Please read the following scenario and answer ALL THREE questions (1-3) at the end. You are...

Please read the following scenario and answer ALL THREE questions (1-3) at the end. You are the project manager of a team of 25 people. Tom from the purchasing department has never been on one of your teams but is considered to be a procurement specialist.

During your one-on-one meeting with Tom, you inform him that you will need 100 pallets of a particularly rare and expensive raw material. You tell Tom to find the supplier with the lowest cost ASAP.  

Ten days later, you receive a panicked call from the inventory control group that 100 pallets of your rare and expensive raw materials have arrived at the dock and must be placed in storage. You are sick to your stomach, as the project budget did not plan for an early shipment, let alone for all of it to be shipped at one time. Upon investigating, you find out that Tom signed the purchased order on your behalf. Ask yourself the following as you answer the questions: Is the message clear, unclear or ambiguous? How was the message or information described by the sender? How was the information received by the receiver? Was feedback necessary on either end?

QUESTIONS:

1. What went wrong?

2. Who was at fault?

3. What could the Project Manager have done to avoid or minimize the situation?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer

✓ in the scenario, project manager didn't communicated clearly with the tom(procurement specialist), he it was ambiguous and he didn't inform Tom the time specificity to acquire the raw materials. The sender's message conveyed the urgency of finding the supplier for expensive raw material which made Tom think that manager is in need of materials. The receiver thought that manager want materials as soon as possible without asking any further information. Feedback is really necessary to make the message more clear and avoid any misunderstanding which may cost heavy later on.

1) project manager communicated to the tom about the need of raw material and to find the supplier of certain expensive raw material but, he didn't tell him till when he need to order and receive the delivede. Neither did he asked Tom, nor Tom asked further details about it. This led to the misunderstanding and early delovery of raw material without budget and storage arrangements.

2) the sender and the receiver both are at fault because of miscommunication and misunderstanding, which occurred because of not using feedback mechanism.

3) project manager would have conveyed it in a clear and unambiguous manner by stating the date of procurement and arrangements for the materials so that Tom will not be at any misunderstanding and hurry to fulfill the urgency.

Add a comment
Know the answer?
Add Answer to:
Please read the following scenario and answer ALL THREE questions (1-3) at the end. You are...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Please read the case and answer the questions at the end. Please respond to two of...

    Please read the case and answer the questions at the end. Please respond to two of your peers. Do you agree or disagree? Curt's Cowboy Corner is a chain of 15 stores that sells cowboy boots and western clothing. Curt opened the first store 10 years ago in a small Rocky Mountain town and quickly gained a following of loyal customers. Based on input from customers and friends, Curt decided to expand his business and began opening new stores in...

  • Please help me answer all 3 questions in this case. The numbers and questions asked, in...

    Please help me answer all 3 questions in this case. The numbers and questions asked, in this case, is different than the other cases similar to it, so please don't copy and past other answers from the same case. Also if you could please provide steps to how you're getting the answers, if possible show it in excel with formulas, please. Answer the following questions using the information provided above. Show all of your calculations in an Excel file. Make...

  • Please read through the article below and answer the question at the end of the article....

    Please read through the article below and answer the question at the end of the article. What Are the Project Management Knowledge Areas? PMI created a set of standard terminology and guidelines for project management, which is known as the project management knowledge areas. This is an evolving standard that is updated periodically in its PMBOK. Project management knowledge areas coincide with the process groups, which are project initiation, project planning, project execution, monitoring and controlling, and project closing. These...

  • CASE STUDY 1. Read the following scenario and answer the questions. You have scrubbed into your...

    CASE STUDY 1. Read the following scenario and answer the questions. You have scrubbed into your first case of the day. While preparing the instrument sets and supplies, you discover the following: • There is water in one of the basins that was wrapped. • A chemical indicator wrapped with a single instrument has not changed color. • There is moisture on the instruments in the set you need to prepare. • One of the hemostatic clamps has dried blood...

  • Read the mini-case, *BELOW* and answer the questions at the end: Minicase: You Can’t Make Stuff...

    Read the mini-case, *BELOW* and answer the questions at the end: Minicase: You Can’t Make Stuff Like This Up Steve once worked as a regional sales director for a large health insurance company called Blue Star Health. Blue Star Health was once quite suc- cessful but had become complacent over the past five years. Competitors gained market share using aggressive marketing and sales tactics, and Blue Star was selling antiquated products and using inefficient processes for settling claims. With falling...

  • Please answer ALL questions or I'll thumbs down, thank you! 1) The following cartoon illustrates a...

    Please answer ALL questions or I'll thumbs down, thank you! 1) The following cartoon illustrates a prototypical receptor tyrosine kinase cascade. Based on your knowledge of this pathway, answer the following questions that focus on the Ras GTPase enzyme and its downstream signaling. a) Complete the signal transduction cascade by filling in the empty boxes with the identities of the molecules. [4 pts] out wwwww yman Ras F Grb2) SOS b) In class, we discussed a few mechanisms that lead...

  • please help me answer these questions, I provided all the information. thank you You are the...

    please help me answer these questions, I provided all the information. thank you You are the financial analyst of the Management and Budgeting Oftice (MBO) for the Procurement Agency of your Municipality The Transport system of your city needs to have an extension/renovation of the existing equipment (eg vehicles, on-board Wi-Fi network, etc.) and infrastructure (e.g. binary for bus, etc). The transport system is totally owned by the municipality, hence it is in charge of investment decision and business activity...

  • Chapter 14 Read Retention: Deciding to Act and answer questions 1 through 4. Thank you. Retention: Deciding to Act Wa...

    Chapter 14 Read Retention: Deciding to Act and answer questions 1 through 4. Thank you. Retention: Deciding to Act Wally's Wonder Wash (WWW) is a full-service, high-tech, high-touch car wash company owned solely by Wally Wheelspoke. Located in a midwestern city of 200,000 people (with another 100,000 in suburbs and more rural towns throughout the county), WWW currently has four facilities within the city. Wally plans to add four more facilities within the city in the next two years, and...

  • Help needed for Project procurement to answer Questions 1-10: Building Trust   Pauly Shore is a junior...

    Help needed for Project procurement to answer Questions 1-10: Building Trust   Pauly Shore is a junior procurement manager for the Goldwell Restaurant Group. He is responsible for the procurement of IT commodities for the data center. After months of negotiating with the three best and lowest-priced bidders for the computer paper contract, Pauly selected Frankie’s Paper Company.  Pauly’s decision was made after a round of golf at Frankie’s country club. On the eighteenth hole, Frankie extended his hand to Pauly and...

  • Read the following case: Answer the questions accordingly: PLEASE MAKE COPY PASTE AVAILABLE EEOC v. Management...

    Read the following case: Answer the questions accordingly: PLEASE MAKE COPY PASTE AVAILABLE EEOC v. Management Hospitality of Racine 666 F.3d 422 (7th Cir. 2012) OPINION BY DISTRICT JUDGE YOUNG: The Equal Employment Opportunity Commission ("EEOC") brought this action on behalf of two serv- ers, Katrina Shisler and Michelle Powell, who were em- ployed at an International House of Pancakes franchise in Racine, Wisconsin (the "Racine IHOP"), alleging that the servers were sexually harassed in violation of Title VII of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT