1. Ans. d) Rolling wave planning
Rolling wave planning is planning done as the project proceeds when the underlying assumptions and risks become more clear.
2. Ans. c) Develop a WBS
Work Breakdown Structure or WBS breaks down the entire project into smaller components as manageable sections. it assigns the roles and responsibility of every individual in order to accomplish a given project or task.
3. Ans. b) Risk auditing
The processes involved in project risk management are : Identifying, Analysing, Prioritize, Ownership, Responding and Monitoring. Auditing is not a part of Project risk management.
4. Ans. c) Both positive and negative risks
Contingent response strategy is planned for emergency condition both for positive and negative risks. Response Strategy for negative risks are : Avoid, Mitigate, or Retain.
Response strategy for positive risks are : Share, Accept or Enhance.
____ Your project has several phases. One of these phases is not planned in detail and...
Early in your project a preliminary list of risks was developed. You have created a more detailed list of risks for further study. You have not scheduled a time to work through this set of risks, because key people who will help you have not yet informed you of their availability. Creating the more detailed list of risks is an output of which process? Perform Qualitative Risk Analysis Perform Quantitative Risk Analysis. Plan Risk Management Identify Risks Risk thresholds are...
A watch list is an output of which risk management process? Perform Quantitative Risk Analysis Implement Risk Responses Perform Qualitative Risk Analysis Plan Risk Responses A project has the following risks: 20 percent probability of a 14-day delay in the receipt of customer requirements; 10 percent probability of a 21 -day delay in the procurement process; 50 percent probability the integration will take 14 days longer than planned. What is the expected value of these events? 49 days Seven days...
Qualitative risks are typically categorized by a group of experts to determine the probability and the impact to project objectives. In the example below, consider the next steps that should be taken as project manager to assemble a group of experts to participate. Who would you select and why? Project Management Body of Knowledge (PMBOK) defines risks as “an uncertain event or condition, that if it occurs, has a positive or negative effect on one or more project objectives” (ProjectRiskCoach,...
B. Risk strategy C. Respanses to individual risks D. Risk categories. 192. The Perform Qualitative Risk Analysis process assesses the priority of identified risks using all af the following EXCEPT A. B. C. Relative probability or likelihoad of occurrence of identified risks. Impact an praject abjectives if the identified risks accur A mathematical technique, such as the expected monetary value (EMV), to create the impression of precision and accuracy. The organization's risk tolerance assaciated with the praject constraints of cast,...
Please read through the article below and answer the question at the end of the article. What Are the Project Management Knowledge Areas? PMI created a set of standard terminology and guidelines for project management, which is known as the project management knowledge areas. This is an evolving standard that is updated periodically in its PMBOK. Project management knowledge areas coincide with the process groups, which are project initiation, project planning, project execution, monitoring and controlling, and project closing. These...
Project risk management is an iterative process that begins with a plan for how risks will be managed throughout the life of the project. Risks must first be identified and analyzed. Then risk responses and action steps must be developed. The risk management plan should also include the steps, processes, or procedures that will be used to continually monitor risk during the project. Defining requirements for a process improvement project can be particularly challenging. Depending on the extent and complexity...
Project Management Processes Assignment Part I by answering the assigned questions. Part II by completing the matching exercise. Part III by answering true or false to the questions. Part I – Answer the following questions (30 points): 1. Why aren’t the processes groups the same as project phases? (15 points) 2. After “create WBS” on a project what would be the next five sequences to follow? (15 points) Part II – Matching Exercise (20 Points): Match column A with B: (2...
Table 1.1
Module Three covers refining your project schedule and fine-tuning resources. Table 1-1: Project Management Process Group and Knowledge Area Mapping (PMBOK Guide® on page 556) provides you with a very specific guideline concerning what task is due for each knowledge area throughout the five projec management process groups. As you can determine from Table 1-1, a large majority of the tasks are complete during the planning process group Describe and explain how sound industry standards or best practices...
(TCO D) You are the project manager for an important healthcare project. You are performing qualitative risk analysis. Below are the values of probability and impact for the top 5 negative risks that were given to you by project team. The person assigned as the risk owner did not come to work today and you will have to rank all risks, given the highest priority to high-exposure risk. The Probability and Impact Scale as discussed with the stakeholders is: Scale...
Project Description: Student groups will select an industrial project to be developed throughout the semester. Students groups will select an appropriate project and define measurable project objectives and requirements. A project plan and schedule will be generated as well as resources allocated to accomplish project objectives. Prepare a group project for the class. Use as your model one of the following Construction project Software development project Events management project ( e.g. Awards banquet) New product development Project Components: Using the...