Question

1. Big Company is evaluating two projects, Project A and Project B. Both projects are of...

1. Big Company is evaluating two projects, Project A and Project B. Both projects are of equal risk. Big Company has a WACC of 10%. The expected Free Cash Flows of the projects are as follows:

Period Project A Project B
0 (25,000) (25,000)
1 5000 20000
2 10000 10000
3 15000 8000
4 20000 6000

1. Compute the Internal Rate of Return of Project “A”.

2. The Internal Rate of Return of Project “B” is 36.15%. If Projects “A” and “B” are independent, considering only at the IRR method, which project(s) should Big Company proceed with

3. The Internal Rate of Return of Project “B” is 36.15%. If Projects “A” and “B” are mutually exclusive, considering only at the IRR method, which project(s) should Big Company proceed with?

SHOW WORK PLEASE

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1.

Let the IRR be x.

Now , Present Value of Cash Outflows=Present Value of Cash Inflows

25000 = 5000/(1.0x) +10000/ (1.0x)^2 +15000/(1.0x)^3+ 20000/(1.0x)^4      

Or x= 27.273%

Hence the IRR is 27.273%

2. When the two projects are independent, considering only at the IRR method, Project A and B would be chosen as both have a higher IRR than the Cost of capital and hence both would be beneficial.

3. When Projects “A” and “B” are mutually exclusive, considering only at the IRR method, the project with the higher IRR would be chosen. This is because in case of mutually exclusive projects, only of the projects would be chosen.

Hence the answer is Project B

Add a comment
Know the answer?
Add Answer to:
1. Big Company is evaluating two projects, Project A and Project B. Both projects are of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The Internal Rate of Return of Project “B” is 12.96%. If Projects “A” and “B” are...

    The Internal Rate of Return of Project “B” is 12.96%. If Projects “A” and “B” are independent, considering only at the IRR method, which project(s) should Big Company proceed with? Group of answer choices a. Project "A" should be chosen because its IRR is lower than Project "B" indicating a more efficient use of capital. b. Project "B" should be chosen because the IRR is higher than the IRR of Project "A" indicating that Project "B" has a higher return....

  • show the steps how to do please 3. DMC company is evaluating two projects Land S....

    show the steps how to do please 3. DMC company is evaluating two projects Land S. The projects' after-tax cash flow ($) (including depreciation) are following: Project L Projects Year 0 -7000 - 13500 Year 1 1000 0 Year 2 1500 6000 Year 3 1500 7500 Year 4 2500 8000 Year 5 2000 Year 6 3000 What is NPV, IRR, and Payback for each project if the required rate of return for capital is 10%. If the projects are mutually...

  • P Q 2 /4 m 77.1% сошрашся шгше vage, occгсаагааг Слсангни са, poposca pojects шагсапросшашу deliver...

    P Q 2 /4 m 77.1% сошрашся шгше vage, occгсаагааг Слсангни са, poposca pojects шагсапросшашу deliver the objective of the campaign. The projects benefit and cost streams are computed as follows. The discount rate for the projects is 9 %. year 5 and after* 150 Green Benefits 3000 7000 Costs 6000 20000 Benefits 4000 Clean Costs 6000 20000 12000 17000 22000 15000 5000 50000 10000 20000 10000 15000 5000 50000 1010 *This means that the payment stream of year 5...

  • Thomas Company is considering two mutually exclusive projects. The firm has a 12% cost of capital....

    Thomas Company is considering two mutually exclusive projects. The firm has a 12% cost of capital. Cash inflows Initial investment Year 1 Year 2 Year 3 Year 4 Year 5 Project A Project B $130000 $85000 $25000 $35000 $45000 $50000 $55000 $40000 $35000 $30000 $10000 $5000 Evaluate and discuss the rankings of NPV and IRR of the two projects on the basis of your finding. O A Project B should be chosen because it has a higher IRR than Project...

  •    Yong Importers, an Asian import company, is evaluating two mutually exclusive projects, A and B. The...

       Yong Importers, an Asian import company, is evaluating two mutually exclusive projects, A and B. The relevant cash flows for each project are given in the table below. The cost of capital for use in evaluating each of these equally risky projects is 10 percent. initial investment               project a                   project b                                            $350,000                  $425,000 year                                              cash inflows (cf) 1                                         140,000                  175,000 2                                         165,000                   150,000 3                                          190,000                  125,000 4                                                                         100,000 5                                                                         75,000 6                                                                         50,000 Which project should be chosen on the basis of...

  • please help a) Layang Indah Sdn Bhd is evaluating two (2) mutually exclusive projects. The cash...

    please help a) Layang Indah Sdn Bhd is evaluating two (2) mutually exclusive projects. The cash flows in RM of each project are as follows: Year Project XX (RM) Project YY (RM) 0 500.000 600.000 1 50.000 200,000 2 150,000 200,000 3 250,000 200.000 4 200.000 200.000 5 100.000 200.000 The company's required rate of return is 10%. By using the following techniques in capital budgeting, which project should the Layang Indah Sdn Bhd undertakes and why? 0 Payback period...

  • Bernie’s Restaurants is considering two mutually exclusive projects having the cash flow streams shown in the...

    Bernie’s Restaurants is considering two mutually exclusive projects having the cash flow streams shown in the table below. Compute the net present value (NPV) for both projects using a 15% required rate of return. Compute the internal rate of return (IRR) for both projects. Compute the profitability index for both projects. Which project should Bernie’s business accept and why? Bernie’s Restaurants Capital Budgeting Projects Year Project A Net Cash Flow Project B Net Cash Flow 0 -$ 90,000 -$100,000 1...

  • Bernie’s Restaurants is considering two mutually exclusive projects having the cash flow streams shown in the...

    Bernie’s Restaurants is considering two mutually exclusive projects having the cash flow streams shown in the table below. Compute the net present value (NPV) for both projects using a 15% required rate of return. Compute the internal rate of return (IRR) for both projects. Compute the profitability index for both projects. Which project should Bernie’s business accept and why? Bernie’s Restaurants Capital Budgeting Projects Year Project A Net Cash Flow Project B Net Cash Flow 0 -$ 90,000 -$100,000 1...

  • 4. Farrah Corporation is considering two projects (see below). For your analysis, assume these projects are...

    4. Farrah Corporation is considering two projects (see below). For your analysis, assume these projects are mutually exclusive with a required rate of return of 12%. Initial investment Cash inflow Year 1 Project 1 $185,000 $230,000 Project 2 $1,100,000 $1,450,000 Compute the following for each project: NPV (net present value) PI (profitability index) IRR (internal rate of return) Which project should be selected? Why?

  • Choosing Between two Mutually Exclusive Projects Question 2: A company can cither invest in project A,...

    Choosing Between two Mutually Exclusive Projects Question 2: A company can cither invest in project A, project B, or neither (the projects are mutually exclusive and the company has no other investment options). Project A requires an initial investment of $1,000,000 and provides cash flows of $300,000 a year for six years. The project will also return $200,000 in capital back to the company in year six. Project B requires a $375,000 investment and will have cash flows of $200,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT