Better Products, Inc., manufactures three products on two machines. In a typical week, 40 hours are available on each machine. The profit contribution and production time in hours per unit are as follows:
| Category | Product 1 | Product 2 | Product 3 |
| Profit/unit | $36 | $58 | $19 |
| Machine 1 time/unit | 0.5 | 2.5 | 1.5 |
| Machine 2 time/unit | 1 | 1.5 | 1.5 |
Two operators are required for machine 1; thus, 2 hours of labor must be scheduled for each hour of machine 1 time. Only one operator is required for machine 2. A maximum of 90 labor-hours is available for assignment to the machines during the coming week. Other production requirements are that product 1 cannot account for more than 50% of the units produced and that product 3 must account for at least 25% of the units produced.
| Product | # of units |
|---|---|
| 1 | |
| 2 | |
| 3 |
| Product | # of units |
|---|---|
| 1 | |
| 2 | |
| 3 |
a.
Let,
xi = number of product i to produce where i = {1,2,3}
Objective is to maximize profit = Max 36P1+58P2+19P3
subject to,
2*(0.5x1+2.5x2+1.5x3)+x1+1.5x2+1.5x3 <= 90 (Labor hours)
or, 2x1+6.5x2+4.5x3 <= 90
0.5x1+2.5x2+1.5x3 <= 40 (Machine 1)
x1+1.5x2+1.5x3 <= 40 (Machine 2)
x1 <= 0.5*(x1+x2+x3) (max percentage of product 1)
or,0.5x1-0.5x2-0.5x3 <= 0
x3 >= 0.25*(x1+x2+x3) (min percentage of product 3)
or, -0.25x1-0.25x2+0.75x3 >= 0
xi >= 0 (non-negativity constraint)
Solving in solver we get,
| Product | # of units |
| 1 | 12 |
| 2 | 6 |
| 3 | 6 |
Projected weekly profit = 894
Solver screenshot

Solver formula

Solver window

Sensitivity report

b) Machine Hours Schedule: Machine 1: 30 hours; Machine 2: 30 hours
c) Value of an additional hour of labour = 9.93
d) New optimal product mix :
| Product | # of units |
| 1 | 16 |
| 2 | 8 |
| 3 | 8 |
Projected weekly profit = 1192
Yes definitely one would be interested in the additional 30 hours available for this resource as profit has increased by using the additional 30 hours

Better Products, Inc., manufactures three products on two machines. In a typical week, 40 hours are...
Use Excel/Solver add in for accurate answers.
Problem 3-19 (Algorithmic) Better Products, Inc., manufactures three products on two machines. In a typical week, 40 hours are available on each machine. The profit contribution and production time in hours per unit are as follows: Category Product 1 Product 2 Product 3 Profit/unit $39 $51 $18 Machine 1 time/unit 1.5 Machine 2 time/unit Two operators are required for machine 1; thus, 2 hours of labor must be scheduled for each hour of...
1. Better Products manufactures three products on two machines. There is $30 profit associated with Product 1, $50 profit with Product 2, and $20 profit with Product 3. Each product requires labor time using machine A and machine B. Product 1 requires 1 hour from machine A and 1 hour from machine B. Product 2 requires 4 hours from machine A and 1 hour from machine B. Product 3 requires 1.5 hours from machine A and .5 hours from machine...
Hercules Inc. manufactures elliptical exercise machines and
treadmills. The products are produced in its Fabrication and
Assembly production departments. In addition to production
activities, several other activities are required to produce the
two products. These activities and their associated activity rates
are as follows:
Activity
Activity Rate
Fabrication
$32
per machine hour
Assembly
$30
per direct labor hour
Setup
$95
per setup
Inspecting
$16
per inspection
Production scheduling
$15
per production order
Purchasing
$6
per purchase order
The activity-base usage...
Hercules Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Rate Activity Fabrication Assembly Setup Inspecting Production scheduling Purchasing $26 per machine hour $36 per direct labor hour $87 per setup $20 per inspection $19 per production order $10 per purchase order The activity-base usage...
4. A company manufactures two products, X and Y by using three machines A, B, and c Each of the products has to be processed on each machines. The Table below shows (a) the hours required on each machine to produce one unit of each of the products (b) the total number of hours available on each machine (c) the profit made on one unit of each product. It is assumed that the profit is directly proportional to the number...
Hercules Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $31 per machine hour Assembly $15 per direct labor hour Setup $50 per setup Inspecting $29 per inspection Production scheduling $16 per production order Purchasing $13 per purchase order The activity-base usage...
Hercules Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $25 per machine hour Assembly $15 per direct labor hour Setup $45 per setup Inspecting $28 per inspection Production scheduling $16 per production order Purchasing $13 per purchase order The activity-base usage...
Hercules Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $24 per machine hour Assembly $10 per direct labor hour Setup $55 per setup Inspecting $23 per inspection Production scheduling $11 per production order Purchasing $8 per purchase order The activity-base usage...
Product costs using
activity rates
Hercules Inc. manufactures elliptical exercise machines and
treadmills. The products are produced in its Fabrication and
Assembly production departments. In addition to production
activities, several other activities are required to produce the
two products. These activities and their associated activity rates
are as follows:
Activity
Activity Rate
Fabrication
$35
per machine hour
Assembly
$35
per direct labor hour
Setup
$86
per setup
Inspecting
$17
per inspection
Production scheduling
$16
per production order
Purchasing
$7
per...
Product costs using activity rates Hercules Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $30 per machine hour Assembly $39 per direct labor hour Setup $89 per setup Inspecting $20 per inspection Production scheduling $19 per production order Purchasing $10 per...