On February 1, 2020, Oriole Contractors agreed to construct a
building at a contract price of $3,130,000. The total estimated
construction costs would be $1,555,000 and the project would be
finished in 2022. Information relating to the costs and billings
for this contract is as follows:
| 2020 | 2021 | 2022 | |||||||
| Total costs incurred to date | $ | 544,250 | $ | 903,650 | $ | 2,380,000 | |||
| Estimated costs to complete | 1,010,750 | 801,350 | -0- | ||||||
| Customer billings to date | 1,100,000 | 1,555,000 | 3,130,000 | ||||||
| Collections to date | 1,000,000 | 1,750,000 | 2,950,000 | ||||||
Calculate the gross profit / (loss) that should be recognized
for 2020, 2021, and 2022 using the percentage completion method.
(Enter negative amounts using either a negative sign
preceding the number e.g. -45 or parentheses e.g.
(45).)
| 2020 | 2021 | 2022 | ||||
| Gross profit / (loss) | $ | $ | $ |
Solution
| 2020 | 2021 | 2022 | |
| Gross profit | $ 551,250 | $ 204,000 | $ (5,250) |
Working
| Working | 2020 | 2021 | 2022 | |
| A | Contract Price | $ 3,130,000 | $ 3,130,000 | $ 3,130,000 |
| B | Cost Incurred to Date | $ 544,250 | $ 903,650 | $ 2,380,000 |
| C | Estimated cost yet to be incurred to complete the contract | $ 1,010,750 | $ 801,350 | $ 0 |
| D = B+C | Total Cost | $ 1,555,000 | $ 1,705,000 | $ 2,380,000 |
| E = (D/B) x 100 | % of Completion | 35% | 53% | 100% |
| F = A x E | Revenue to date | $ 1,095,500 | $ 1,658,900 | $ 3,130,000 |
| G | Revenue of Previous year | $ 0 | $ 1,095,500 | $ 1,658,900 |
| H = F - G | Net Revenue this year | $ 1,095,500 | $ 563,400 | $ 1,471,100 |
| I | Cost to date | $ 544,250 | $ 903,650 | $ 2,380,000 |
| J | Cost to date of previous year | $ 0 | $ 544,250 | $ 903,650 |
| K = I - J | Net Cost for the year | $ 544,250 | $ 359,400 | $ 1,476,350 |
| L = H - K | Gross Profits | $ 551,250 | $ 204,000 | -$ 5,250 |
On February 1, 2020, Oriole Contractors agreed to construct a building at a contract price of...
On February 1, 2017, Marsh Contractors agreed to construct a
building at a contract price of $5,720,000. Marsh estimated total
construction costs would be $3,936,000 and the project would be
finished in 2019. Information relating to the costs and billings
for this contract is as follows:
2017
2018
2019
Total costs incurred to date
$1,476,000
$2,592,000
$4,560,000
Estimated costs to complete
2,460,000
1,728,000
-0-
Customer billings to date
2,120,000
3,936,000
5,520,000
Collections to date
1,920,000
3,420,000
5,420,000
Fill in the...
Ex. 18-127-Percentage-of-completion and completed-contract methods. On February 1, 2012, Marsh Contractors agreed to construct a building at a contract price of $5,400,000. Marsh estimated total construction costs would be $4,000,000 and the project would be finished in 2014. Information relating to the costs and billings for this contract is as follows: 2014 2012 $1,500,000 2,500,000 2,200,000 2,000,000 2013 $4,600,000 $2,640,000 1,760,000 4,000,000 3,500,000 Total costs incurred to date Estimated costs to complete Customer billings to date Collections to date -0-...
During 2020, Oriole Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete Billings to date Collections to date 2020 $366,300 623,700 297,000 270,000 2021 $831,440 262,560 894,000 816,000 2022 $1,067,000 -0- 1,590,000 1,417,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized...
Sandhill Construction Company has entered into a non-cancellable contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $650,000 and will take three years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period. 2022 $660,000 Costs to date Estimated costs to complete Progress billings to date (non-refundable) Cash collected to date 2020 $292,500 357,500 292,500 262,500 2021 $487,500 162,500...
On March 1, 2020, Waterway Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,400,000. The building was completed by October 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below: 2020 2021 2022 Contract costs incurred during the year $2,700,600 $2,503,700 $2,125,700 Estimated costs to complete the contract at 12/31 3,729,400 2,125,700 –0– Billings...
Problem 18-11 Your answer is partially correct. Try again. On July 1, 2020, Cullumber Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,920,000. On July 1, Cullumber estimated that it would take between 2 and 3 years to complete the building. On December 31, 2022, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2020,...
During 2020, Pharoah Company started a construction job with a
contract price of $1,620,000. The job was completed in 2022. The
following information is available.
2020
2021
2022
Costs incurred to date
$373,700
$902,000
$1,070,000
Estimated costs to complete
636,300
198,000
–0–
Billings to date
303,000
899,000
1,620,000
Collections to date
273,000
807,000
1,412,000
Compute the amount of gross profit to be recognized each year,
assuming the percentage-of-completion method is used.
Gross profit recognized in 2020
$enter a dollar amountenter...
During 2020, Martinez Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $830,680 $1,074,000 Estimated costs to complete 584,100 262,320 –0– Billings to date 302,000 898,000 1,600,000 Collections to date 272,000 818,000 1,420,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 Gross profit recognized in...
During 2020, Sunland Company started a construction job with a contract price of $1.590,000. The job was completed in 2022. The following information is available Costs incurred to date Estimated costs to complete Billings to date Collections to date 2020 2021 2022 $410,000 $901,180 $1,067.000 590.000 197,820 -0- 297.000 903,000 1.590,000 271.000 805,000 1.434.000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used Gross profit recognized in 2020 $ Gross profit recognized...
During 2020, Sunland Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete 2020 2021 2022 $410,000 $901,180 $1,067,000 590,000 197,820 -0- 297,000 903,000 .590,000 271,000 805,000 1,434,000 Billings to date Collections to date ✓ Your answer is correct Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in...