A company budgeted $256220 of overhead costs for the current year. actual overhead costs for the year were $200380. The plant wide allocation base, machine hours, was budgeted at 48910 hours. actual machine hours were 58760. A total of 99120 units was budgeted to be produced and 98000 units were actually produced. What is the companys overhead rate for the current year?
Answer
-Note that allocation base = Machine Hours
-Calculation for answer
| A | Budgeted Overhead Cost | $256,220 |
| B | Budgeted machine hours | 48,910 |
| C = A/B | Company Overhead rate for current year | $ 5.24 per machine hour [256220 / 48910] |
A company budgeted $256220 of overhead costs for the current year. actual overhead costs for the...
Pinacle Corp. budgeted $240,550 of overhead cost for the current year. Actual overhead costs for the year were $215,420. Pinacle's plantwide allocation base, machine hours, was budgeted at 53,640 hours. Actual machine hours were 55,160. A total of 96,670 units was budgeted to be produced and 98,000 units were actually produced. Pinacle's plantwide factory overhead rate for the current year is: a. $4.48 per machine hour b. $4.02 per machine hour c. $2.23 per machine hour d. $2.49 per machine...
Pinacle Corp. budgeted $218,870 of overhead cost for the current year. Actual overhead costs for the year were $202,840. Pinacle's plantwide allocation base, machine hours, was budgeted at 46,230 hours. Actual machine hours were 48,160. A total of 105,910 units was budgeted to be produced and 98,000 units were actually produced. Pinacle's plantwide factory overhead rate for the current year is: O a $4.73 per machine hour Ob. $2.07 per machine hour Oc. $4.39 per machine hour Od. $1.92 per...
Pinacle Corp. budgeted $255,590 of overhead cost for the current year. Actual overhead costs for the year were $232,640. Pinacle's plantwide allocation base, machine hours, was budgeted at 50,170 hours. Actual machine hours were 52,360. A total of 103,940 units was budgeted to be produced and 98,000 units were actually produced. Pinacle's plantwide factory overhead rate for the current year is: a.$2.24 per machine hour b.$4.64 per machine hour c.$5.09 per machine hour d.$2.46 per machine hour
Pinnacle Corp. budgeted $258,700 of overhead cost for the current year. Actual overhead costs for the year were $240,730. Pinnacle's plantwide allocation base, machine hours, was budgeted at 54,860 hours. Actual machine hours were 55,670. A total of 108,360 units was budgeted to be produced and 98,000 units were actually produced. Pinnacle's plantwide factory overhead rate for the current year is: a. $4.39 per machine hour b. $4.72 per machine hour c. $2.39 per machine hour d. $2.22 per machine...
The options for the boxes are as followed:
Actual overhead costs
Actual qty of the allocated base used
Estimated overhead costs
Estimated of the qty allocated base used
Woodall makes handheld calculators in two models: basic and professional. Woodall estimated $1,149,500 of manufacturing overhead and 605,000 machine hours for the year. The basic model actually consumed 280,000 machine hours, and the professional model consumed 325,000 machine hours. Requirements 1. Compute the predetermined overhead allocation rate using machine hours (MHr) as...
The options for the boxes are as followed:
Actual overhead costs
Actual qty of the allocated base used
Estimated overhead costs
Estimated of the qty allocated base used
Woodall makes handheld calculators in two models: basic and professional. Woodall estimated $1,149,500 of manufacturing overhead and 605,000 machine hours for the year. The basic model actually consumed 280,000 machine hours, and the professional model consumed 325,000 machine hours. Requirements 1. Compute the predetermined overhead allocation rate using machine hours (MHr) as...
Behring Corporation applies manufacturing overhead to products on the basis of standard machine-hours. Budgeted and actual fixed manufacturing overhead costs for the most recent month appear below: Original Budget Actual Costs Fixed overhead cost: Supervision $4,680 $4,800 Utilities 6,120 5,820 Factory depreciation 21,240 20,720 Total fixed manufacturing overhead cost $32,040 $31,340 The company based its original budget on 3,600 machine-hours. The company actually worked 3,570 machine-hours during the month. The standard hours...
CutQua company expects to incur $800,000 in overhead costs this coming year- $200,000 in thee Cut and Polish department and S600,000 in the Quality Control department. Total annual direct labor costs are expected to be $160,000. The Cut and Polish department expects to use 20,000 machine hours, and the Quality Control department plans to utilize 40,000 hours of direct labor time for the year. Total available hours (capacity) are 25,000 for the Cut and Polish artment and 60,000 for the...
1)
2)
3)
4)
5)
The Botosan Factory has determined that its budgeted factory overhead budget for the year is $615,420 and budgeted direct labor hours are 473,400. If the actual direct labor hours for the period are 430,800, how much overhead would be allocated to the period? Oa, $576,841 Ob. $560,040 Oc. $476,034 Od. $677,648 Blue Ridge Marketing Inc. manufactures two products, A and B. Presently, the company uses a single plantwide factory overhead rate for allocating overhead to...
The standard variable overhead cost rate for the Gordon Company is $13.25 per unit. Budgeted fixed overhead cost is S80,000. The company budgeted 8,000 units for the current period and actually produced 4,100 finished units. What is the fixed overhead volume variance? Assume the allocation base for fixed overhead costs is the number of units expected to be produced OA. $25,675 unfavorable OB. $39,000 favorable OC. S39.000 unfavorable O D. $25,675 favorable