Given the following bill-of-materials: One A requires 2 units of B, 3 units of C, and 1 unit of D. One B requires 1 unit of C and 1 unit of D. One C requires 1 unit of D and 2 units of E. One D requires 1 unit of F and 2 units of G. If the demand for product A is 50 units, what will be the gross requirement for component E?
In order to produce 1 unit of A, number of C required is 3
Therefore in order to produce 50 units of A, the number of C required would be 3*50
= 150
In order to produce 1 Units of A, the number of B required is 2
Therefore in order to produce 50 units if A, the number of B required as 2*50
= 100
In order to produce 1 Unit of B, the number of C required is 1
Therefore in order to produce 100 units of B, the number of C required would be 1*100
= 100
Total C required would be 150+100
= 250
In order to produce 1 Unit of C, the number of E required is 2
Therefore, in order to produce 250 Units of C, the number of E required would be 2*250
= 500
In order to produce 50 Units of A, the number of E required would be 500
1 A requires:
2 B
3 C
1 D
1 B requires:
1 C
1 D
1 C requires:
1 D
2 E
1 D requires:
1 F
2 G
(Note: E is only directly required by C.)
B:
C:
D:
C:
D:
Total C:
Total D:
D:
E:
Total D:
(Note: D requires F and G, but these do not affect E.)
Only C directly demands E, and we’ve already calculated:
E is only needed for C.
Total C required = 250 (from A and B).
Each C requires 2 E, so:
Answer: The gross requirement for component E is units
Given the following bill-of-materials: One A requires 2 units of B, 3 units of C, and...
2. The bill of materials for product A with the associated component parts and planning factors (in parenthesis) are showed below. How many units of the following components are required to make one unit of the product A? 10 points p. 195 B(2) C (3) ľITRSP-300 H o m ework #3 Fall 2018 (A) Component B (B) Component C (C) Component D (D) Component E (E) Component F (F) Component G
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...
One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time of...
One unit of A is made of one unit of B and one unit of C. B is
made of four units of C and one unit each of E and F. C is made of
two units of D and one unit of E. E is made of three units of F.
Item C has a lead time of one week; Items A, B, E, and F have
two-week lead times; and Item D has a lead time of...
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...
Product A needs 3 components of B and 2 components of C. Component B on the other hand needs 2 units of component C and E. Component C requires a unit of D, and 3 components of E. Component D on the other hand requires 5 units of E. Lead time is 2 weeks. The company expects to deliver 100 units of A on the 3rd week, 250 units on the 5th week, and 500 units on the 8th week....
One unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time...
One unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time...
Product A consists of three units of Subassembly B, three units of C, and one unit of D. B is composed of four units of E and three units of F. C is made of two units of H and two units of D. H is made of five units of E and two units of G. To produce 100 units of A, determine the numbers of units of B, C, D, E, F, G, and H required using the...