Question

The following table shows the demand forecasts and committed orders so far for a product in...

The following table shows the demand forecasts and committed orders so far for a product in the next eight weeks.
Month Forecast Committed orders
1 60 82
2 60 80
3 60 60
4 60 40
5 45 20
6 45 0
7 45 0
8 45 0
The lot size has been determined to be 80 units whenever there is scheduled production. Beginning inventory is 95 units.
Calculate the MPS and ATP for each week. If there is no MPS or ATP for a week, enter 0. No decimals.
Months MPS ATP
1
2
3
4
5
6
7
8
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Explanation

  1. Requirement = Max(Forecast,orders)
  2. Opening inventory = 95 units for period 1 and for other periods, Opening inventory = Projected on-hand inventory after production of previous periods
  3. Projected on-hand inventory without production = Opening Inventory – requirement
  4. MPS = If Projected on-hand inventory without production is less than 0, then MPS – 80 else 0
  5. Projected on-hand inventory after production = MPS+opening inventory – requirement
  6. ATP happens only when there is MPS scheduled

ATP for period 1 = Opening inventory + MPS - (Actual customer orders till we have another MPS)

ATP for other periods = MPS - (Actual customer orders till we have another MPS)

Add a comment
Know the answer?
Add Answer to:
The following table shows the demand forecasts and committed orders so far for a product in...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following table shows the demand forecasts and committed orders for a product. Month Forecast Committed...

    The following table shows the demand forecasts and committed orders for a product. Month Forecast Committed orders 1 60 80 2 60 60 3 60 40 4 60 82 5 45 20 6 45 0 7 45 0 8 45 0 The lot size has been determined to be 80 units whenever there is scheduled production. Beginning inventory is 95 units. Calculate the MPS and ATP for each week. If no MPS or ATP for a week, enter 0. No...

  • Q1. Develop a Master Production Schedule (MPS) The Forecast is 84 units for first period and...

    Q1. Develop a Master Production Schedule (MPS) The Forecast is 84 units for first period and 80 for the second period, and 60 units for each of the next three periods. The starting Inventory is 20 units. The company uses lot size of 50 units. Committed Orders are as follows: What is the available to promise? Period Customer Orders 1 82 2 82 3 58 4 40 5 20 Q2 Complete the following problem. There are 20 on hand and...

  • needing help with Excel 3. Complete the master production schedule based on the following information: 1...

    needing help with Excel 3. Complete the master production schedule based on the following information: 1 4 9 2 3 320 100 30 60 50 80 110 5 6 7 40 240 290 60 60 60 410 20 Week Forecast Customer Orders Projected On-Hand Inventory MPS Released MPS Due Available to Promise (ATP) Additional Information: On-hand inventory: 600 Schedule production whenever projected on-hand inventory drops below 30 MPS lot size: 300 Production lead time or lead time for MPS releases:...

  • Using the following MPS record, what is the MPS start for week 7? MPS Lot Size...

    Using the following MPS record, what is the MPS start for week 7? MPS Lot Size Lead Time 10 1 3 4 5 6 7 8 9 45 25 20 20 20 20 40 20 T PERIOD Quantity on Hand Forecast Customer Orders Booked 1 Projected On Hand Inventory MPS Quantity MPS Start ATP 25 20 25 5 25 8_ 30

  • Question 4 (4 points) This shows product availability: S&OP MRP Inventory forecasts MPS customer due dates...

    Question 4 (4 points) This shows product availability: S&OP MRP Inventory forecasts MPS customer due dates Question 5 (4 points) The amount of time represented by each time period in an MPS plan must be equal. True False Question 6 (4 points) ATP uses the MAX(forecast, customer orders) True False Next Page Page 1 of 7 a89

  • Prepare a master schedule given this information: It is now the end of week 1; customer...

    Prepare a master schedule given this information: It is now the end of week 1; customer orders are 25 for week 2, 16 for week 3, 11 for week 4, 8 for week 5, and 3 for week 6. Use the MPS rule of ordering production when projected on-hand inventory would be negative without production. Suppose that there are currently 64 pumps in inventory and a production lot size of 70 pumps is used. (Leave no cells blank - be...

  • Problem 1 Week 1 2 3 4 5 6 7 8 9 10 Forecast 65 70...

    Problem 1 Week 1 2 3 4 5 6 7 8 9 10 Forecast 65 70 60 65 70 65 65 60 55 40 Customer Orders 20 25 10 40 10 30 5 10 0 5 Available 100 Average PAB (w/out starting) ATP Total ATP MPS Total MPS On hand = 100 Lot size = 100 multiples Safety Stock = 25 1. Complete the MPS time-phased record above with the information as given

  • Prepare a master schedule and an available to promise table given customer orders below. MPS is...

    Prepare a master schedule and an available to promise table given customer orders below. MPS is 85 units, and the company has 150 units to begin with. Forecast for the eight-period work duration is 75 units.                 Week 1 2 3 4 5 6 7 8 Customer Order 75 85 90 48 55 72 88 90

  • complete the table and then answer the multiple-choice questions. Handwritten solutions, can be submitted as pdfs....

    complete the table and then answer the multiple-choice questions. Handwritten solutions, can be submitted as pdfs. Problem 1: MPS and ATP A partial table for end item B is provided below. Compute the MPS for item B and then the ATP values. Complete the table and then answer the multiple-choice questions: you need to complete the table to receive full credit (even if the answers to multiple-choice questions are correct). Item B Lead Time: 1 weeks Lot Size: 80 units...

  • 1. Using the information in the following table, prepare a prospective MPS and calculate the available-to-...

    1. Using the information in the following table, prepare a prospective MPS and calculate the available-to- promise (ATP) quantities on the table below. The order policy is to produce in lots your calculations on the paper to receive full or partial credits. of 100. Show all Week 4 7 50 20 8 50 10 2 5 6 Quantity on hand: 401 404040 50 95 Forecast Customer orders (booked) Projected on-hand Inventory MPS quantity Available-to-promise (ATP) 20 40 45 15 75...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT