the beginning of the first period is $13,717 |
|
| 5. |
Project B NPV. You include the initial $XXXXX cost as one of the values, because the payment occurs at the end of the first period is $10,869 |
|
| 6. |
Project C NPV. You do not include the initial $XXXXX cost as one of the values, because the payment occurs at the beginning of the first period is -$21,271 |
|
| 7. |
Project A NPV. You include the initial $XXXXX cost as one of the values, because the payment occurs at the end of the first period is $26,557 |
Project A NPV=-450000+150000/17%*(1-1/1.17^5)=29901.92
Project B NPV=-400000+0/1.17+50000/1.17^2+200000/1.17^3+300000/1.17^4+200000/1.17^5=12717.03378
Project C NPV=-105250+25000/17%*(1-1/1.17^4)=-36669.1247
the highest project is A.
You have to include the initial cost for all projects
You have 3 projects to consider. Project A with current and projected future rate of return...
d. Calculate the series of NATCFs and the
NPV for this project at a 10% discount rate assuming that you
finance the investment using a 7-year loan with a fixed interest
rate of 6% (annual compounding and end-of-year payments) and a 50%
down payment. Complete the final two columns of Table 1 below.
Hint: This will require you to adjust the NATCF calculations
that you made for part a. You will need to account for the loan
when calculating the...
Please answer this fully. This is a major final project so it's
crucial I get it right. Thank you so much!
You are working in a strategic management role at Best Bean, Inc., a chain of coffee shops. Your team is considering expanding in 2020 by building one or more new retail outlets in the Detroit area. Four locations (A, B, C, and D) are being considered. Locations A, B, and Care ten year investments, with income projections shown in...
Refer to Table 1. Write the Excel formula for each cell marked with “?” in columns B, C and D such that formula could be copied and pasted into columns D, E, F and G using Microsoft Excel without further editing. There is no need to explicitly write the Excel formula for cells marked with “Copy & paste”. Label each formula clearly with cell reference position. In 2020, BS Bank employs 800 employees in its call centres in the United States...