Short term decision making
Shot plc manufactures three types of furniture products - chairs,
stools and tables. The budgeted unit cost and resource requirements
of each of these items are detailed below:
Chair Stools Table
($) ($) ($) Timber cost 5.00 15.00 10.00
Direct labour cost 4.00 10.00 8.00
Variable overhead cost 3.00 7.50 6.00
Fixed overhead cost 4.50 11.25 9.00
16.50 43.75 33.00
Budgeted volumes 4,000 2,000 1,500
per annum
ICLBAT/JANUARY2019
6
These volumes are believed to equal the market demand for these
products. The fixed overhead costs are attributed to the three
products on the basis of direct labour hours. The labour rate is
$4.00 per hour. The cost of timber is $2.00 per square metre. The
products are made from a specialist timber. A memo from the
purchasing manager advises you that because of a problem with the
supplier it is to be assumed that this specialist timber is limited
in supply to 20,000 square metres per annum.
The sales director has already accepted an order for 500 chairs,
100 stools and 150 tables, which if not supplied would incur a
financial penalty of $2,000. These quantities are included in the
market demand estimates above. The selling prices per unit of the
three products are: -
Chair $20.00
Stool $50.00
Table $40.00
Required:
(a) Determine the optimum production plan and state the net profit
that this should yield per annum. (13 marks) (b) Discuss one
qualitative factor that you should consider (especially in the long
term) in your decision in part (a). (2 marks)
Short term decision making Shot plc manufactures three types of furniture products - chairs, stools...
Short term decision making Shot plc manufactures three types of furniture products - chairs, stools and tables. The budgeted unit cost and resource requirements of each of these items are detailed below: Chair ($) Stools($) Table ($) Timber cost 5.00 15.00 10.00 Direct labour cost 4.00 10.00 8.00 Variable overhead cost 3.00 7.50 6.00 Fixed overhead cost 4.50 11.25 9.00 16.50 43.75 33.00 Budgeted volumes per...
ii) Treehouse Furniture manufactures a variety of desks, chairs, tables and shelf units which are sold to public school systems throughout Queensland. The accountant of the company's School Desk Division is currently preparing a budget for the first quarter of 20x9. The following sales forecast has been made by the division's sales manager. January February March 5,000 desk and chair sets 6,000 desk and chair sets 7,500 desk and chair sets Each desk and chair set requires 10 metres of...
Lyon Factory Ltd. manufactures two products: chairs and stools. Each chair requires 3 m of upholstery and 4 kg steel. Each stool requires 2 m of upholstery and 5 kg of steel. Upholstery costs $2 per meter and steel costs $5 per kilogram. Lyon Factory expects inventories at January 1, 2017, to be as follows: Chairs Stools Upholstery 25 units 15 units 75 m Inventories of raw materials should not be allowed to fall below the amounts given as at...
Q.2 (Max Marks:90) Bombera Ltd operates at capacity and makes glass-topped dining tables and wooden chairs, which are then typically sold as sets of four chairs with one table. However, some customers purchase replacement or extra chairs, and others buy some chairs or a table only, so the sales mix is not exactly 4:1. Bombera Ltd is planning its annual budget for the financial year 2018. Information for 2018 follows: Input prices Direct materials Wood $5.30 per board metre Glass...
A furniture making business manufactures quality furniture to customers' orders. It has three production departments and two service departments. Budgeted overhead costs for the coming year are: Totals £ Rent and Rates 12, 800 21.00 Machine insurance 6,000 2,000 Canteen 3200 6,400 Depreciation 18,000 36000 Production supervisor's salaries Heating and lighting 6,400 2,810 70,400 32.000 The three production departments - A B and C,, and the two service departments - X and V, are housed in the new premises, the...
Case #2 Breakaway Inc. manufactures three products at its plant in Minnedosa, Manitoba: Montage, Creek, and Pulse. In this facility, production is limited to 450,000 machine hours per year. Direct material and direct labour costs are variable. To develop a production plan for the upcoming year, the company's accountant has compiled the following data: Montage Creek Pulse Total demand for 2021 350,000 350,000 350,000 Sales price per unit $20.00 $28.00 $24.00 Direct materials cost per unit $8.00 $9.00 $10.00 Direct...
This is BBM206/05 Business Accounting
II subjectQuestion 3 Loci Sdn Bhd manufactures three products, X, Y and Z. Demand for products X and Y is relatively elastic whilst demand for product Z is relatively inelastic. Each product uses the same materials and the same type of direct labour but in different quantities. For many years, the company has been using full absorption costing and absorbing overheads on the basis of direct labour hours. Selling prices are then determined using cost plus...
The Gadget Co produces three products, A, B and C, all made from the same material. Until now, it has used traditional absorption costing to allocate overheads to its products. The company is now considering an activity-based costing system in the hope that it will improve profitability. Information for the three products for the last year is as follows: A B C Production and sales volumes (units) 15,000 12,000 18,000 Selling price per unit $7.50 $12 $13 Raw material usage...
Glocker Company makes three products in a single facility. These products have the following unit product costs: Products A B C Direct materials $10.90 $15.80 $8.00 Direct labour $12.50 $12.60 $9.90 Variable manufacturing overhead $2.40 $1.20 $1.40 Fixed manufacturing overhead $11.60 $7.20 $7.80 Unit product cost $37.40 $36.80 $27.10 Direct materials and direct labour are variable costs Additional data concerning these products are listed below. Products A B C Mixing minutes per unit 2.00 1.00 0.50 Selling price per unit...
1. Diamond Ltd makes 2 types of baseball bat the “Jonny Bench (JB)” and the “Mickey Mantles (MM)”. The standard costs for these items are shown below: Standard cost JB MM Price £100.00 £55.00 Variable costs Wood –maple 1.5 metres @ £3 per metre 4.50 4.50 Varnish- £12 per litre 6.00 4.00 Labour (variable) @ £15 per hour 45.00 22.50 Variable overhead based on labour hours 15.00 7.50 Total variable cost 70.50 38.50 Standard contribution £29.50 £16.50 Budgeted fixed overheads...